What is on the map
Existing lines and substations: OpenStreetMap contributors (ODbL). Ethiopia, Kenya, Uganda, Rwanda, Burundi and the neighbors extracted 8 November 2026; Tanzania and DR Congo 4 November 2026. All power lines tagged 66 kV and above plus lines with no voltage tag. Coverage is uneven: Kenya and Uganda are mapped in detail, Ethiopia's lines often lack voltage tags.
Gap-fill: where a line in TANESCO's 2015 network, the World Bank 2017 DRC grid or the World Bank 2017 Africa grid is more than 3 km from any OSM line, the missing stretch is drawn dotted with its source and year. These can be out of date. Line lengths are mapped segment lengths, so a double circuit counts once.
Generation, 10 MW and above, merged without duplicates in this order: our curated register (projects we track with their date history), Global Energy Monitor's Global Integrated Power Tracker (September 2026 release, CC BY 4.0; units rolled up into one plant per status, cancelled, shelved, mothballed and retired units left out, and records GEM took from TransitionZero left out because their license is non-commercial), then the WRI Global Power Plant Database (2021), OpenStreetMap plants with a tagged capacity and the World Bank AICD inventory (about 2011), each only where nothing is already mapped nearby. Each plant says which source it came from. Each plant says which source it came from. Pipeline generation and transmission: utilities, regulators, funders (World Bank, AfDB, EU), the Nile Basin Initiative and press. Each feature links its source.
Pipeline routes are drawn substation to substation and are indicative, not surveyed alignments. Where no public in-service date exists, the year is our estimate and is marked as such.
Constraints are qualitative flags from published reports, not a load-flow study.
World Bank 2017 planned lines are kept as a record of the 2017 plan: many have since been built or dropped.
Towns in the search: GeoNames (CC BY 4.0), places with 1,000 or more people plus capitals and district seats. Distances from a town to the grid are straight-line distances to the nearest mapped line of 66 kV and above.
Map colors
Line colors follow the Southern African Power Pool's grid map (2021, version 2), so every Aloe Energy grid atlas reads the same way: solid for existing lines, broken for proposed ones. The interface uses Aloe Energy's palette.
Regional statistics
Installed capacity, peak demand and generation mix: national regulators and utilities (EPRA Kenya, Uganda's Ministry of Finance, REG and RURA Rwanda, AREEN Burundi, EEP Ethiopia), 2024-2026. Electricity access: Tracking SDG7 2026 (2024 data). Interconnector ratings and traded power: utilities, the Nile Basin Initiative, EPRA and the ITSF country assessments. EAPP has no public transfer-limit table, so the map shows traded or contracted MW against the rating.
History and the master plan
Looking back with the year slider, plants appear in the year they were commissioned (WRI database and the project register); plants with no known year stay faint. The transmission network is today's, because line build years are not in the open data. Master plan: EAPP Regional Power System Master Plan 2014 (executive summary). An update is under way with World Bank and IRENA support; it will replace the 2014 plan on the map when published.
Comments
Use the comment control on this page. Every pipeline project has a short tag at the bottom of its popup (for example #moma or #caculo-cabaca); quote it so the thread points at the right project. Opening the page with that tag after the address jumps straight to it.
Deal stage and slippage
Stages run from concept to operating in eight steps. The slippage score compares the latest in-service year with the first one found in public sources; each date links to where it was said. Our own estimates are never scored.
Coming next
Demand and grid-arrival layer (settlements, mines, distance to grid), then quantified constraints (interconnector limits, hosting capacity, price spreads).