What is on the map
This map combines our three regional atlases, rebuilt from them each month: the SAPP, EAPP and Madagascar grid atlases. Tanzania and DR Congo, members of both power pools, come from the SAPP atlas. OpenStreetMap extracts: 4 November 2026 for SAPP countries, 8 November 2026 for EAPP countries and Madagascar (Madagascar from 33 kV, because most of its grid is 63 and 35 kV). The notes below are from the SAPP atlas; each regional atlas lists its own sources.
Existing lines and substations: OpenStreetMap contributors (ODbL), extracted 4 November 2026, all power lines tagged 66 kV and above plus lines with no voltage tag. Coverage is uneven: South Africa is mapped in detail, Tanzania, DRC and Angola much less so.
Gap-fill: where a line in TANESCO's 2015 network (via the World Bank), the World Bank 2017 country grids for DRC and Mozambique, or the World Bank 2017 Africa grid is more than 3 km from any OSM line, the missing stretch is drawn dotted with its source and year. These can be out of date. Line lengths are mapped segment lengths, so a double circuit counts once.
Generation, 10 MW and above, merged without duplicates in this order: our curated register (projects we track with their date history), Global Energy Monitor's Global Integrated Power Tracker (September 2026 release, CC BY 4.0; units rolled up into one plant per status, cancelled, shelved, mothballed and retired units left out, and records GEM took from TransitionZero left out because their license is non-commercial), then the WRI Global Power Plant Database (2021), OpenStreetMap plants with a tagged capacity and the World Bank AICD inventory (about 2011), each only where nothing is already mapped nearby. Each plant says which source it came from. Each plant says which source it came from. Pipeline generation and transmission: SAPP monthly reports (Feb 2026), SAPP project portfolio (2023), World Bank, NTCSA GCCA and press. Each feature links its source.
Pipeline routes are drawn substation to substation and are indicative, not surveyed alignments. Where no public in-service date exists, the year is our estimate and is marked as such.
Constraints are qualitative flags from published SAPP and NTCSA material, not a load-flow study. Hosting capacity is only published for South Africa.
World Bank 2017 planned lines are kept as a record of the 2017 plan: many have since been built or dropped.
Towns in the search: GeoNames (CC BY 4.0), places with 1,000 or more people plus capitals and district seats. Distances from a town to the grid are straight-line distances to the nearest mapped line of 66 kV and above.
Map colors
Line colors follow the Southern African Power Pool's own grid map (SAPP grid map 2021, version 2): solid for existing lines, broken for proposed ones, with the same colour for each voltage. The interface uses Aloe Energy's palette.
Regional statistics and limits
Supply, demand, market prices and project updates: SAPP monthly report, August 2026. Planned against delivered capacity, 2022-26 committed capacity and the 2026 demand forecast: SAPP Annual Report 2022 (the latest published). Transfer limits: SAPP's published table (undated); endpoints are placed at the named substations and drawn as straight lines. Resource potential: IRENA (2021). Solar and wind grids: NASA POWER long-term climatology, about 1° resolution.
History and the master plan
The year slider runs from 2004, the first year of SAPP's yearly commissioning data. Looking back, plants appear in the year they were commissioned (WRI database, SAPP annual reports and the project register); plants with no known year stay faint. The transmission network is today's, because line build years are not in the open data. Capacity added per year: SAPP annual reports 2015 and 2022. Master plan: SAPP's draft Generation and Transmission Master Plan 2025-2045 (public consultation, chapters 0 and 4); its generation chapter is charts only, so plants are not listed from it. 2017 dates: SAPP Pool Plan 2017.
Comments
Use the comment control on this page. Every pipeline project has a short tag at the bottom of its popup (for example #moma or #caculo-cabaca); quote it so the thread points at the right project. Opening the page with that tag after the address jumps straight to it.
Deal stage and slippage
Stages run from concept to operating in eight steps. The slippage score compares the latest in-service year with the first one found in public sources; each date links to where it was said. Our own estimates are never scored.
Coming next
Demand and grid-arrival layer (settlements, mines, distance to grid), then quantified constraints (interconnector limits, hosting capacity, price spreads).