Grows where the grid hasn’t.
Who supplies the power, what it costs, and when it goes off
One picture of electricity across 39 African countries (the 17 core countries of the Southern African and Eastern Africa power pools, Djibouti, Madagascar and 20 West and Central African countries): the utilities and regulators, the tariff a household or business actually pays, and load shedding since 2015. Every number links to the regulator or utility document it came from.
Tariffs
- Every country protects the first block. Lifeline or social tariffs run from under one US cent per kWh (Angola) and under two cents (Zambia, Mozambique) to about 9 cents (Kenya, Eswatini) and 14 cents (Eskom Homelight), usually for the first 15 to 200 kWh a month.
- The middle of the ladder is where it bites. Rwanda charges 89 francs for the first 20 kWh and 310 for the next 30; Uganda jumps from 250 to 779 shillings after 15 kWh.
- Business often pays more than industry. In most countries the small commercial rate is above the industrial energy rate, partly because industry pays separately for demand. DR Congo, Zambia and Burundi are the exceptions.
- West and Central Africa widen the spread. Nigeria's lifeline block costs 4 naira (about 0.3 US cents) per kWh and Guinea's first block about 1 cent, while Liberia charges 13 US cents for its social block and 22 cents for households. In nine of the 22 added countries we found no published tariff grid at all.
- Tariffs are moving. Ethiopia raises tariffs every quarter to 2028, Botswana added 9% in August 2026, Malawi 12% in January 2026, and several Mission 300 compacts commit to cost-reflective tariffs.
Load shedding
- Drought drives the big episodes. Zambia (2015/16, 2019 to 2021, 2024/25), Zimbabwe (2019, 2022/23, 2024/25), Ethiopia (2019) and Tanzania (2023/24) all trace their worst years to low reservoirs.
- Plant failure drives the long ones. South Africa's 2019 to 2024 run came from unplanned outages at coal plants; Malawi's 2022/23 cuts followed cyclone damage at Kapichira.
- Imports carry the shortage across borders. When Eskom shed load in 2015 it also cut supply to Botswana, Namibia, Eswatini and Lesotho.
- Reliability data is scarce. Only four utilities in 39 publish SAIDI where we could find it, and their definitions differ.
Tariffs by customer class
The energy charge in each country's current tariff order, converted at the central bank rate on 30 October 2026. Sorted by the measure shown, lowest first. A tariff is a list of charges, not one number: some include VAT and levies, some add a fixed monthly charge or a monthly fuel and currency adjustment on top. Hover a bar to see what it includes.
Ethiopia raises its tariff every quarter and we have not yet found the step in force in November 2026, so it is left out. No published tariff grid was found for Sierra Leone, Mauritania, Chad, the Central African Republic, Gabon, São Tomé and Príncipe, the Comoros, Madagascar or Djibouti, so they are not in the chart. Nigeria shows Ikeja Electric's Band B rate (Band A, for feeders with 20 hours a day or more, is 209.50 naira). Kenya's energy charge excludes the monthly pass-through charges (KSh 4.16 per kWh in September 2026) and levies; Eskom's figures exclude VAT and serve its direct customers only (most households buy from municipalities); Namibia shows the City of Windhoek; Zimbabwe excludes the 6% rural electrification levy. Exchange rates: ZAR 16.64; ZMW 20.23; KES 129.89; MWK 1,734.01; NAD 16.64; LSL 16.64; SZL 16.64; UGX 4,351.09; TZS 2,640.73; RWF 1,475.00; BIF 3,013.13; BWP 13.46; MZN 64.19; AOA 913.00; ETB 160.94; XOF 587.14; XAF 587.14; NGN 1,346.00; GHS 11.66; GNF 8,829.00; GMD 72.17 per US dollar.
