Power prices in Africa
What electricity costs, from every angle: 64 signed or awarded deals by source in 23 countries, the Southern African Power Pool's day-ahead, intraday and forward markets, what it costs to build and run each kind of plant, how prices and fuel costs have moved, and a calculator that shows which plant is cheapest for the hours it runs. Every figure links to where it was published.
Every deal, by technology
Each dot is one deal: what the buyer agreed to pay the seller per megawatt-hour, in the year it was agreed. A line through a dot shows the range when a tender had several winners. Rows are ordered by the typical (median) deal. The scale is logarithmic so the cheapest solar and the dearest diesel fit on one chart.
Prices are what was published at award or signing. Many escalate with inflation or move with fuel prices, and some deals never reached operation; the status of each is in the table below.
Coal against the rest, in short
- New coal sold at US$59-130 per MWh. South Africa's private coal bids (2016) came in near US$60, Kenya's Lamu plant signed at about US$75 (its tender assumed coal at US$50 a tonne), and Morocco's Safi bid about US$130 including fuel. Of these, only Safi and Zimbabwe's public Hwange expansion were built.
- Solar and wind auctions now sell well below coal. Solar PV tenders cleared at US$20-50 per MWh in Egypt, Ethiopia, Senegal, Côte d'Ivoire, Tunisia and South Africa; wind at US$24-30 in Egypt and about US$33 in South Africa's 2021 round.
- Firm power costs more. Dispatchable bids (gas, solar with batteries) in South Africa's 2021 risk mitigation round averaged about US$106 per MWh; battery storage there bid US$100-140 per MWh of stored energy in 2025.
- Old hydro is the cheapest power in the table (under US$20 per MWh in Uganda), while new large hydro sells at about US$40-85.
- Shortage power is the most expensive: US$170-260 per MWh for Zambia's 2024 imports and diesel, US$230 for Kenya's dearest oil plants and US$500 for rented diesel in Malawi.
All 64 deals
Original price as published, US$ per MWh in the year of the deal, and in 2025 dollars. Click a heading to sort. Download: CSV (CC BY 4.0). Deals at plants we map are also pinned on the grid atlases: switch on "Signed power prices" on the Africa, SAPP or EAPP atlas.
Show the table
| Pool | Country | Source | Deal | Type | Year | Status | As published | US$/MWh | 2025 US$ | Where it was published |
|---|---|---|---|---|---|---|---|---|---|---|
| SAPP | Malawi | Diesel and fuel oil | Rented diesel generation bought by ESCOM | Emergency purchase | 2021 | phased out | 500 USD/MWh | 500 | 594 | The Nation via CONREMA: ESCOM paid about US$0.50/kWh for rented diesel from Aggreko and EGENCO, against 8 US c for JCM solar Press or analysis About US$0.50/kWh as reported (c. 2021); compared with the 8 US c/kWh Salima solar PPA |
| SAPP | Malawi | Solar PV | Salima 60 MW solar PPA with ESCOM (MERA-approved) | Auction | 2018 | operating | 80 USD/MWh | 80 | 103 | The Nation via CONREMA (Aug 2021): MERA confirms the 8 US c/kWh tariff agreed between ESCOM and JCM and approved by MERA Reported from an official source Tender bid range 8.259-9.235 US c/kWh (2017, Africa Energy); MERA-approved PPA 8 US c; versus about 50 US c for rented diesel |
| SAPP | South Africa | Battery storage | BESIPPPP bid window 3 (5 preferred bidders) | Auction | 2025 | preferred bidders | 1,801-2,478 ZAR/MWh | 120 101-139 | 120 | Department of Electricity and Energy, BESIPPPP BW3 preferred bidders (30 May 2025) Official document Evaluation price R/MWh for 4-hour storage; average 40% below BW1 and 8% below BW2 |
| SAPP | South Africa | Coal | Coal Baseload IPP programme bid window 1 - Thabametsi (557 MW) | Auction | 2016 | awarded; did not proceed | 60.2 USD/MWh | 60.2 | 80.8 | ENR, South Africa approves two new coal-fired power plants (Oct 2016) Reported from an official source Also: SAnews (government news agency): bids well below the 82c/kWh qualification price (10 Oct 2016) First-year price; evaluation price US$75.41/MWh; qualification price 82c/kWh escalating with CPI (SAnews 10 Oct 2016) |
| SAPP | South Africa | Coal | Coal Baseload IPP programme bid window 1 - Khanyisa (306 MW) | Auction | 2016 | awarded; did not proceed | 59.3 USD/MWh | 59.3 | 79.5 | ENR, South Africa approves two new coal-fired power plants (Oct 2016) Reported from an official source Also: SAnews (government news agency): bids well below the 82c/kWh qualification price (10 Oct 2016) First-year price; evaluation price US$75.77/MWh |
| SAPP | South Africa | Coal | Medupi (public coal) - estimated lifetime cost | Lifetime cost estimate (not a contract) | 2016 | operating | 1,050 ZAR/MWh | 68.5 | 91.9 | Daily Maverick (C. Yelland), Understanding the cost of electricity from Medupi, Kusile and IPPs, 22 Jul 2016 Press or analysis LCOE in May 2016 rand, 8% real WACC, 30 years, 85% load factor; not a contract price |
| SAPP | South Africa | Coal | Kusile (public coal) - estimated lifetime cost | Lifetime cost estimate (not a contract) | 2016 | operating | 1,190 ZAR/MWh | 77.7 | 104 | Daily Maverick (C. Yelland), Understanding the cost of electricity from Medupi, Kusile and IPPs, 22 Jul 2016 Press or analysis LCOE in May 2016 rand; not a contract price |
| SAPP | South Africa | Gas | RMIPPPP - floating gas power (3 Karpowership projects) | Auction | 2021 | preferred bidders; not built | 1,550 ZAR/MWh | 105 99.3-114 | 124 | Engineering News, RMIPPPP update (11 Jun 2021) Reported from an official source Also: DMRE ministerial briefing, 18 Mar 2021 (official range R1,468-1,885/MWh) Evaluation prices incl. fuel forecast; dispatchable 05:00-21:30; mid = average of the three per Futuregrowth |
| SAPP | South Africa | Mixed dispatchable bids | RMIPPPP - all 8 preferred bidders (weighted average) | Auction | 2021 | mixed | 1,575 ZAR/MWh | 106 99.3-128 | 126 | Department of Mineral Resources and Energy, Minister Mantashe media briefing announcing RMIPPPP preferred bidders (18 Mar 2021) Official document Official range R1,468-1,885/MWh, weighted average R1,575/MWh, 1,845 MW across 8 bids (gas, hybrid and storage). Engineering News reported the ACWA Power DAO hybrid at R1,460/MWh. |
| SAPP | South Africa | Solar PV | REIPPPP bid window 5 solar PV (weighted average) | Auction | 2021 | awarded; partly built | 429 ZAR/MWh | 29 | 34.5 | Engineering News, REIPPPP Bid Window 5 update (5 Nov 2021); CSIR via Engineering News 12 Nov 2021 Reported from an official source Weighted average 42.9c/kWh; cheapest 37.4c/kWh; Figures announced by Minister Mantashe at the 28 Oct 2021 briefing. |
| SAPP | South Africa | Solar PV | REIPPPP bid window 7 solar PV (first 8 preferred bidders) | Auction | 2024 | preferred bidders | 461 ZAR/MWh | 25.2 23-26.9 | 25.9 | Department of Electricity and Energy, REIPPPP Bid Window 7 list of successful bidders (Dec 2024) Official document Range of bid prices; mid is the simple mean used in Aloe's carbon finance report |
| SAPP | South Africa | Wind | REIPPPP bid window 5 wind (weighted average) | Auction | 2021 | awarded; partly built | 495 ZAR/MWh | 33.5 | 39.8 | Engineering News, REIPPPP Bid Window 5 update (5 Nov 2021); CSIR via Engineering News 12 Nov 2021 Reported from an official source Weighted average 49.5c/kWh; cheapest 34.4c/kWh; Figures announced by Minister Mantashe at the 28 Oct 2021 briefing. |
