Eastern Africa Power Pool
Kenya electricity grid and access
About 17 million people in Kenya live where satellites see no electric light at night, and 95% of them live within 15 km of a power line. This page brings together what our open atlases show for Kenya: about 7,477 km of high-voltage lines, 3,381 MW of power plants and the projects still to come.

Open the live atlas for Kenya Download the two-page brief (PDF) Distribution network map
Free A2 posters of Kenya’s grid: today and 2035 and beyond (PDF). All posters
Lines, substations and demand
Kenya's mapped high-voltage network runs to about 7,477 km of lines at 66 kV and above, with 65 substations. The highest voltage on the map is 500 kV, and 54% of the line length runs at 220 kV or more. About 498 km come from older World Bank (2017) maps, used where OpenStreetMap has gaps. Installed capacity was about 3,869 MW (Dec 2025), and peak demand about 2,439 MW (Dec 2025). The latest international tracking report puts access to electricity at 77% of people.
| Voltage | km |
|---|---|
| 500 kV | 612 |
| 400 kV | 1,213 |
| 220 kV | 1,932 |
| 132 kV | 2,712 |
| Voltage not recorded | 510 |
| Gap-fill from older public maps | 498 |
| Total | 7,477 |
Who lives near the grid but off it
About 17 million people in Kenya, roughly 31% of the population, live where satellites see no electric light at night. Of them, 95% live within 15 km of a mapped or predicted power line: 7.2 million within 2 km, 9.3 million 2 to 15 km away, and 889,000 farther out. The largest group lives 2 to 15 km out: close enough to plan for the grid, too far for a quick connection. That is where mini-grids built to join the grid later can do the most good. Solar home systems are common in Kenya, and they barely show at night from space, so this proxy overstates how many people have no power at all. At its 2016-2023 pace, about 3.7 percentage points a year (World Bank), Kenya would reach the 100% access target in its Mission 300 compact by 2030: on track.
- Within 2 km: 7.2 million (41%)
- 2 to 15 km: 9.3 million (54%)
- More than 15 km: 889,000 (5%)
See the numbers as a table
| Distance | Million people | Share |
|---|---|---|
| Within 2 km of a line | 7.19 | 41% |
| 2 to 15 km | 9.34 | 54% |
| More than 15 km | 0.89 | 5% |
| Total | 17.43 | 100% |
How we count this
"Without night-time light" is a satellite proxy, not a measured access rate. Distances are straight lines to mapped or predicted lines. See the grid-edge atlas for the method.
Power plants and projects
There are 43 operating power plants of 10 MW and above, adding up to about 3,381 MW. The largest is Lake Turkana wind farm (310 MW, wind). Another 39 plants totaling about 9,588 MW are under construction or planned, 113 MW of them under construction. Most of the pipeline is nuclear. One early-stage project, Tana River nuclear power plant, accounts for 42% of that, so the total says more about ambition than about what will be built soon. The largest plant under construction is Olkaria 1 geothermal power plant (63 MW, geothermal).
Three transmission projects touching Kenya are in our register.
- Kenya-Uganda Lessos-Tororo 400 kV (Kenyan section) (400 kV): under construction, expected 2027.
- Kenya PPP: Kibos-Kakamega-Musaga 220 kV (220 kV): procurement, expected 2028.
- Kenya PPP: Lessos-Loosuk 400 kV (400 kV): procurement, expected 2028.
| Type | Operating MW | Pipeline MW |
|---|---|---|
| Hydro | 803 | 1,010 |
| Oil | 830 | |
| Solar | 267 | 706 |
| Wind | 632 | 1,730 |
| Geothermal | 752 | 1,098 |
| Nuclear | 5,000 | |
| Biomass | 97 | 45 |
| Total | 3,381 | 9,588 |
More about Kenya
Open any topic for the full text and tables.
