West African Power Pool grid atlas
Benin, Burkina Faso, Cabo Verde, Cote d’Ivoire, The Gambia, Ghana, Guinea, Guinea-Bissau, Liberia, Mali, Mauritania, Niger, Nigeria, Senegal, Sierra Leone and Togo: the grid today, every power plant of 1 MW and above, the pipeline and the WAPP master plan. Public data.
Grows where the grid hasn’t.
What is on the map
Existing lines and substations: OpenStreetMap contributors (ODbL), extracted 17-18 November 2026 (openstreetmap.fr and Geofabrik extracts). All power lines tagged 66 kV and above plus lines with no voltage tag. Coverage is uneven: Nigeria, Ghana and Cote d’Ivoire are mapped in detail; Liberia, Sierra Leone, Guinea-Bissau and Cabo Verde have few mapped lines. Gaps filled from the World Bank Africa grid map 2017 (ECREEE data for West Africa).
Gap-fill: where a line in TANESCO's 2015 network, the World Bank 2017 DRC grid or the World Bank 2017 Africa grid is more than 3 km from any OSM line, the missing stretch is drawn dotted with its source and year. These can be out of date. Line lengths are mapped segment lengths, so a double circuit counts once.
Generation, 1 MW and above, merged without duplicates in this order: our curated register (projects we track with their date history), Global Energy Monitor's Global Integrated Power Tracker (September 2026 release, CC BY 4.0; units rolled up into one plant per status, cancelled, shelved, mothballed and retired units left out, and records GEM took from TransitionZero left out because their license is non-commercial), then the WRI Global Power Plant Database (2021), OpenStreetMap plants with a tagged capacity and the World Bank AICD inventory (about 2011), each only where nothing is already mapped nearby. Smaller plants (added 17 Nov 2026) come last, from Global Energy Monitor and then OpenStreetMap, only where no plant is mapped within 2 km, so they never replace a larger plant. Each plant says which source it came from. Pipeline generation and transmission: utilities, regulators, funders (World Bank, AfDB, EU), the Nile Basin Initiative and press. Each feature links its source.
Pipeline routes are drawn substation to substation and are indicative, not surveyed alignments. Where no public in-service date exists, the year is our estimate and is marked as such.
Constraints are qualitative flags from published reports, not a load-flow study.
World Bank 2017 planned lines are kept as a record of the 2017 plan: many have since been built or dropped.
Towns in the search: GeoNames (CC BY 4.0), places with 1,000 or more people plus capitals and district seats. Distances from a town to the grid are straight-line distances to the nearest mapped line of 66 kV and above.
Map colors
Line colors follow the Southern African Power Pool's grid map (2021, version 2), so every Aloe Energy grid atlas reads the same way: solid for existing lines, broken for proposed ones. The interface uses Aloe Energy's palette.
Regional statistics
Installed capacity: Mission 300 compact figures for Cote d’Ivoire, Ghana and Guinea, published figures for Nigeria, and for the other countries the sum of operating units in Global Energy Monitor (Sep 2026). Electricity access: World Bank WDI (2024 data). Interconnector ratings and trade: World Bank, CI-Energies (ITSF country assessment 2026), NERC and TCN. WAPP publishes no transfer-limit table, so the map shows traded or contracted MW against the rating where known.
History and the master plan
Looking back with the year slider, plants appear in the year they were commissioned (WRI database and the project register); plants with no known year stay faint. The transmission network is today's, because line build years are not in the open data. Master plan: ECOWAS Master Plan for regional power generation and transmission 2019-2033 (Tractebel for ECOWAS and WAPP, 2018). Routes are drawn from its text and are indicative.
Comments
Use the comment control on this page. Every pipeline project has a short tag at the bottom of its popup (for example #moma or #caculo-cabaca); quote it so the thread points at the right project. Opening the page with that tag after the address jumps straight to it.
Deal stage and slippage
Stages run from concept to operating in eight steps. The slippage score compares the latest in-service year with the first one found in public sources; each date links to where it was said. Our own estimates are never scored.
Coming next
Demand and grid-arrival layer (settlements, mines, distance to grid), then quantified constraints (interconnector limits, hosting capacity, price spreads).