Guinea

West African Power Pool - distribution network

Guinea distribution network map

Few medium-voltage lines in Guinea are in public data, so most lines here are predicted (dashed): they follow major roads where night-time lights suggest a line, joined to the nearest substation. Mapped lines are solid. Together they give a first picture of where the distribution network runs.

1,221km of mapped medium-voltage lines, 11 to 33 kV
9,069km more predicted along roads, where no line is mapped
88%of the network on this map is predicted, not mapped
25substations in public data

Click a line, substation or plant for details. Click the map to zoom with the scroll wheel. Lines are indicative, not for engineering or investment decisions.

What the map shows

Lines by voltage and source

Public data on Guinea's medium-voltage network is scarce, so most of this map is predicted rather than mapped. If the utility publishes its network, those lines would replace the predicted ones. There is no public low-voltage data for Guinea, so the map shows medium voltage only.

Each line keeps its source. Where two sources map the same line, we keep one, in this order: utility data, the World Bank 2017 map, OpenStreetMap, then predicted lines.

Line length by voltage
Voltagekm
30 to 33 kV964
15 to 22 kV127
Medium voltage, not recorded130
Predicted along roads9,069
Total10,291

Line length by source
SourcekmShare
ECOWAS distribution grid 2017 (ECREEE, via energydata.info), existing lines (2017)1,08211%
World Bank Africa electricity grid (2017)80%
OpenStreetMap (newer lines not in the 2017 map)1311%
Predicted along roads (night-time lights, roads and substations)9,06988%
Total10,291100%
Method and caveats

How we built this map

  • We start from utility data where it is public (for Guinea, ECOWAS distribution grid 2017 from ECREEE, via energydata.info), existing lines from 2017), then add the World Bank Africa electricity grid (2017) and OpenStreetMap lines below 40 kV and power=minor_line, each only where it runs more than 250 m from a line already on the map.
  • Predicted lines follow major roads (motorway to tertiary, from OpenStreetMap), because rural feeders mostly run along roads. A road section is predicted to carry a line where gridfinder (Arderne et al. 2020), a model built on night-time lights, predicts one running along it and no mapped line already explains it. Predicted sections are then joined to the nearest substation or mapped line along the roads, so they form connected feeders, and short gaps along the same road are closed. Smaller (unclassified) roads are used only to reach villages and towns in OpenStreetMap that sit within 1.5 km of a night-time-light prediction. They may be lines that exist but are not mapped, lines at another voltage, or no line at all. We tested the model on Kenya with Kenya Power's own map left out: 85% of the predicted line length lay within 1 km of a real Kenya Power line, and mapped plus predicted lines reached 54% of the real network, against 6% for mapped lines alone.
  • OpenStreetMap power lines with no voltage tag are shown as medium voltage with the voltage not recorded, unless they run along a known high-voltage line or link two parts of the high-voltage network over a long distance. A few may still be high-voltage lines.
  • The 2017 map does not show lines built since then, and OpenStreetMap coverage depends on volunteers. Low-voltage networks are rarely public.
  • Transmission lines (40 kV and above) are left out of this map; see the grid-edge atlas for the wider grid. World Bank lines with no recorded voltage are left out, since some are transmission.
  • Geometry is simplified to about 30 m for the web. Lengths are measured before simplifying.

Sources

  • Medium-voltage lines: ECOWAS distribution grid 2017 (ECREEE, via energydata.info), existing lines (2017), published by the World Bank on energydata.info (CC BY-SA 4.0). These lines, as shown on this map, are shared under the same licence.
  • Other medium-voltage lines: World Bank Group, Africa electricity grids (2017), via energydata.info (CC BY 4.0).
  • Lines, substations and small plants: OpenStreetMap contributors (ODbL), downloaded 12 November 2026.
  • Predicted lines: our road-based model, using gridfinder (Arderne, Zorn, Nicolas and Koks 2020, Predictive mapping of the global power system using open data, Scientific Data, CC BY 4.0), OpenStreetMap roads and settlements (ODbL) and the substations on this map.

The map is free to view. The data is available on request: email [email protected] and tell us what you need it for. Last built 12 November 2026.

Back to Guinea grid and access data