| SAPP | Zambia | Diesel and fuel oil | Emergency inland diesel generation (2024 drought) | Emergency purchase | 2024 | planned | 260 USD/MWh | 260 | 267 | ZESCO emergency tariff application to ERB, July 2024 (p.6) Official document 26.00 US c/kWh |
| SAPP | Zambia | Gas | Emergency supply via Mozambique (floating gas power) (2024 drought) | Emergency purchase | 2024 | contracted | 220 USD/MWh | 220 | 226 | ZESCO emergency tariff application to ERB, July 2024 (p.6) Official document 22.00 US c/kWh; supplied through EDM from a powership |
| SAPP | Zambia | Imports across a border | Emergency imports from South Africa (2024 drought) | Emergency purchase | 2024 | contracted | 170 USD/MWh | 170 | 174 | ZESCO emergency tariff application to ERB, July 2024 (p.6) Official document 17.00 US c/kWh |
| SAPP | Zambia | Solar PV | Scaling Solar Zambia round 1 (two projects) | Auction | 2016 | operating | 60.1-78.4 USD/MWh | 69.2 60.1-78.4 | 92.8 | IFC, Scaling Solar Zambia PPP story (6.015 US c/kWh, 25-year fixed) Official document Also: IFC press release, winners confirmed, Lusaka 13 Jun 2016 (6.02 and 7.84 US c/kWh) Neoen/First Solar 6.015 US c/kWh (45 MW), Enel 7.84 US c/kWh (28 MW); fixed 25 years |
| SAPP | Zambia | Solar PV | GET FiT Zambia solar round 1 (weighted average) | Auction | 2019 | awarded | 44.1 USD/MWh | 44.1 | 55.5 | Multiconsult (GET FiT Zambia tender agent), record-breaking utility-scale solar PV tender in Zambia (Apr 2019) Official document Weighted average 4.41 US c/kWh; same figure used in Aloe's carbon finance report; Lowest award 3.999 US c/kWh (Bulemu East and West). |
| SAPP | Zambia | Solar PV | 100 MW solar IPP in Southern Province (20-year PPA with ZESCO) | Negotiated PPA | 2026 | operating | 78 USD/MWh | 78 | 78 | pv magazine, Zambia commissions 100 MW solar project (24 Sep 2026) Press or analysis US$0.078/kWh |
| SAPP | Zimbabwe | Coal | Hwange units 7 and 8 (600 MW public coal) - tariff approved by ZERA for the PPA with ZETDC | Regulated or public-plant tariff | 2018 | operating | 110 USD/MWh | 110 | 141 | The Herald (Zimbabwe), Sino-Hydro and ZESA deal settled, quoting ZETDC MD Julian Chinembiri Reported from an official source Also: Proximo, Sino Hydro inks PPA for 600 MW Hwange expansion (regulator approved 11 US c/kWh) 11 US c/kWh approved by ZERA when the PPA was concluded, before financial close (c. 2017-18); in 2022 ZESA said Hwange 7-8 power would come in at 10.7 US c/kWh |
| SAPP | Zimbabwe | Solar PV | Capped tariff for new solar IPPs under the government support agreement | Feed-in tariff or cap | 2024 | policy cap | up to 90 USD/MWh | up to 90 | 92.4 | The Herald (Zimbabwe), 10 new IPPs to generate 271MW (4 Mar 2024) Press or analysis Cap of 9 US c/kWh regardless of size; previous level 12 US c/kWh |
| EAPP | Djibouti | Imports across a border | Ethiopia exports to Djibouti | Import contract | 2022 | operating | 65 USD/MWh | 65 60-70 | 71.5 | The Reporter (Ethiopia), With surplus power, Ethiopia exports more (2022) Reported from an official source Between 6 and 7 US c/kWh |
| EAPP | Egypt | Solar PV | Feed-in tariff round 1 (20-50 MW solar) | Feed-in tariff or cap | 2014 | mostly not built | 143 USD/MWh | 143 | 195 | IEA/IRENA Policies database, Egypt feed-in tariff for wind and solar PV (Sep 2014) Reported from an official source Also: Prime Minister Decree No. 1947 of 2014 on feed-in tariffs (FAOLEX) 20-50 MW solar: 102.5 piasters (14.34 US c/kWh); 0.5-20 MW: 13.6 US c. Round 2 (2016) cut to 8.4 US c. |
| EAPP | Egypt | Solar PV | Kom Ombo 200 MW solar (EETC tender) | Auction | 2019 | operating | 24.7 USD/MWh | 24.7 | 31.1 | ACWA Power, Kom Ombo PV project page (2.47 US c/kWh; PPA with the Government of Egypt) Official document Lowest tariff contracted to date for solar in North Africa per the developer; earlier press gave 2.48 US c/kWh at award |
| EAPP | Egypt | Solar PV | Abydos 500 MW solar (bilateral PPA with EETC) | Negotiated PPA | 2022 | operating | 20 USD/MWh | 20 | 22 | IFC press release via pv magazine, IFC and partners invest $1.1 billion (2022) Official document 2 US c/kWh |
| EAPP | Egypt | Wind | Amunet 500 MW wind (Gulf of Suez) | Negotiated PPA | 2022 | operating | 30 USD/MWh | 30 | 33 | IFC press release via pv magazine (2022) Official document 3 US c/kWh |
| EAPP | Egypt | Wind | 2 GW Red Sea wind (ACWA Power PPA) | Negotiated PPA | 2025 | signed | 24 USD/MWh | 24 | 24 | Zawya / Asharq Business, Egypt to buy electricity from Red Sea wind farm at 2.4 cents/kWh Press or analysis 2.4 US c/kWh |
| EAPP | Ethiopia | Solar PV | Scaling Solar Ethiopia round 1 (Gad and Dicheto; 250 MW) | Auction | 2019 | signed | 25.3 USD/MWh | 25.3 | 31.9 | ACWA Power, PPA signing with Ethiopian Electric Power for Gad and Dicheto (22 Dec 2019) Official document Also: The Reporter (Ethiopia), citing the Ministry of Finance: 2.5260 US c/kWh 2.526 US c/kWh over 20 years |
| EAPP | Kenya | Coal | Lamu coal plant (1050 MW) PPA with Kenya Power | Negotiated PPA | 2017 | cancelled | 75.2 USD/MWh | 75.2 | 98.8 | Business Daily via swara.co.ke, ERC approves Lamu coal plant (Feb 2017): PPA price KES 7.7 (7.52 US c)/kWh Reported from an official source PPA with Kenya Power at 7.52 US c/kWh; the tender tariff was 7.81 US c at an assumed US$50/t coal; IEEFA estimated far higher real costs; plant cancelled |
| EAPP | Kenya | Diesel and fuel oil | Thermal (oil-fired) IPPs - highest tariffs | Negotiated PPA | 2026 | operating | up to 230 USD/MWh | up to 230 | 230 | African Business, Why Kenya is buying more electricity from Ethiopia (Jun 2026) Press or analysis Up to US$0.23/kWh |
| EAPP | Kenya | Geothermal | Feed-in tariff for geothermal 35-70 MW (2012 revision) | Feed-in tariff or cap | 2012 | policy (replaced by auctions) | 88 USD/MWh | 88 | 123 | IEA Policies database, 2nd revision of feed-in tariffs for renewable energy (Kenya) Reported from an official source 8.8 US c/kWh; wind 10.1-50 MW 11 US c; small hydro 8.25 US c |
| EAPP | Kenya | Geothermal | KenGen (public) geothermal tariff | Regulated or public-plant tariff | 2025 | operating | 8,240 KES/MWh | 63.7 | 63.7 | SolarQuarter, Kenya moves to procure 1112 MW as Parliament lifts PPA freeze (22 Nov 2025), citing parliamentary debate Reported from an official source KSh 8.24/kWh |
| EAPP | Kenya | Geothermal | Private geothermal IPPs (highest legacy PPA) | Negotiated PPA | 2025 | operating | up to 17,280 KES/MWh | up to 134 | 134 | SolarQuarter (22 Nov 2025), citing parliamentary debate Reported from an official source Up to KSh 17.28/kWh; MPs proposed a 7 US c/kWh cap on new PPAs |
| EAPP | Kenya | Imports across a border | Kenya Power imports from Ethiopia (2022 PPA) | Import contract | 2022 | operating | 65 USD/MWh | 65 | 71.5 | The EastAfrican, Kenya injects first dispatch of Ethiopia power (2022) Reported from an official source 6.5 US c/kWh for first years; renegotiation clause |
