Eastern Africa Power Pool grid atlas

Ethiopia, Kenya, Uganda, Rwanda and Burundi, with Tanzania and DR Congo: the grid today, every power plant of 10 MW and above, the pipeline and the EAPP master plan. Public data.

Grows where the grid hasn’t.

    2026Network and projects expected in service by this year

    Voltage

    50132330765 kV

    Showing 50 kV and up

    Color lines by

    Background

    Choose power plants

    SmallestLargest

    Showing 100 MW to 12,000 MW (all)

    Type
    Status
    Circle size

    Move the year above to look back to 2004 or ahead to the 2030s. Tap anything on the map for details.

    More options

    Transmission today (OpenStreetMap, Nov 2026)

    Pipeline transmission

    Power plants: filled circle is operating, ring is under construction or planned, circle area shows MW.

    Constraints

    Color: share of rating usable (SAPP) or in use (EAPP, dashed) under 50% 50-79% 80%+. Width: rated MW. All links on one map

    The MW label shows power actually traded or contracted; its color compares it with the rating where one is published: 80%+, 40-80%, under 40%.

    Resources

    Filters

    What is on the map

    Existing lines and substations: OpenStreetMap contributors (ODbL). Ethiopia, Kenya, Uganda, Rwanda, Burundi and the neighbors extracted 8 November 2026; Tanzania and DR Congo 4 November 2026. All power lines tagged 66 kV and above plus lines with no voltage tag. Coverage is uneven: Kenya and Uganda are mapped in detail, Ethiopia's lines often lack voltage tags.

    Gap-fill: where a line in TANESCO's 2015 network, the World Bank 2017 DRC grid or the World Bank 2017 Africa grid is more than 3 km from any OSM line, the missing stretch is drawn dotted with its source and year. These can be out of date. Line lengths are mapped segment lengths, so a double circuit counts once.

    Generation, 10 MW and above, merged without duplicates in this order: our curated register (projects we track with their date history), Global Energy Monitor's Global Integrated Power Tracker (September 2026 release, CC BY 4.0; units rolled up into one plant per status, cancelled, shelved, mothballed and retired units left out, and records GEM took from TransitionZero left out because their license is non-commercial), then the WRI Global Power Plant Database (2021), OpenStreetMap plants with a tagged capacity and the World Bank AICD inventory (about 2011), each only where nothing is already mapped nearby. Each plant says which source it came from. Each plant says which source it came from. Pipeline generation and transmission: utilities, regulators, funders (World Bank, AfDB, EU), the Nile Basin Initiative and press. Each feature links its source.

    Pipeline routes are drawn substation to substation and are indicative, not surveyed alignments. Where no public in-service date exists, the year is our estimate and is marked as such.

    Constraints are qualitative flags from published reports, not a load-flow study.

    World Bank 2017 planned lines are kept as a record of the 2017 plan: many have since been built or dropped.

    Towns in the search: GeoNames (CC BY 4.0), places with 1,000 or more people plus capitals and district seats. Distances from a town to the grid are straight-line distances to the nearest mapped line of 66 kV and above.

    Map colors

    Line colors follow the Southern African Power Pool's grid map (2021, version 2), so every Aloe Energy grid atlas reads the same way: solid for existing lines, broken for proposed ones. The interface uses Aloe Energy's palette.

    Regional statistics

    Installed capacity, peak demand and generation mix: national regulators and utilities (EPRA Kenya, Uganda's Ministry of Finance, REG and RURA Rwanda, AREEN Burundi, EEP Ethiopia), 2024-2026. Electricity access: Tracking SDG7 2026 (2024 data). Interconnector ratings and traded power: utilities, the Nile Basin Initiative, EPRA and the ITSF country assessments. EAPP has no public transfer-limit table, so the map shows traded or contracted MW against the rating.

    History and the master plan

    Looking back with the year slider, plants appear in the year they were commissioned (WRI database and the project register); plants with no known year stay faint. The transmission network is today's, because line build years are not in the open data. Master plan: EAPP Regional Power System Master Plan 2014 (executive summary). An update is under way with World Bank and IRENA support; it will replace the 2014 plan on the map when published.

    Comments

    Use the comment control on this page. Every pipeline project has a short tag at the bottom of its popup (for example #moma or #caculo-cabaca); quote it so the thread points at the right project. Opening the page with that tag after the address jumps straight to it.

    Deal stage and slippage

    Stages run from concept to operating in eight steps. The slippage score compares the latest in-service year with the first one found in public sources; each date links to where it was said. Our own estimates are never scored.

    Coming next

    Demand and grid-arrival layer (settlements, mines, distance to grid), then quantified constraints (interconnector limits, hosting capacity, price spreads).