Utility, tariff, load shedding, reliability
Click a column heading to sort. Reliability is SAIDI, the average hours a customer goes without power in a year, where the utility or regulator publishes it.
| Country | Utility and regulator | Household US$/kWh | Block and date | Load shedding now | SAIDI |
|---|---|---|---|---|---|
| AngolaSAPP | ENDE (Empresa Nacional de Distribuicao de Electricidade)IRSEA | 0.01514.16 AOA | single ratedate not stated on page | None reportednothing found | |
| BotswanaSAPP | Botswana Power Corporation (BPC)Botswana Energy Regulatory Authority (BERA) | 0.1161.5637 BWP | B2: above 200 kWh2026-08-01 | Unclearload management program exists (10 A limit at peaks); active status not stated | |
| DR CongoSAPP | SNELARE (Autorite de regulation du secteur de l'electricite) | 0.0890.0888 USD | 1-600 kWh/monthdate not stated | Yesunscheduled cuts (delestage) in Kinshasa and other cities | |
| EswatiniSAPP | Eswatini Electricity Company (EEC)ESERA (Eswatini Energy Regulatory Authority) | 0.1722.8624 SZL | single rate2026/27 | Unclearwinter load management Jun-Aug (peaks 06:00-08:00, 17:00-20:00); none announced now | |
| LesothoSAPP | Lesotho Electricity Company (LEC)Lesotho Water and Electricity Authority (LEWA) | 0.1252.0816 LSL | single rate2025-04-01 | None reportednothing found | |
| MalawiSAPP | Electricity Supply Corporation of Malawi Limited (ESCOM)Malawi Energy Regulatory Authority (MERA) | 0.070122.25 MWK | above 50 kWh/month2026-01-19 | Yesload shedding (hours not published in source) | |
| MozambiqueSAPP | Electricidade de Mocambique (EDM)ARENE (Autoridade Reguladora de Energia) | 0.1036.63 MZNto confirm | 0-300 kWh/month2019-03-01 | Nonenone found (maintenance cuts only) | |
| NamibiaSAPP | City of Windhoek and other distributorsElectricity Control Board (ECB) | 0.1462.4298 NAD | single rate2026-09-01 | None reportednothing found | |
| South AfricaSAPP | Eskom Holdings SOC LtdNational Energy Regulator of South Africa (NERSA) | 0.1682.8005 ZAR | single rate2026-04-01 | Nonenone | 35.09hours, FY2026 (to 31 Mar 2026) |
| TanzaniaSAPP | TANESCOEWURA | 0.111292 TZS | single rate2016-04-01 | Nonenone (per parliamentary committee chair, Feb 2026) | 554minutes per customer per year, FY2023/24 |
| ZambiaSAPP | ZESCO LimitedEnergy Regulation Board (ERB) | 0.0491.00 ZMW | 100-200 kWh/month2025-11-01 | Unclearnot confirmed | 184hours, 2025 |
| ZimbabweSAPP | Zimbabwe Electricity Transmission and Distribution Company (ZETDC)Zimbabwe Energy Regulatory Authority (ZERA) | 0.1600.16 USDto confirm | 101-200 kWh/monthcurrent at 11 Nov 2026 (date of order not stated) | Nonenone (no widespread load shedding reported) | |
| EthiopiaEAPP | Ethiopian Electric Utility (EEU) | not found | None reportednothing found | ||
| KenyaEAPP | Kenya Power and Lighting Company PLC (KPLC)Energy and Petroleum Regulatory Authority (EPRA) | 0.12716.50 KES | 30-100 kWh/month2025-07-01 | Nonenone (scheduled) | 10.14hours, FY2023/24 |
| UgandaEAPP | UEDCLElectricity Regulatory Authority (ERA) | 0.179779.4 UGXto confirm | 16-80 kWh/month2026-10 to 2026-12 | Noneno scheduled load shedding found; frequent unplanned outages reported | |
| RwandaEAPP | Rwanda Energy Group (REG) / EUCLRURA | 0.210310 RWF | 20-50 kWh/month2025-10-01 | Nonenone found (planned maintenance only) | |
| BurundiEAPP | REGIDESOAREEN | 0.046138 BIFto confirm | 101-300 kWh2012-06-01 | Uncleargeneration deficit; no schedule found | |
| DjiboutiEAPP | Electricite de Djibouti (EDD) | not found | Nonenone found for 2026; outages tied to the Ethiopia line in Oct 2024 | ||
| NigeriaWest Africa | 11 distribution companies (DisCos), e.g. Ikeja ElectricNigerian Electricity Regulatory Commission (NERC); state regulators since the Electricity Act 2023 | 0.04662.48 NGN | feeders with 16+ hours/day2025-05-01 | Unclearnot confirmed for November 2026; DisCo load shedding reported Aug 2026 after a partial grid collapse | |