| EAPP | Kenya | Imports across a border | Kenya Power imports from Ethiopia (July 2026 supply agreement) | Import contract | 2026 | operating | 155 USD/MWh | 155 | 155 | Capital Ethiopia, Kenya Power to pay 15.5 cents per kWh (10 Jul 2026) Reported from an official source Plus a monthly demand charge; up to 400 MW |
| EAPP | Kenya | Wind | Lake Turkana wind (310 MW) PPA with Kenya Power | Negotiated PPA | 2011 | operating | 75.2 EUR/MWh | 105 | 150 | National Assembly of Kenya, Public Investments Committee report on the Auditor-General special audit of Lake Turkana Wind Power Official document Euro cents 7.52/kWh for the 20-year PPA (agreed 2011). Press reports give step tariffs of 8.53 then 7.68 euro cents and billing near 9.2 euro cents after indexation. |
| EAPP | Rwanda | Gas | Lake Kivu methane-to-power - first plant (26 MW) | Negotiated PPA | 2011 | operating | 120 USD/MWh | 120 | 172 | The EastAfrican (12 Dec 2015), quoting Infrastructure Minister James Musoni Reported from an official source 0.12 US$/kWh; second plant (56 MW) agreed 0.098 US$/kWh |
| EAPP | Rwanda | Gas | Lake Kivu methane-to-power - second plant (56 MW) | Negotiated PPA | 2015 | operating | 98 USD/MWh | 98 | 133 | The EastAfrican (12 Dec 2015), quoting Infrastructure Minister James Musoni Reported from an official source 0.098 US$/kWh |
| EAPP | Uganda | Hydro | Karuma hydro (600 MW) generation tariff years 1-10 | Regulated or public-plant tariff | 2017 | operating | 49.7 USD/MWh | 49.7 | 65.3 | Daily Monitor op-ed citing ERA/UEGCL tariffs; Business Focus (Feb 2026) quoting ERA Reported from an official source Also: Uganda Standard, Karuma tariff according to ERA (4.97 / 2.7 / 1.17 US c) Falls to 2.7 US c years 11-15 and 1.17 US c after year 15; public plant |
| EAPP | Uganda | Hydro | Isimba hydro (183 MW) generation tariff years 1-15 | Regulated or public-plant tariff | 2019 | operating | 41.6 USD/MWh | 41.6 | 52.4 | The Independent (Uganda), implications of Isimba for end-user tariffs (2019) Reported from an official source Also: Business Focus (URN), ERA source: Isimba 4.1 then 1.01 US c Falls to 1.01 US c/kWh after year 15 |
| EAPP | Uganda | Hydro | Bujagali hydro (250 MW IPP) after 2018 refinancing | Negotiated PPA | 2020 | operating | 83 USD/MWh | 83 | 103 | The Observer (Uganda), President's statement on plant costs Reported from an official source Was 13.8 US c/kWh before refinancing |
| EAPP | Uganda | Hydro | Kiira-Nalubaale hydro (Eskom Uganda concession) | Regulated or public-plant tariff | 2022 | operating | 13.1 USD/MWh | 13.1 | 14.4 | Eskom Uganda 2023 tariff application presentation Official document 1.31 US c/kWh in 2022 (1.75 in 2021); old, fully depreciated plant |
| WAPP | Burkina Faso | Solar PV | Urbasolar 30 MW solar - PPA with SONABEL | Negotiated PPA | 2020 | signed | 48,000 XOF/MWh | 83.4 | 104 | PV Tech, ground broken on AMEA's Togo PV project; Urbasolar plans 30 MW in Burkina Faso (2020) Press or analysis CFA 48/kWh, against CFA 130/kWh for thermal power |
| WAPP | Côte d'Ivoire | Solar PV | Scaling Solar Côte d'Ivoire - Laboa (36 MWac) and Touba (44 MWac) | Auction | 2025 | awarded | 32.1-33.1 EUR/MWh | 36.8 36.3-37.4 | 36.8 | IFC press release, winning bidder announced to provide solar power at record low rates in Côte d'Ivoire (7 Aug 2025) Official document Also: IFC project disclosure SS CdI (46370) EUR 0.03310/kWh Laboa, EUR 0.03213/kWh Touba; Infinity Power (Infinity and Masdar); 25-year concessions |
| WAPP | Ghana | Gas | Renegotiated thermal IPP tariffs (2025) | Negotiated PPA | 2025 | operating | up to 100 USD/MWh | up to 100 | 100 | Graphic Online (2025), quoting the Ministry of Finance Reported from an official source Reduced from 13-15 US c to below 10 US c/kWh |
| WAPP | Ghana | Renewables (mixed) | Renegotiated renewable IPP tariffs (2025) | Negotiated PPA | 2025 | operating | 65 USD/MWh | 65 | 65 | Graphic Online, Govt targets 100% monthly payments to IPPs (2025), quoting the Ministry of Finance Reported from an official source Reduced from about 18 US c to about 6.5 US c/kWh |
| WAPP | Mali | Solar PV | Phanes Energy Mali solar IPP - PPA with EDM-SA | Negotiated PPA | 2020 | signed | 55,000 XOF/MWh | 95.6 | 119 | Financial Afrik (23 Dec 2020), quoting the Phanes Group at the EDM-SA PPA signing Reported from an official source 55 FCFA/kWh against about 200 FCFA/kWh that EDM pays for rented generators; PPA signed 25 Nov 2020 |
| WAPP | Nigeria | Solar PV | 14 solar IPP PPAs with the bulk trader NBET | Negotiated PPA | 2016 | mostly not built | 115 USD/MWh | 115 75-115 | 154 | ThisDay, FG approves entry price for proposed solar plants (26 Jul 2016), quoting NBET Reported from an official source 11.5 US c/kWh signed; government later sought 7.5 US c/kWh |
| WAPP | Senegal | Gas | Cap des Biches combined cycle (West African Energy) - announced price | Negotiated PPA | 2020 | operating | 46,000-56,900 XOF/MWh | 89.5 80-98.9 | 111 | Orishas Finance, on the West African Energy plant (2020) Press or analysis 56.9 FCFA/kWh on naphtha, 46 FCFA/kWh on gas; PPA terms not published |
| WAPP | Senegal | Solar PV | Scaling Solar Senegal (Kael and Kahone; 60 MW) | Auction | 2018 | operating | 38-39.8 EUR/MWh | 45.9 44.8-47 | 58.8 | IFC Senegal Scaling Solar PPP brief (2021); ECREEE Scaling Solar experience in Senegal Official document 3.8016 and 3.9831 euro c/kWh (24.94 and 26.13 FCFA/kWh); +1.2%/yr; earlier Senegal solar about 10 euro c |
| WAPP | Sierra Leone | Diesel and fuel oil | Karpowership floating plant for Freetown (renegotiated contract) | Emergency purchase | 2018 | signed | 164 USD/MWh | 164 | 210 | AYV News, quoting the Minister of Energy on the renegotiated Karpowership agreement (2018) Reported from an official source Also: Karpowership, Sierra Leone project page (contract with EDSA, MoE and MoF, June 2018) Cut to 16.4 US c/kWh from 19.596 US c/kWh; later 2020 contract terms not public |
| CAPP | Cameroon | Diesel and fuel oil | Diesel plants on isolated grids (production cost) | Regulated or public-plant tariff | 2022 | operating | 200,000 XAF/MWh | 321 | 353 | Ecomatin citing the Ministry of Water and Energy (MINEE) Reported from an official source About 200 FCFA/kWh (Bertoua, Maroua, Banyo, Yoko) |
| CAPP | Cameroon | Hydro | Nachtigal hydro (420 MW IPP) PPA with ENEO | Negotiated PPA | 2018 | operating | 61 EUR/MWh | 71.9 | 92.2 | MIGA, guarantees for Nachtigal Hydropower (2018) Official document EUR 0.061/kWh; French Treasury gives 6.2 euro c |
| CAPP | Cameroon | Hydro | Memve'ele hydro (public) energy price in ENEO's 2024 revenue decision | Regulated or public-plant tariff | 2024 | operating | 43,270 XAF/MWh | 71.4 | 73.3 | ARSEL, tariff decision on ENEO's 2024 allowed revenue Official document 43.27 FCFA/kWh |
| CAPP | Chad | Solar PV | Djermaya solar IPP, phase 1 (32 MWp) PPA with SNE | Negotiated PPA | 2018 | signed | 79,000 XAF/MWh | 142 | 182 | African Development Bank, Djermaya solar PV partial risk guarantee summary (as disclosed; copy on the Early Warning System) Official document Also: InfraCo Africa, PPA signed for the 60 MWp Djermaya Solar project (9 Aug 2018) Initial tariff XAF 79/kWh under a 25-year PPA; 4 MWh battery in phase 1; Chad relies mainly on HFO and diesel |