Mission 300What the energy compact commits to
Kenya's Mission 300 energy compact commits to raising electricity access from 75% to 100% by 2030. New access is planned as 96% grid, 4% mini-grids and 0% standalone solar. Each value is quoted, with its page, on our compacts page, where compacts sit side by side. Nothing is scored or ranked.
| Commitment | Value |
|---|---|
| Electricity access now | 75% (2024) |
| Access target | 100% by 2030 |
| Planned split of new access | grid 96%, mini-grids 4%, standalone solar 0% |
| Clean cooking target | from 34% to 100% by 2030 |
| Private investment sought | US$5.1 billion |
| Rules for mini-grids when the grid arrives | Mentioned only |
| E-waste commitment | Yes |
Waste to WealthSecond life for solar and batteries
Between 2026 and 2040, about 26,200 tonnes of solar equipment and stationary batteries are expected to retire in Kenya, most of it off-grid solar kits and mini-grids. That is 6.3% of the total for the 18 countries in our second-life atlas. Up to 35 MWh of retired batteries could be tested and reused as storage, for example in solar home systems, shops and mini-grids (0.8% of the atlas total). Eastern Africa and Madagascar have e-waste collection and dismantling, in Kenya and Rwanda, but no recycler for panels or lithium batteries yet, so this waste would have to travel to South Africa, mostly by sea to Durban.
| Stream | Tonnes | Share of country |
|---|---|---|
| Solar panels | 10,029 | 38% |
| Off-grid solar kits and mini-grids | 15,711 | 60% |
| Batteries | 444 | 2% |
| Total | 26,184 | 100% |
| Kenya | Atlas total | Share | |
|---|---|---|---|
| Retiring solar and batteries (tonnes) | 26,184 | 412,668 | 6.3% |
| Reusable battery storage (MWh) | 35 | 4,322 | 0.8% |
| Retiring in 2030 (tonnes) | 1,194 | ||
| Retiring in 2035 (tonnes) | 1,675 | ||
| Retiring in 2040 (tonnes) | 2,770 |
From our second-life atlas, central case, by country. Electric vehicle batteries are modeled for the region as a whole, so they are not in these country figures.
EmissionsGrid emission factor
Each megawatt-hour generated in Kenya in 2024 came with about 0.07 tonnes of CO2. For carbon projects such as solar mini-grids, the combined margin (the usual basis for crediting) is about 0.04 tCO2/MWh. Looking ahead, our scenarios from the plants in the pipeline put the average at 0.00 to 0.14 tCO2/MWh in 2030 and 0.00 to 0.14 in 2035, depending on how many plants arrive on time (see the scenarios). We have not yet rated the quality of its data. See our grid emission factors for the method and all 38 countries.
Grid mix, 2024. 10% of the electricity used is imported.
Oil and diesel 9% Hydro 23% Solar 5% Wind 16% Bioenergy 2% Geothermal and other 45%
Air in the city
Satellite-based estimates put fine particulate matter (PM2.5) in Nairobi, the capital, at about 19 µg/m³ on average in 2023, about 4 times the WHO guideline of 5, up from 15 in 2013. The WHO database has a ground measurement of 13 µg/m³ for 2021. On OpenAQ, 1 low-cost sensor in and around the city averaged about 20 over the 12 months to October 2026. Electric motorbikes and buses cut exhaust where people breathe it; see e-mobility for 71 cities.
| Measure | tCO2/MWh |
|---|---|
| Generated in country | 0.065 |
| Electricity used, with imports | 0.059 |
| Combined margin (for carbon projects) | 0.039 |
Tariffs and load sheddingWhat power costs here
Kenya Power's DC2 Ordinary tariff, in force from 1 July 2025. Our utilities, tariffs and load shedding page compares 39 African countries by customer class, with what each tariff includes and load shedding since 2015.
| Measure | Value |
|---|---|
| Lifeline or first block (0-30 kWh/month) | 12.14 KES/kWh, about US$0.093 |
| Household (30-100 kWh/month) | 16.50 KES/kWh, about US$0.127 |
| Load shedding now | None (scheduled) |
Energy charge only, at the central bank rate on 30 October 2026. Check what is included (VAT, levies, fixed charges) on the research page.