| GhanaWest Africa | ECG (south); NEDCo (north)Public Utilities Regulatory Commission (PURC); Energy Commission (licensing) | 0.1752.037509 GHS | 0-300 kWh/month2026-07-01 | Unclearnot confirmed for November 2026; curtailments without a timetable in Apr-May 2026 | |
| Cote d'IvoireWest Africa | CIE (concession)ANARE-CI | 0.12673.66 XOF | up to 180 x kVA per two monthsdate not stated on page | Unclearnot confirmed for November 2026; network-driven cuts in early 2026 | |
| SenegalWest Africa | SenelecCommission de Regulation du Secteur de l'Energie (CRSE) | 0.233136.49 XOF | 151-250 kWh/month2026-01-01 | Unclearended in Oct 2026 after a Sep-Oct deficit, per Senelec | |
| BeninWest Africa | SBEEAutorite de Regulation de l'Electricite (ARE) | 0.213125 XOF | 0-250 kWh2021-01 | Yesload shedding reported in Nov 2026 (import limits) | |
| TogoWest Africa | CEETAutorite de Reglementation du Secteur de l'Electricite (ARSE) | 0.15893 XOF | 31-120 kWh/month2025-05 | Unclearnot confirmed for November 2026; evening-peak cuts reported Jun and Oct 2026 | |
| Burkina FasoWest Africa | SONABELARSE (Burkina) | 0.16496 XOFto confirm | 0-50 kWh/month2023-10-01 | Unclearnot confirmed for November 2026; cuts are seasonal (Mar-May) | |
| NigerWest Africa | NIGELECAutorite de Regulation du Secteur de l'Energie (ARSE) | 0.11668.37 XOFto confirm | 0-150 kWh/month2018 structure, extended each year (2026 extension) | Unclearnot confirmed for November 2026; 40 MW plant added near Niamey in Jun 2026 | |
| GuineaWest Africa | Electricite de Guinee (EDG) | 0.044387 GNFto confirm | 41-330 kWh per 30 daysdate not stated (in force since at least 2022) | Yesunscheduled outages in Conakry reported again in Sep 2026 | |
| Sierra LeoneWest Africa | EDSA (distribution); EGTC (generation, transmission)Sierra Leone Electricity and Water Regulatory Commission (SLEWRC) | not found | Unclearnot confirmed for November 2026; Freetown load shedding reported Apr-May 2026 | ||
| LiberiaWest Africa | Liberia Electricity Corporation (LEC)Liberia Electricity Regulatory Commission (LERC) | 0.2200.22 USDto confirm | single rate2026-01-01 | Yesscheduled load shedding reported Sep 2026 | |
| The GambiaWest Africa | NAWECPublic Utilities Regulatory Authority (PURA) | 0.19213.85 GMD | 0-300 kWh/month2023-04-10 | Unclearnot confirmed for November 2026; supply crisis reported Jun 2026 | |
| MauritaniaWest Africa | SOMELECAutorite de Regulation (ARE) | not found | Unclearnot confirmed for November 2026; long cuts in Nouakchott Aug-Sep 2026 | ||
| CameroonCentral Africa | Eneo CameroonARSEL | 0.13579 XAF | 111-400 kWh/month2012 (ARSEL decision 0096, May 2012; prepaid banding Nov 2024) | Unclearnot confirmed for November 2026; dry-season rationing in the north from 20 Jan 2026 | |
| ChadCentral Africa | TchadElec | not found | Unclearnot confirmed for November 2026; persistent cuts in N'Djamena | ||
| Central African RepublicCentral Africa | Energie Centrafricaine (ENERCA) | not found | Yesunscheduled outages in Bangui reported Aug 2026 | ||
| Republic of the CongoCentral Africa | Energie Electrique du Congo (E2C)ARSEL (Congo), advisory only | 0.08449.08 XAF | single rate, all consumptiondate not stated | Unclearnot confirmed for November 2026; crisis after the Oct 2025 Imboulou breakdown | |
| GabonCentral Africa | SEEGARSEE | not found | Unclearnot confirmed for November 2026; persistent load shedding reported Feb 2026 | ||
| Sao Tome and PrincipeCentral Africa | EMAE | not found | Unclearnot confirmed for November 2026; rationing from Aug 2025 | ||