| CAPP | Gabon | Hydro | Kinguélé Aval run-of-river hydro (34-35 MW) - concession and 30-year PPA with SEEG | Negotiated PPA | 2019 | signed | 40 EUR/MWh | 44.8 | 56.4 | Meridiam press release, Kinguélé hydropower concession contract signed in Gabon (24 Oct 2019) Reported from an official source The developer describes its Gabon hydro tariffs as about 4 euro cents/kWh, without a project-by-project figure; take-or-pay PPA |
| COMELEC | Algeria | Solar PV | Sonelgaz 2 GW solar tender (8 packages) | Auction | 2024 | under construction | 7,382 DZD/MWh | 55 | 56.4 | MEED, Algeria jumpstarts renewables programme (8 Jul 2024) Press or analysis Average AD 7.382/kWh (about 5.4 US c) |
| COMELEC | Morocco | Coal | Safi coal IPP (1386 MW) - winning levelized bid | Auction | 2012 | operating | 130 USD/MWh | 130 | 182 | MEED, First-ranked bidder named for Moroccan power plant Press or analysis MAD 1053/MWh (about US$130/MWh) incl. fuel at the time; 30-year PPA with ONEE |
| COMELEC | Morocco | Concentrated solar (CSP) | Noor Ouarzazate I (CSP with 3 h storage) | Auction | 2012 | operating | 1,620 MAD/MWh | 189 | 265 | Masen, Noor Ouarzazate I project page (price of kWh 1.62 dh) Official document Also: World Bank/ESMAP: tariff projected at US$0.19/kWh MAD 1.62/kWh (about US$189/MWh) |
| COMELEC | Morocco | Concentrated solar (CSP) | Noor Ouarzazate III (CSP tower with 7 h storage) | Auction | 2015 | operating | 1,420 MAD/MWh | 139 | 189 | NREL SolarPACES database, NOOR III Reported from an official source MAD 1.42/kWh |
| COMELEC | Morocco | Solar PV | Noor PV I (Ouarzazate IV - Laayoune - Boujdour; 170 MW) | Auction | 2016 | operating | 460 MAD/MWh | 44.8 | 60.1 | RenewEconomy, quoting Masen: combined rate of the three Noor PV I projects 0.46 dirhams/kWh Reported from an official source MAD 0.46/kWh |
| COMELEC | Morocco | Solar with storage | Noor Midelt II (400 MW PV with battery) - bids | Auction | 2025 | awarded | 324 MAD/MWh | 34.7 34.6-36.4 | 34.7 | MEED, Acwa Power submits Noor Midelt 2 and 3 winning bids (2025) Press or analysis Levelized tariffs bid MAD 0.3233-0.3398/kWh; ACWA's MAD 0.3245 won (offered free battery cycles); battery about 5% of tariff |
| COMELEC | Tunisia | Solar PV | 2019 tender (500 MW; 5 projects) | Auction | 2019 | partly built | 71.8-97.9 TND/MWh | 29 24.5-33.5 | 36.5 | Enerdata, Tunisia's STEG awards solar capacity (Dec 2019); Kapitalis via pv magazine Reported from an official source 2.44-2.86 US c/kWh as reported at award; Prices from the Ministry of Industry tender results (adviser Mehdi Majoul). |
| COMELEC | Tunisia | Solar PV | 2024 tender (first phase of 1.7 GW; 4 projects) | Auction | 2024 | awarded | 98-124 TND/MWh | 35.7 31.5-39.9 | 36.6 | PFI, Scatec/Aeolus sign Sidi Bouzid II PPA Press or analysis TND 0.098-0.124/kWh |
| COMELEC | Tunisia | Solar PV | Authorization regime round 6 (small plants up to 10 MW) | Feed-in tariff or cap | 2026 | approved | 142-217 TND/MWh | 59.9 47.4-72.4 | 59.9 | pv magazine, Tunisia allocates 455 MW of PV in sixth licensing round (7 Sep 2026) Reported from an official source TND 0.142/kWh (2-10 MW) to 0.217/kWh (up to 1 MW) |
How the numbers were put together
- What counts. Prices a buyer agreed to pay a seller: auction results, signed PPAs, feed-in tariffs and caps, cross-border import contracts, tariffs set for public plants, and emergency purchases. Two lifetime cost estimates for South Africa's public coal plants are included and marked, because public coal has no contract price.
- Sources. Regulators, ministries, utilities and power pools first, then development finance institutions and the companies that signed the contract, then reporting that quotes a named official. Every row links to its source and is tagged: 20 rows come from an official, development-bank or contract-party document, 31 are reported from a named official source, and 13 rest on press or analysis alone.
- Currencies. Prices in rand, dirham, euro, dinar and shilling are converted at the IRS yearly average rate for the year of the deal; CFA francs through the fixed euro peg. US dollar prices are used as published.
- 2025 dollars. Adjusted with the US consumer price index (BLS CPI-U annual averages). Deals from 2026 are shown as signed.
- Limits. Many PPAs are not public, so coverage is uneven: no published deal prices were found for Angola, Botswana, DR Congo, Mozambique, Tanzania or Mauritania, and West and Central Africa have far fewer published prices than the east and south. Prices are not like-for-like: some include fuel, some escalate, some are paid in local currency, and firm power is worth more than daytime solar.
What power sells for on the market
Only the Southern African Power Pool runs a regional market with published prices. Its day-ahead price rose with the 2024-2025 drought and has since fallen by about two thirds, below most of the new coal and gas contracts in the table above.
Price by time of day
SAPP prices each day in three blocks: peak, standard and off-peak hours. In Jun 2026 the day-ahead price was 9.7 US cents per kWh at peak, 4.7 in standard hours and 4.4 off-peak. The weekly forward market, where members fix a price for the coming week, cleared at 9.3, 6.8 and 4.7, and the intraday market, which settles changes on the day itself, at 14.5, 7.1 and 5.8.
Gaps are months where SAPP's report gives no figure for that block or no trades matched. The weekly forward market only began matching trades in July 2025.
How much is traded
In Jun 2026 members traded 97.4 GWh day-ahead, 16.6 GWh in weekly forwards, 13.1 GWh in monthly forwards and 7.4 GWh intraday. The monthly forward market has traded every month since Sep 2025, but SAPP's reports do not publish its price. The balancing market receives bids every month but no order has been activated since it opened in April 2022.
Sources for the market figures
- SAPP Market Performance Report, April 2026
- SAPP Market Performance Report, August 2025
- SAPP Market Performance Report, February 2025
- SAPP Market Performance Report, January 2026
- SAPP Market Performance Report, June 2026
- SAPP Market Performance Report, March 2025
- SAPP Market Performance Report, May 2025
- SAPP Market Performance Report, May 2026
- SAPP Market Performance Report, November 2025
- SAPP Market Performance Report, October 2025
Figures are as printed in each report. Where a report's labels conflict, we note it in the data file. Some blocks are missing for some months because the report gives only the change, not the level.
The other power pools
SAPP
Day-ahead, intraday, forward and balancing markets, with prices published every month. Most energy still moves under bilateral contracts.
EAPP
A day-ahead platform has been tested but formal trading had not started by September 2026. Trade is bilateral: Kenya paid Ethiopia 6.5 US cents per kWh from 2022 and about 15.5 cents under the July 2026 agreement.
WAPP
The regional electricity market is due to launch in 2026; rules and the regional transmission tariff were adopted in 2025-2026. Imports already cut costs: Guinea's hydro took Guinea-Bissau's supply cost from 25 to 11 US cents per kWh.
CAPP
No regional market or published cross-border prices.
COMELEC
No regional market. Morocco trades with Spain, where the day-ahead price averaged about 65 euros per MWh (about US$74) in 2025.
