Country data

Mission 300 compact country

Guinea electricity access and grid

About 9.4 million people in Guinea live where satellites see no electric light at night, and 80% of them live within 15 km of a power line. This page brings together what our grid-edge screening and Guinea's Mission 300 energy compact say about who still needs power, how close the grid is and what the country has committed to.

9.4 Mpeople live without night-time light, a proxy for no power
80%of them live within 15 km of a power line
10,400km of mapped and predicted power lines, all voltages (gridfinder)
53%electricity access in 2024, as stated in the compact
100%access target for 2030 in the Mission 300 compact
The grid today

Lines and access

Gridfinder, which combines OpenStreetMap lines with medium-voltage lines predicted from night-time lights, maps about 10,372 km of existing and likely power lines in Guinea. That includes lower-voltage distribution lines, so it is not comparable with the high-voltage totals on our grid-atlas country pages. We have not yet built a detailed grid atlas for this country.

Mission 300 energy compact
CommitmentValue
Electricity access now53% (2024)
Access target100% by 2030
Planned split of new accessgrid 71%, mini-grids 10%, standalone solar 19%
Clean cooking targetfrom 12% to 35% by 2030
Private investment soughtUS$7.6 billion
Rules for mini-grids when the grid arrivesYes
E-waste commitmentNo
Near the grid, not on it

Who lives near the grid but off it

About 9.4 million people in Guinea, roughly 64% of the population, live where satellites see no electric light at night. Of them, 80% live within 15 km of a mapped or predicted power line: 3.0 million within 2 km, 4.5 million 2 to 15 km away, and 1.9 million farther out. The largest group lives 2 to 15 km out: close enough to plan for the grid, too far for a quick connection. That is where mini-grids built to join the grid later can do the most good. At its 2016-2023 pace, about 2.3 percentage points a year (World Bank), Guinea would reach the 100% access target in its Mission 300 compact around 2044, not 2030; the target needs about 7.0 points a year.

  • Within 2 km: 3.0 million (32%)
  • 2 to 15 km: 4.5 million (48%)
  • More than 15 km: 1.9 million (20%)
See the numbers as a table
People without night-time light, by distance to a line
DistanceMillion peopleShare
Within 2 km of a line3.0132%
2 to 15 km4.4948%
More than 15 km1.9220%
Total9.41100%
How we count this

"Without night-time light" is a satellite proxy, not a measured access rate. Distances are straight lines to mapped or predicted lines. See the grid-edge atlas for the method.

Topics

More about Guinea

Open any topic for the full text and tables.

Mission 300

What the energy compact commits to

Guinea's Mission 300 energy compact commits to raising electricity access from 53% to 100% by 2030.

Guinea's Mission 300 energy compact commits to raising electricity access from 53% to 100% by 2030. New access is planned as 71% grid, 10% mini-grids and 19% standalone solar. Each value is quoted, with its page, on our compacts page, where compacts sit side by side. Nothing is scored or ranked.

Emissions

Grid emission factor

Each megawatt-hour generated in Guinea in 2024 came with about 0.19 tonnes of CO2.

Each megawatt-hour generated in Guinea in 2024 came with about 0.19 tonnes of CO2. For carbon projects such as solar mini-grids, the combined margin (the usual basis for crediting) is about 0.12 tCO2/MWh. Looking ahead, our scenarios from the plants in the pipeline put the average at 0.35 tCO2/MWh in 2030 and 0.35 in 2035, depending on how many plants arrive on time (see the scenarios). We have not yet rated the quality of its data. See our grid emission factors for the method and all 38 countries.

Grid mix, 2024.

Oil and diesel 25% Hydro 74% Solar 1%

Air in the city

Satellite-based estimates put fine particulate matter (PM2.5) in Conakry, the capital, at about 27 µg/m³ on average in 2023, about 5 times the WHO guideline of 5, down from 30 in 2013. The WHO database has no ground measurement for the city. Electric motorbikes and buses cut exhaust where people breathe it; see e-mobility for 71 cities.

Grid emission factor, 2024 (tCO2/MWh)
MeasuretCO2/MWh
Generated in country0.189
Electricity used, with imports0.189
Combined margin (for carbon projects)0.118
Tariffs and load shedding

What power costs here

EDG's Domestic low voltage tariff.

EDG's Domestic low voltage tariff. Our utilities, tariffs and load shedding page compares 39 African countries by customer class, with what each tariff includes and load shedding since 2015.

Tariff and load shedding
MeasureValue
Lifeline or first block (1-40 kWh per 30 days)107 GNF/kWh, about US$0.012
Household (41-330 kWh per 30 days)387 GNF/kWh, about US$0.044
Load shedding nowUnscheduled outages in Conakry reported again in Sep 2026

Energy charge only, at the central bank rate on 30 October 2026. Check what is included (VAT, levies, fixed charges) on the research page.

Certificates and carbon credits

Renewable energy certificates

Guinea cannot issue I-RECs, the international renewable energy certificate, yet.

Guinea cannot issue I-RECs, the international renewable energy certificate, yet. On the voluntary carbon registries it has 12 carbon credit projects, 2 of them issuing, with about 0.1 million credits issued; 0 are renewable energy projects. See our certificates page to compare certificates with carbon credits across the region.

Certificates and carbon credits
MeasureValue
I-REC statusNot approved
Registered plants-
I-RECs issued, all years-
Carbon credit projects12
Carbon credits issued0.1 million

I-RECs: Xpansiv I-REC Registry statistics, October 2026. Carbon projects: CarbonPlan OffsetsDB (Verra, Gold Standard and other voluntary registries), data to June 2026. Article 6: UNEP Copenhagen Climate Centre Article 6 Pipeline, November 2026.

Reference

Neighbors, sources and updates

Sources 4 sources
  • People without night-time light and distance to the grid: WorldPop 2020 and gridfinder (Arderne et al. 2020, CC BY 4.0), as screened in our grid-edge atlas.
  • City air: Atmospheric Composition Analysis Group, Washington University in St. Louis (PM2.5 V6.GL.02.04); WHO Ambient Air Quality Database 2026.
  • Emission factors: our grid emission factors (Ember, 2024).
  • Compact commitments: the national Mission 300 energy compact, as quoted page by page on our compacts page.

The maps are free to view. The data behind this page is available on request: email [email protected]. Lines are indicative, not for engineering or investment decisions.

What changed

Our data is checked every month, and this page is rebuilt after each check.

  • 16 November 2026 - Latest update to the grid-edge atlas, which this page is generated from.

Common questions about Guinea

Where can I find a map of Guinea's electricity grid?

Our free grid-edge atlas shows Guinea with mapped and predicted power lines and where people without power live. A detailed high-voltage atlas is not built yet.

How many people in Guinea live without electricity?

About 9.4 million people live where satellites see no electric light at night, a proxy for living without power. Of them, 80% are within 15 km of a power line.

What is the grid emission factor for Guinea?

About 0.19 tCO2/MWh for electricity used in 2024, and 0.12 tCO2/MWh as a combined margin for carbon projects. See our grid emission factors for the method.

What is Guinea's Mission 300 energy compact target?

Guinea's Mission 300 energy compact commits to raising electricity access from 53% to 100% by 2030. New access is planned as 71% grid, 10% mini-grids and 19% standalone solar. See all compacts side by side on our compacts page.

Can I get the data for Guinea?

Yes, on request. The maps are free to view; email [email protected] and tell us what you need it for.