| MadagascarIndian Ocean | JIRAMAOffice de Regulation de l'Electricite (ORE) | not found | Yesscheduled load shedding; the Antananarivo grid was 23.5 MW short in Sep 2026 | ||
| ComorosIndian Ocean | SONELEC | not found | Unclearnot confirmed for November 2026; load shedding on Grande Comore in 2025 |
Load shedding, country by country
Each bar is an episode of scheduled load shedding or rationing, or a major unscheduled outage, from the start date to the end date the utility, regulator or press reported. An arrow means it had not been reported over at the time of our check. Drought years stand out: 2015/16 and 2019 on the Zambezi, 2019 at Gibe III in Ethiopia, and 2024 across the south.
Coverage is uneven: South Africa has hourly records (CSIR), Zambia has its regulator's yearly reports, and for most other countries the dates come from utility statements quoted in the press. A missing bar means we found no reported episode, not that there was none.
Method
- Sources. Tariffs come from the regulator's tariff order or the utility's published schedule; where neither was online we used a press report of the notice and mark it "to confirm". Load shedding comes from the utility, regulator or official statistics first, then from press reports quoting them.
- One exchange-rate date. All US dollar values use each central bank's rate on 30 October 2026. Where a central bank's site did not load we used an official cross rate on the same date (Burundi's central bank table for Uganda and Rwanda, South Africa's for Mozambique) or Kenya's tax authority weekly rate for Kenya. The CFA franc, Comorian franc, dobra and Djibouti franc are pegged, so they are converted at their peg and the European Central Bank euro rate on the same date. The Guinean franc uses a market rate and the Gambian dalasi the central bank rate of 4 September 2026, because the 30 October official rates were not found.
- No scores. We do not rank utilities or countries. The chart and table sort by one stated measure at a time.
- Kept current. Tariffs are checked every quarter and load shedding status every month.
Sources and updates
What changed 2 updates
- 16 November 2026 - Added 22 countries: Djibouti, Madagascar and 20 West and Central African countries. Tariffs from regulator or utility documents for 13 of them; no published grid found yet for the other nine. Utilities and regulators for all 22; load shedding status for all 22.
- November 2026 - First edition: 17 countries, tariffs in force at 12 November 2026, load shedding episodes since 2015, utilities register and published reliability figures.
Common questions
Which African country has the cheapest electricity?
By the household energy charge we collected, Angola at about US$0.015 per kWh. Low tariffs often mean the state covers part of the cost, and many of these utilities say their tariffs are below cost. Compare what each tariff includes before comparing the numbers.
Is there load shedding in South Africa now?
No. Eskom reported more than 540 days without load shedding by 9 November 2026. Some high-loss areas still have feeder-level "load reduction", which Eskom aims to end by March 2027.
Is there load shedding in Zambia now?
ZESCO's 2025 report says load management eased toward the end of 2025. We have not found a 2026 statement from ZESCO or the Energy Regulation Board confirming the current status, so the table shows it as unclear.
What is a lifeline tariff?
A low rate for the first few units a household uses each month, meant to keep basic lighting and phone charging affordable. Bands range from 15 kWh (Uganda) to 200 kWh (Botswana).
Can I use this data?
Yes. Our compiled table is published under CC BY 4.0; please credit Aloe Energy and the original regulator or utility. The underlying tariff orders are public documents. The data file is available on request by email.