What utilities pay on average (cost of supply)
A deal price is what one plant is paid. A utility's average cost blends old and new plants, imports and losses. These are the published averages we found, in US$ per MWh. The West African figures are USAID's 2022 estimates of production cost before trade.
| Pool | Country | Measure | Year | US$/MWh | Source |
|---|---|---|---|---|---|
| SAPP | South Africa | Eskom average selling price | 2025 | 135 | Daily Investor, citing Eskom (2025/26 average tariff 241.64 c/kWh) Average price across all sales, not a generation cost |
| SAPP | Namibia | NamPower average bulk tariff (2025/26) | 2025 | 115 | The Namibian / ECB announcement, May 2025 N$2.0611/kWh; rises to N$2.14 from 1 Aug 2026; NAD at par with ZAR |
| SAPP | Zambia | ZESCO average cost of emergency power bought in 2024 | 2024 | 232 | ZESCO emergency tariff application to ERB, July 2024 (p.5) Weighted average of imports and diesel during the drought |
| EAPP | Uganda | Weighted average generation cost (ERA) | 2026 | 60 | Business Focus (Uganda), quoting an ERA source (Feb 2026) About 6 US c/kWh |
| EAPP | Tanzania | Long-run marginal cost of generation (master plan) | 2020 | 67 | Tanzania Power System Master Plan, 2020 update (executive summary) 6.7 US c/kWh |
| WAPP | Ghana | Average cost of production | 2026 | 100 | IMF, Ghana selected issues paper (2026) US$0.10/kWh vs willingness to pay of US$0.15/kWh |
| WAPP | Cote d'Ivoire | Weighted average cost of production | 2020 | 90.6 | US Trade.gov, Cote d'Ivoire country commercial guide (energy), citing CI-Energies and CIE 52.13 FCFA/kWh; the source does not give the year (about 2020) |
| CAPP | Cameroon | Average cost-reflective tariff computed by ARSEL for ENEO | 2024 | 164 | ARSEL, tariff decision on ENEO's 2024 allowed revenue 99.55 FCFA/kWh vs 84.84 FCFA/kWh actually collected; the state pays the gap |
| WAPP | Nigeria | Production cost before trade (USAID estimate) | 2022 | 180 | USAID, West Africa power trade presentation (2022) |
| WAPP | Ghana | Production cost before trade (USAID estimate) | 2022 | 90 | USAID, West Africa power trade presentation (2022) |
| WAPP | Cote d'Ivoire | Production cost before trade (USAID estimate) | 2022 | 80 | USAID, West Africa power trade presentation (2022) |
| WAPP | Senegal | Production cost before trade (USAID estimate) | 2022 | 140 | USAID, West Africa power trade presentation (2022) |
| WAPP | Mali | Production cost before trade (USAID estimate) | 2022 | 160 | USAID, West Africa power trade presentation (2022) |
| WAPP | Burkina Faso | Production cost before trade (USAID estimate) | 2022 | 210 | USAID, West Africa power trade presentation (2022) |
| WAPP | Togo | Production cost before trade (USAID estimate) | 2022 | 210 | USAID, West Africa power trade presentation (2022) |
| WAPP | Benin | Production cost before trade (USAID estimate) | 2022 | 180 | USAID, West Africa power trade presentation (2022) |
| WAPP | Guinea | Production cost before trade (USAID estimate) | 2022 | 140 | USAID, West Africa power trade presentation (2022) |
| WAPP | Liberia | Production cost before trade (USAID estimate) | 2022 | 140 | USAID, West Africa power trade presentation (2022) |
| WAPP | Sierra Leone | Production cost before trade (USAID estimate) | 2022 | 150 | USAID, West Africa power trade presentation (2022) |
| WAPP | The Gambia | Production cost before trade (USAID estimate) | 2022 | 190 | USAID, West Africa power trade presentation (2022) |
| WAPP | Guinea-Bissau | Production cost before trade (USAID estimate) | 2022 | 210 | USAID, West Africa power trade presentation (2022) |
| WAPP | Mauritania | Production cost before trade (USAID estimate) | 2022 | 110 | USAID, West Africa power trade presentation (2022) |
| WAPP | Cote d'Ivoire | Average selling price of electricity (excl. taxes) | 2023 | 117 | Ministry of Economy (economie-ivoirienne.ci), electricity sector page, citing MMPE and the CI-Energies yearbook 71 FCFA/kWh in 2023, 68 in 2022 |
What it costs to build and run each kind of plant
A deal price bundles three costs: building the plant (and often its grid connection), running it, and fuel. This tab shows them separately, from real African projects where we have them. Keeping an existing plant running is usually far cheaper to build than a new one: about US$459-495 per kW to extend old coal units at Hwange and Jorf Lasfar, against US$2,641-3,108 per kW for the new units built at the same stations (2025 dollars).
US$ per kW of capacity in 2025 dollars, log scale. Costs are headline figures as reported; some include grid lines, roads, interest or grants, as noted in the table. Battery cost is per kW of a 4-hour system.
All build costs (29 projects)
| Project | Country | Type | MW | Year | As reported | US$/kW (2025) | What it covers and source |
|---|---|---|---|---|---|---|---|
| BESIPPPP bid window 3 (5 projects; 616 MW / 2464 MWh) | South Africa | New build new build | 616 | 2025 | 9,500 m ZAR | 862 | storage incl. grid connection at Eskom substations (site-specific round) SAnews, Minister announces preferred bidders under BESIPPPP BW3 (30 May 2025) |
| Jorf Lasfar units 1-4 PPA extension to 2044 with modernization | Morocco | Existing plant life extension | 1,356 | 2020 | 500 m USD | 459 | modernization + payment for extended right of use Moroccan Ministry of Economy and Finance, signing of the Jorf Lasfar PPA extension (24 Jan 2020) |
| Hwange units 1-6 rehabilitation (PPP with Jindal; 15-year agreement) | Zimbabwe | Existing plant life extension | 920 | 2025 | 455 m USD | 495 | generation (as reported) Engineering News / Reuters, Zimbabwe agrees $455m power plant refurbishment deal with Jindal (17 Sep 2025) |
| Kusile (Eskom headline cost) | South Africa | New build new build | 4,800 | 2025 | 160,500 m ZAR | 1,870 | generation (headline) Daily Investor, Eskom spent R432 billion on two power stations (2026) |
| Medupi (Eskom headline cost) | South Africa | New build new build | 4,764 | 2021 | 145,000 m ZAR | 2,445 | generation (headline; excludes much interest and later FGD retrofit) Daily Investor, Eskom spent R432 billion on two power stations (2026) |
| Lamu coal plant (cancelled) | Kenya | New build new build | 1,050 | 2017 | 2,000 m USD | 2,502 | generation (as reported) NS Energy, Lamu coal power plant project profile |
| Safi coal IPP | Morocco | New build new build | 1,386 | 2014 | 2,600 m USD | 2,551 | generation (as reported) Enerdata, Safi coal-fired power plant secures US$2.6bn financing (2014) |
| Hwange units 7 and 8 (new units at an existing station) | Zimbabwe | New build new units at an existing site | 600 | 2023 | 1,500 m USD | 2,641 | generation (as reported) CleanTechnica, Zimbabwe looks to IPPs and rural mini-grids (Jul 2025), citing ZERA |
| Jorf Lasfar units 5 and 6 (new units at an existing station) | Morocco | New build new units at an existing site | 700 | 2014 | 1,600 m USD | 3,108 | generation (as reported) TAQA Morocco, About the group |
| Sendou coal plant (cost to date) | Senegal | New build new build | 125 | 2021 | 200,400 m XOF | 3,432 | generation (as reported) Global Energy Monitor / doc.surf summary of Sendou power station |
| Central Termica de Temane combined cycle | Mozambique | New build new build | 450 | 2021 | 652 m USD | 1,722 | generation incl. 25 km 400 kV plant connection (see components) Zitamar News, Temane gas-fired power plant reaches financial close (2021) |
| Azura-Edo open cycle gas IPP | Nigeria | New build new build | 459 | 2015 | 900 m USD | 2,663 | total funding; may include gas supply infrastructure (see components) MIGA, Nigeria Azura-Edo IPP case study (2024) |
| Kariba dam rehabilitation (plunge pool and spillway) | Zambia/Zimbabwe | Existing plant dam safety rehabilitation | 1,830 | 2014 | 294 m USD | 219 | dam safety works (see components) World Bank, Kariba Dam Rehabilitation Project restructuring paper |