Certificates and carbon creditsRenewable energy certificates
Kenya can issue I-RECs, the international renewable energy certificate. 9 plants are registered (199 MW) and 676 GWh of certificates have been issued. On the voluntary carbon registries it has 346 carbon credit projects, 159 of them issuing, with about 85.4 million credits issued; 21 are renewable energy projects. Under the Paris Agreement it has 5 bilateral Article 6 agreements, 7 Article 6.2 activities and 17 activities approved for the UN's new crediting mechanism. Check it on the I-REC Standard site. See our certificates page to compare certificates with carbon credits across the region.
| Measure | Value |
|---|---|
| I-REC status | Issuing |
| Registered plants | 9 (199 MW) |
| I-RECs issued, all years | 676 GWh |
| Carbon credit projects | 346 |
| Carbon credits issued | 85.4 million |
I-RECs: Xpansiv I-REC Registry statistics, October 2026. Carbon projects: CarbonPlan OffsetsDB (Verra, Gold Standard and other voluntary registries), data to June 2026. Article 6: UNEP Copenhagen Climate Centre Article 6 Pipeline, November 2026.
Neighbors, sources and updates
Neighboring countries
More in the EAPP grid atlas, grid-edge atlas, second-life atlas, grid emission factors and Mission 300 compacts, or see all countries.
Sources 8 sources
- Grid lines: OpenStreetMap contributors (ODbL), with gap-fill from the World Bank Africa electricity grid (2017).
- Power plants: Global Energy Monitor, Global Integrated Power Tracker (September 2026), with WRI and curated public project sources.
- Capacity and access: national regulators and utilities, and the Tracking SDG7 Energy Progress Report 2026.
- People without night-time light and distance to the grid: WorldPop 2020 and gridfinder (Arderne et al. 2020, CC BY 4.0), as screened in our grid-edge atlas.
- Retiring solar and batteries: our second-life atlas model (central case, regular losses), from public project registers and IRENA lifetimes.
- City air: Atmospheric Composition Analysis Group, Washington University in St. Louis (PM2.5 V6.GL.02.04); WHO Ambient Air Quality Database 2026; OpenAQ (sensor data, November 2025 to October 2026).
- Emission factors: our grid emission factors (Ember, 2024).
- Compact commitments: the national Mission 300 energy compact, as quoted page by page on our compacts page.
The maps are free to view. The data behind this page is available on request: email [email protected]. Lines are indicative, not for engineering or investment decisions.
What changed 3 updates
Our data is checked every month, and this page is rebuilt after each check.
- 13 November 2026 - Latest update to the EAPP grid atlas, which this page is generated from.
- 2026 - Kenya PPP: Kibos-Kakamega-Musaga 220 kV: PS Alex Wachira, now expected construction from Aug 2026.
- 2026 - Kenya PPP: Lessos-Loosuk 400 kV: PS Alex Wachira, now expected construction from Aug 2026.
Common questions about Kenya
Where can I find a map of Kenya's electricity grid?
The free EAPP grid atlas maps Kenya's high-voltage lines, substations, power plants of 10 MW and above and planned projects. Open it zoomed to Kenya.
How many people in Kenya live without electricity?
About 17 million people live where satellites see no electric light at night, a proxy for living without power. Of them, 95% are within 15 km of a power line.
How long is Kenya's transmission network?
About 7,477 km of mapped lines at 66 kV and above, mostly from OpenStreetMap, with older public maps filling gaps.
How much power generation does Kenya have?
Operating plants of 10 MW and above add up to about 3,381 MW in our atlas, with about 9,588 MW more under construction or planned.
What is the grid emission factor for Kenya?
About 0.06 tCO2/MWh for electricity used in 2024, and 0.04 tCO2/MWh as a combined margin for carbon projects. See our grid emission factors for the method.
What is Kenya's Mission 300 energy compact target?
Kenya's Mission 300 energy compact commits to raising electricity access from 75% to 100% by 2030. New access is planned as 96% grid, 4% mini-grids and 0% standalone solar. See all compacts side by side on our compacts page.