← Aloe Energy research
Aloe Energy research

Madagascar grid atlas

Madagascar's three separate grids (Antananarivo, Toamasina, Fianarantsoa), power plants of 5 MW and above, the lines and plants promised, and the least-cost plan. Public data.

Grows where the grid hasn’t.

    2026Network and projects expected in service by this year

    Voltage

    35132330765 kV

    Showing 50 kV and up

    Color lines by

    Background

    Choose power plants

    SmallestLargest

    Showing 5 MW to 12,000 MW (all)

    Type
    Status
    Circle size

    Move the year above to look back to 2004 or ahead to the 2030s. Tap anything on the map for details.

    More options

    Transmission today (OpenStreetMap, Nov 2026)

    Pipeline transmission

    Power plants: filled circle is operating, ring is under construction or planned, circle area shows MW.

    Constraints

    The MW label shows power actually traded or contracted; its color compares it with the rating where one is published: 80%+, 40-80%, under 40%.

    Resources

    Filters

    What is on the map

    Existing lines and substations: OpenStreetMap contributors (ODbL), extracted 8 November 2026, all power lines tagged 35 kV and above plus lines with no voltage tag. Madagascar is thinly mapped (about 550 km of lines), so much of the grid is still missing.

    Gap-fill: where a line in the World Bank 2017 Africa grid (from the World Bank AICD study) is more than 3 km from any OSM line, the missing stretch is drawn dotted with its source and year. Earlier plans: the 2014 planned network compiled by KTH from ORE, Artelia and JIRAMA data (energydata.info, CC0).

    Generation, 5 MW and above, merged without duplicates in this order: our curated register (with date histories), Global Energy Monitor's Global Integrated Power Tracker (September 2026, CC BY 4.0; TransitionZero records left out because they are non-commercial), then the WRI Global Power Plant Database (2021) and OpenStreetMap where nothing is mapped nearby. Each plant says which source it came from.

    Pipeline routes are drawn substation to substation and are indicative. Several endpoints (Ambodiroka, Lokoho, Namorona, Bevory) are only approximately known. Where no public in-service date exists, the year is our estimate and is marked as such.

    Constraints are qualitative flags from published reports, not a load-flow study.

    Towns in the search: GeoNames (CC BY 4.0), places with 1,000 or more people plus capitals and district seats.

    Map colors

    Line colors follow the Southern African Power Pool's grid map, so every Aloe Energy grid atlas reads the same way, with an extra class for 33-35 kV. The interface uses Aloe Energy's palette.

    Statistics and plans

    Grid structure: the least-cost plan (PDMC 2018) and recent press (L'Express de Madagascar, 2026). Finances and losses: JIRAMA and the IMF. Generation: IRENA. Access: Tracking SDG7 2026 and the World Bank Mission 300 compact (2025). Plan: PDMC 2018, approved in 2022.

    Comments

    Use the comment control on this page. Every pipeline project has a short tag at the bottom of its popup (for example #moma or #caculo-cabaca); quote it so the thread points at the right project. Opening the page with that tag after the address jumps straight to it.

    Deal stage and slippage

    Stages run from concept to operating in eight steps. The slippage score compares the latest in-service year with the first one found in public sources; each date links to where it was said. Our own estimates are never scored.

    Coming next

    Demand and grid-arrival layer (settlements, mines, distance to grid), then quantified constraints (interconnector limits, hosting capacity, price spreads).