| Julius Nyerere hydro | Tanzania | New build new build | 2,115 | 2026 | 2,840 m USD | 1,343 | generation (headline; analysts' all-in estimates far higher) Energy Global / Reuters, Tanzania commissions country's largest hydropower plant (24 Aug 2026) |
| Karuma hydro | Uganda | New build new build | 600 | 2024 | 1,688 m USD | 2,887 | generation + transmission lines and substations (see components) Construction Review Online, Karuma hydropower plant factsheet (2024) |
| Isimba hydro | Uganda | New build new build | 183 | 2019 | 567 m USD | 3,902 | generation incl. a road bridge New Vision, Isimba power cheapest in East Africa (2019) |
| Koeberg decommissioning and waste liability (Eskom provision) | South Africa | Existing plant decommissioning | 1,860 | 2021 | 8,000 m ZAR | 346 | generation (as reported) Daily Maverick (21 Feb 2021), quoting Eskom chief nuclear officer Riedewaan Bakardien on the R16.2bn nuclear liability |
| Koeberg long-term operation (20 more years) | South Africa | Existing plant life extension | 1,860 | 2024 | 21,000 m ZAR | 632 | generation (as reported) Republikein / Eskom, Koeberg's long-term operation to cost R21bn (24 Jul 2024) |
| Cuamba solar with battery (15 MWac; 2 MW/7 MWh) | Mozambique | New build new build | 15 | 2021 | 36 m USD | 2,851 | generation + storage + substation upgrade Energy-Storage.news, Mozambique's first solar project with battery storage reaches financial close (2021) |
| Komati coal plant decommissioning and repurposing (150 MW PV; 70 MW wind; 150 MW batteries) | South Africa | Existing plant repurposing | 220 | 2022 | 497 m USD | 2,485 | decommissioning + new generation + storage + social programmes Engineering News, $497m just transition loan for Komati repowering approved by World Bank (4 Nov 2022) |
| Kishapu (Shinyanga) solar phase 2 (estimate) | Tanzania | New build new build | 100 | 2025 | 77 m USD | 770 | generation (as reported) Ecofin Agency, Tanzania connects first utility-scale solar plant to grid (phase 2 estimated at TZS 200.4bn, about US$77m) |
| Gafsa 100 MW and Tataouine 200 MW solar | Tunisia | New build new build | 300 | 2024 | 800 m TND | 880 | generation (as reported) Enterprise, Tunisia ramps up solar ambitions (13 May 2024), citing TAP |
| Kishapu (Shinyanga) solar phase 1, TANESCO-owned | Tanzania | New build new build | 50 | 2024 | 46 m USD | 944 | generation + 33/220 kV substation and grid tie Ecofin Agency, Tanzania connects first utility-scale solar plant to grid (TZS 118.6bn, about US$46m, AFD sovereign loan) |
| Kom Ombo 200 MW solar | Egypt | New build new build | 200 | 2021 | 163 m USD | 968 | generation (as reported) ACWA Power, Kom Ombo PV project page |
| Kairouan 100 MW solar (AMEA Power) | Tunisia | New build new build | 100 | 2024 | 300 m TND | 990 | generation (as reported) Enterprise, Tunisia ramps up solar ambitions (13 May 2024), citing TAP |
| Ferke Solar (52.4 MWp) | Cote d'Ivoire | New build new build | 52.4 | 2026 | 41,000 m XOF | 1,346 | generation (as reported) Capmad, Ferke Solar de 52,4 MWc inaugurated (5 Jul 2026) |
| Gad and Dicheto solar (planned investment) | Ethiopia | New build new build | 250 | 2019 | 300 m USD | 1,511 | generation (as reported) Afrik21, ACWA Power secures Gad and Dicheto contract (2019) |
| Boundiali public solar plant (37.5 MWp) | Cote d'Ivoire | New build new build | 37.5 | 2024 | 75.6 m EUR | 2,239 | generation (as reported) Afrik21 / African Energy Council, Boundiali solar plant inaugurated (2024) |
| Kipeto wind farm (incl. 220 kV line to Isinya) | Kenya | New build new build | 100 | 2021 | 344 m USD | 4,087 | generation + own grid connection (220 kV line to Isinya) Africa Energy Portal, BioTherm connects its 100 MW Kipeto wind farm (2021) |
Generation, lines and substations, split where the source allows
| Project | Part | What | Year | US$ m (2025) | Source |
|---|---|---|---|---|---|
| Karuma hydro | generation | Dam and 600 MW underground power station (EPC contract price) | 2013 | 1,907 | The EastAfrican, Chinese firm to build Karuma plant (29 Jun 2013) |
| Karuma hydro | line + substations | Karuma Interconnection Project: 248 km 400 kV to Kawanda, 55 km 400 kV to Olwiyo, 76 km 132 kV to Lira; new Kawanda 400/220 kV, Karuma 400/132/33 kV and Olwiyo 132/33 kV substations; Lira bay extension | 2023 | 306 | Daily Monitor, Govt commissions Shs1 trillion Karuma interconnection project (2023) |
| Temane gas-to-power and transmission | generation | 450 MW combined cycle plant incl. 25 km 400 kV link to Vilanculos substation | 2021 | 775 | Zitamar News, Temane gas-fired power plant reaches financial close (2021) |
| Temane gas-to-power and transmission | line + substations | Temane Transmission Project: 563 km 400 kV single circuit; new 400 kV substations at Vilanculos, Chibuto and Matalane; Maputo substation extension | 2019 | 694 | OPEC Fund, Temane Transmission Project (TREP/TTP) |
| Temane gas-to-power and transmission | compensation (land and resettlement) | Resettlement and compensation spent along the 563 km line | 2025 | 58.6 | AIM (Mozambique News Agency), 20 Nov 2025 |
| Azura-Edo gas IPP | generation | 461 MW open cycle plant | 2014 | 952 | Sweetcrude Reports, quoting President Jonathan at the groundbreaking (18 Oct 2014) |
| Azura-Edo gas IPP | fuel supply | Associated gas supply infrastructure | 2014 | 408 | Sweetcrude Reports, quoting President Jonathan at the groundbreaking (18 Oct 2014) |
| South Sudan - Uganda 400 kV interconnector | transmission line | 299 km 400 kV line (150 km Uganda; 149 km South Sudan) | 2024 | 169 | The Observer (Uganda), citing the AfDB appraisal report (Nov 2024) |
| South Sudan - Uganda 400 kV interconnector | substation | New 400/132/33 kV substations at Bibia and Gumbo, Karuma 400 kV extension, Olwiyo upgrade to 400/132/33 kV, and surrounding 33 kV integration | 2024 | 64.3 | The Observer (Uganda), citing the AfDB appraisal report (Nov 2024) |
| Karuma - Tororo 400 kV line and Ntinda substation | line + substations | 400 kV double circuit Karuma-Tororo line and Ntinda substation (financing agreement) | 2026 | 387 | AllAfrica, Uganda and Standard Chartered sign EUR 641m financing (11 Feb 2026) |
| Kariba dam rehabilitation | other (dam safety) | Plunge pool reshaping | 2014 | 135 | World Bank, Kariba Dam Rehabilitation Project restructuring paper |
| Kariba dam rehabilitation | other (dam safety) | Spillway refurbishment (6 gates) | 2014 | 169 | World Bank, Kariba Dam Rehabilitation Project restructuring paper |
| Kariba dam rehabilitation | other (management) | Institutional support and project management | 2014 | 95.6 | World Bank, Kariba Dam Rehabilitation Project restructuring paper |
| Uganda-Tanzania interconnector, Tanzania side | line + substations | USD 676,000/km incl. substations | - | via Line Routing cost points | |
| Uganda-Tanzania interconnector, Uganda side | line + substations | USD 852,000/km, more complex substations | - | via Line Routing cost points | |
| Isang (Botswana) - Mahikeng (South Africa) | line + substations | incl. branches; ~USD 540,000/km | - | via Line Routing cost points | |
| Burundi (Jiji-Mulembwe) - Tanzania (Kigoma), double circuit | line + substations | EUR 64 M at ~1.08 USD/EUR; incl. substations | - | via Line Routing cost points | |
| Malawi-Zambia (Nkhoma - Chipata West), double circuit | line + substations | incl. substation extensions; ~USD 700,000/km | - | via Line Routing cost points | |
| Mozambique-Malawi, Mozambique section (Matambo - border), line-only EPC | transmission line | L&T signed price 2021, incl. the 1.7 km Zambezi crossing; no substation; ~USD 248,000/km | - | via Line Routing cost points | |
| Temane-Maputo 400 kV - spent | compensation (land and resettlement) | ~USD 104,085/km. 219 houses, 2,736 farms; incl. community support and consultancy | - | via Line Routing cost points | |
| Mozambique-Malawi interconnector, Malawi section (border - Phombeya) 400 kV - government allocation for the RAP | compensation (land and resettlement) | ~USD 46,053/km. | - | via Line Routing cost points | |
| Iringa-Mbeya 400 kV - RAP budget 2018 (TZS 7.99 bn at ~2,270 TZS/USD) | compensation (land and resettlement) | ~USD 12,054/km. 1,747 PAPs, 48 households relocated, 1,216 ha, 315 graves | - | via Line Routing cost points | |
| TAZA Tanzania section (Iringa - Sumbawanga), compensation only 400 kV - allocated (TZS 21.4 bn at ~2,600 TZS/USD) | compensation (land and resettlement) | ~USD 13,275/km. 6,279 people compensated | - | via Line Routing cost points | |
| Zambia-Tanzania interconnector, Pensulo - Mpika - Kasama 330 kV - RAP budget Dec 2025 | compensation (land and resettlement) | ~USD 4,947/km. 172 houses, 1,606 ha wayleave (easement); excludes USD 2.85 M social investment fund | - | via Line Routing cost points | |
| Phombeya - Nkhoma (MCA-Malawi) 400 kV - compensation set aside 2015 (USD 5 M) | compensation (land and resettlement) | ~USD 28,902/km. 3,278 households affected, 54 dwelling houses | - | via Line Routing cost points | |
| Alaska - Karoi (ZETDC, AfDB) 132 kV - ESMP compensation budget | compensation (land and resettlement) | ~USD 2,353/km. 35 farmers economically displaced, no settlements; shares the Kariba lines wayleave; 132 kV, reference only | - | via Line Routing cost points |
Fuel and running costs
| Where | Item | Year | As reported | US$ (that year) | Source |
|---|---|---|---|---|---|
| South Africa | Eskom generation cost - coal | 2025 | 546 ZAR per MWh | 30.5 | Daily Investor, citing Eskom (2025) Primary energy cost per MWh from the coal fleet |
| South Africa | Eskom generation cost - diesel open cycle gas turbines | 2025 | 6084 ZAR per MWh | 340 | Daily Investor, citing Eskom (2025) About 11 times coal |
| South Africa | Eskom primary energy cost (FY2025 total) | 2025 | 150207 ZAR million per year | 8,399 | Eskom interim financial statements, 30 Sep 2025 (comparative for year to 31 Mar 2025) Coal ~R91bn, IPPs R45.6bn, OCGT diesel R13.3bn, nuclear R7.3bn, imports R6.6bn (Business Report, citing Eskom 2025 annual report) |
| South Africa | Export coal price (API4 fob Richards Bay) - 2025 average | 2025 | 89 USD per tonne | 89 | Engineering News, Exxaro benefits from stronger local coal demand (2 Dec 2025) US$105/t in 2024; export price, not the price Eskom pays |
| South Africa | Carbon tax headline rate | 2026 | 308 ZAR per tCO2e | 17.2 | Daily Maverick, South Africa's carbon tax survives Budget (1 Mar 2026), citing the 2026 Budget Review R236 in 2025; R462 by 2030 |
| South Africa | Carbon tax effective rate after maximum allowances (combustion) | 2026 | 46.2 ZAR per tCO2e | 2.6 | Just Share, Opaque corporate lobbying continues (13 Apr 2026) About US$2.82/t |
| Nigeria | Benchmark gas price to power plants | 2024 | 2.42 USD per MMBtu | 2.4 | Nairametrics, on NERC's MYTO 2024 inputs (Apr 2024) Set by NMDPRA; used by NERC in tariffs |
| Ghana | Natural gas price used in the July 2025 tariff review | 2025 | 7.7134 USD per MMBtu | 7.7 | Citi Newsroom, PURC announces 2.45% increase (25 Jun 2025) Hydro-thermal mix assumed 28.8% / 71.2% |
| Kenya | Fuel energy charge passed to consumers (thermal fuel cost) | 2025 | 3.25-4.14 KES per kWh | 0 | EPRA Energy and Petroleum Statistics Report FY2024/25 (Table 2.5, p.27) Monthly range Jul 2024 - Jun 2025 |
| Cameroon | Production cost of diesel plants on isolated grids | 2022 | 200 XAF per kWh | 0.3 | Ecomatin, citing MINEE |
Lifetime cost studies (levelized cost of electricity)
Levelized cost spreads the build, running and fuel costs over every MWh a plant is expected to produce in its life. Studies differ in their assumptions, so compare within a study, not across them.
| Scope | Source | Measure | Year | As reported | US$/MWh (2025) | Study |
|---|---|---|---|---|---|---|
| World | wind | LCOE weighted average (new projects) | 2024 | 34 USD per MWh | 34.9 | Energy Institute, summarising IRENA Renewable Power Generation Costs in 2024 (30 Jul 2025) Onshore wind |
| World | solar PV | LCOE weighted average (new projects) | 2024 | 43 USD per MWh | 44.1 | Energy Institute, summarising IRENA Renewable Power Generation Costs in 2024 (30 Jul 2025) |
| World | CSP | LCOE weighted average (new projects) | 2024 | 92 USD per MWh | 94.4 | Energy Institute, summarising IRENA Renewable Power Generation Costs in 2024 (30 Jul 2025) |
| World | battery storage | LCOE weighted average (new projects) | 2024 | 104 USD per MWh | 107 | Energy Institute, summarising IRENA Renewable Power Generation Costs in 2024 (30 Jul 2025) |
| Africa | wind | LCOE (Africa) | 2024 | 52 USD per MWh | 53.4 | Greentech Lead, summarising IRENA Renewable Power Generation Costs in 2024 Same LCOE as Europe but a much larger financing share |
| World | battery storage | installed cost | 2024 | 192 USD per kWh | 197 | Greentech Lead, summarising IRENA Renewable Power Generation Costs in 2024 Down 93% since 2010 |
| South Africa | coal | LCOE new build (EPRI study for the IRP) | 2023 | 1,400-1,600 ZAR per MWh | 80.1-91.6 | Business Day, Still more gaps than answers in IRP data (15 Jan 2024) |
| South Africa | coal | LCOE new build with carbon capture (EPRI) | 2023 | 2,500-2,880 ZAR per MWh | 143-165 | Business Day (15 Jan 2024) |
| South Africa | solar PV | LCOE ground-mounted (EPRI) | 2023 | 1,000 ZAR per MWh | 57.2 | Business Day (15 Jan 2024) Rooftop up to R3,200 |
| South Africa | solar + storage | LCOE (EPRI) | 2023 | 4,300 ZAR per MWh | 246 | Business Day (15 Jan 2024) |
| South Africa | coal | LCOE existing plant (Lazard ranges in rand) | 2023 | 525-1,340 ZAR per MWh | 30.1-76.7 | Business Day (15 Jan 2024) Brownfield reference: existing coal vs new |
| South Africa | coal | LCOE new build (Lazard ranges in rand) | 2023 | 1,230-3,000 ZAR per MWh | 70.4-172 | Business Day (15 Jan 2024) |
| South Africa | gas | LCOE combined cycle (Lazard ranges in rand) | 2023 | 1,120-1,830 ZAR per MWh | 64.1-105 | Business Day (15 Jan 2024) |
| South Africa | wind | LCOE onshore (Lazard ranges in rand) | 2023 | 435-1,400 ZAR per MWh | 24.9-80.1 | Business Day (15 Jan 2024) |
| South Africa | solar PV | LCOE utility-scale (Lazard ranges in rand) | 2023 | 435-1,740 ZAR per MWh | 24.9-99.6 | Business Day (15 Jan 2024) |
| South Africa | nuclear | LCOE new build (Lazard ranges in rand) | 2023 | 2,500-4,000 ZAR per MWh | 143-229 | Business Day (15 Jan 2024) |
| World | nuclear | Cost of a 10-20 year nuclear life extension | 2022 | --50 USD per MWh | --55 | Engineering News, IEA backs nuclear life extensions as Koeberg pushes ahead (30 Jun 2022) Less than US$50/MWh |
| Kenya | geothermal | Generation cost (World Bank assessment) | 2025 | 85 USD per MWh | 85 | Business Front, Kenya's renewable energy electricity cheaper |
| Kenya | hydro | Generation cost of existing hydro (World Bank) | 2025 | 30-50 USD per MWh | 30-50 | Business Front, Kenya's renewable energy electricity cheaper Brownfield reference |
| Kenya | solar and wind | Expected auction prices (World Bank) | 2025 | 50-70 USD per MWh | 50-70 | Business Front, Kenya's renewable energy electricity cheaper |
| Tanzania | system | Long-run marginal cost of generation | 2020 | 67 USD per MWh | 83.3 | Tanzania Power System Master Plan 2020 update New-projects-only unit cost of supply 13.7 US c in 2021 |
How prices have moved
Solar deals in this table had a typical (median) price of US$80 per MWh in 2012-2018 (7 deals) and US$36 in 2019-2026 (14 deals), as signed. Coal and gas deal prices have not fallen the same way; much of their cost is fuel, priced on world markets.
Each dot is one deal, US$ per MWh as signed (log scale). Hover for the deal; click to open its source.
Fuel prices
Thermal plants pass fuel costs through to buyers, so these prices drive what coal, gas and oil power costs. Brent crude averaged US$69.1 a barrel in 2025 and US$125 in Oct 2026; South African export coal US$94.9 a tonne in 2025 and US$100 in Oct 2026; LNG delivered to Japan US$12 per MMBtu in 2025 and US$16.6 in Oct 2026.
Coal, US$ per tonne
Gas, US$ per MMBtu
Oil, US$ per barrel
Monthly averages, nominal US dollars. Source: World Bank Commodity Price Data (the Pink Sheet), updated 3 November 2026, CC BY 4.0. Some South African coal months in 2022-2024 are World Bank estimates.
Which plant is cheapest, and for how many hours a year?
Levelized cost is a plant's lifetime cost per MWh: build cost, fixed and variable running costs and fuel, spread over everything it produces. It depends heavily on how many hours the plant runs.
A screening curve plots a plant's yearly cost per kW against the hours it runs. Plants that are cheap to build but expensive to fuel (peakers) win for few hours; plants that are expensive to build but cheap to run win for many. Where the lines cross shows which plant suits which job.
Least-cost expansion planning picks the cheapest mix of plants to meet demand over the next 20-30 years, using a capacity expansion model (such as PyPSA, OSeMOSYS or PLEXOS) that also handles when solar and wind produce, storage, reserves and the grid. National integrated resource plans and SAPP's pool plan are built this way.
Economic dispatch is the day-to-day version: run the plants you already have in order of their running cost.
Yearly cost per kW against hours run
Cost per MWh against how much of the year it runs
| Show | Build cost US$/kW | Fixed O&M US$/kW-yr | Variable O&M US$/MWh | Heat rate Btu/kWh | Life years | Runs at most % of year | US$/MWh at that level |
|---|---|---|---|---|---|---|---|
Solar and wind lines stop at the share of the year they can run (set it for your site; the defaults are illustrative). The dashed coal line is an existing unit given a life extension. Lines that run off the top of a chart are cut; hover to read them. Everything is in 2025 US dollars and real terms; edit any number.
Where the default numbers come from
- Solar PV: build cost from Median of 8 African utility solar builds in this dataset (2025 US$); running costs from EIA AEO2026 fixed O&M (2025 US$); IRENA 2024 global installed cost US$691/kW for comparison.
- Wind (onshore): build cost from EIA AEO2026 overnight cost (2025 US$); Kipeto, Kenya US$4,087/kW incl. its 220 kV line; IRENA 2024 global US$1,041/kW; running costs from EIA AEO2026 O&M.
- Hydro (large, new): build cost from Median of Karuma, Isimba and Julius Nyerere in this dataset (2025 US$); running costs from EIA AEO2026 O&M.
- Geothermal: build cost from EIA AEO2026 overnight cost (2025 US$); running costs from EIA AEO2026 O&M; Kenyan projects vary widely.
- Coal (new): build cost from Median of 7 African new coal builds in this dataset (2025 US$); running costs from EIA AEO2023 ultra-supercritical coal O&M and heat rate, inflated from 2022 to 2025 US$.
- Coal (keep an old unit running): build cost from Hwange 1-6 refurbishment and Jorf Lasfar 1-4 extension in this dataset (2025 US$); running costs from Same O&M and heat rate as new coal; older units usually burn more coal per MWh.
- Gas, combined cycle: build cost from Temane, Mozambique, in this dataset (2025 US$; includes a 25 km 400 kV line); running costs from EIA AEO2026 O&M and heat rate.
- Gas, open cycle (peaker): build cost from EIA AEO2026 industrial-frame turbine (2025 US$); Azura-Edo, Nigeria total funding about US$2,663/kW; running costs from EIA AEO2026 O&M and heat rate.
- Diesel or fuel-oil engines: build cost from EIA AEO2023 internal combustion engine, inflated from 2022 to 2025 US$; running costs from EIA AEO2023 O&M and heat rate, inflated to 2025 US$.
- wacc (% a year (real)): Assumption. IEA's model uses 4-7% for utility solar and onshore wind and 8-9% for coal, gas and nuclear depending on the stage of economic development; African projects often pay more
- coal price (US$/t): World Bank Pink Sheet, coal South Africa (Richards Bay), 2025 average; Oct 2026: 100.0
- coal gj t (GJ/t): 6,000 kcal/kg NAR, the World Bank South Africa coal specification
- gas price (US$/MMBtu): World Bank Pink Sheet, LNG Japan, 2025 average (proxy for imported LNG); Oct 2026: 16.59. Domestic gas is far cheaper: Nigeria US$2.42, Ghana US$7.71 (this dataset)
- diesel price (US$/GJ): Implied by Eskom's 2025 open-cycle turbine fuel cost of R6,084/MWh at R17.884/US$ and EIA's 9,142 Btu/kWh heat rate
- co2 price (US$/t CO2): Off by default. South Africa's carbon tax: R308/t headline (about US$17), about R46/t effective after allowances (about US$2.6), 2025
- co2 coal (kg CO2/GJ): IPCC 2006 default, other bituminous coal
- co2 gas (kg CO2/GJ): IPCC 2006 default, natural gas
- co2 diesel (kg CO2/GJ): IPCC 2006 default, gas/diesel oil
EIA: US Energy Information Administration, Annual Energy Outlook cost and performance tables (public domain). Fuel prices: World Bank Pink Sheet. Build costs marked "this dataset" are the African projects in the True cost tab.
What this calculator leaves out
- When each plant produces: solar only in daylight, wind when it blows. A system needs firm capacity or storage for the rest, which a screening curve does not price.
- Grid connection and transmission, unless included in the build cost.
- Construction time and interest during construction, taxes, inflation indexation and currency risk.
- Plant-specific fuel contracts: many African plants buy gas or coal well below world prices, and some far above.
Sources and updates
What changed
- November 2026 - Tabs added for SAPP market detail (time of day, forward and intraday prices, volumes), build and running costs, price and fuel trends, and a screening-curve planning calculator. First edition: 64 deals in 23 countries across the five power pools, SAPP day-ahead prices from January 2025 to June 2026, and published utility averages.
Common questions
Is coal cheaper than solar in Africa?
Not for new plants, by the prices that have been signed. New coal deals came in at US$59-130 per MWh, while solar PV auctions in Egypt, Ethiopia, Senegal, Côte d'Ivoire, Tunisia and South Africa cleared at US$20-50. Solar only produces in daylight, so the fair comparison for round-the-clock supply is solar with storage, which bid about US$35 per MWh in Morocco in 2025 and more in smaller markets.
What is the price on the SAPP day-ahead market?
The monthly average was 5.3 US cents per kWh (US$53 per MWh) in June 2026, down from 17.6 cents in April 2025. SAPP publishes it in its monthly market performance reports.
Does SAPP have a forward market for electricity?
Yes. SAPP runs weekly and monthly forward physical markets next to its day-ahead and intraday markets. Weekly forward prices are published by time of day; the monthly forward market trades every month, but its price is not published in SAPP's reports. See the Markets tab.
What is a screening curve in power planning?
A chart of a plant's yearly cost per kW against the hours it runs. Plants that are cheap to build but costly to fuel win for few hours; plants that are costly to build but cheap to run win for many. The Planning tab lets you change every input. Full least-cost planning uses capacity expansion models that also handle storage, reserves and when solar and wind produce.
How much does Kenya pay for electricity from Ethiopia?
6.5 US cents per kWh under the 2022 agreement, and about 15.5 cents plus a monthly demand charge under the agreement signed in July 2026.
What is the lowest solar tariff in Africa?
In this table, Egypt's 500 MW Abydos plant at 2 US cents per kWh (2022), then Ethiopia's Scaling Solar round at 2.526 cents (2019) and Egypt's Kom Ombo at about 2.5 cents.
Why are some countries missing?
Many power purchase agreements are confidential. We list a country once a price has been published by an official source or reported from one.