Cabo Verde electricity grid and access
About 42,000 people in Cabo Verde live where satellites see no electric light at night, and 38% of them live within 15 km of a power line. This page brings together what our open atlases show for Cabo Verde: 121 MW of power plants and the projects still to come.

Open the live atlas for Cabo Verde Download the country report (PDF, 0.2 MB, November 2026) Rapport pays en français (PDF, novembre 2026) Relatório do país em português (PDF, novembro de 2026) Distribution network map
Free A2 posters of Cabo Verde’s grid: today and 2035 and beyond (PDF). All posters
Lines, substations and demand
Our map shows no lines of 66 kV and above in Cabo Verde: its grids run at lower voltages, island by island. Installed capacity was about 177 MW (2024). The latest international tracking report puts access to electricity at 98% of people.
Who lives near the grid but off it
About 42,000 people in Cabo Verde, roughly 8% of the population, live where satellites see no electric light at night. Of them, 38% live within 15 km of a mapped or predicted power line: 2,000 within 2 km, 14,000 2 to 15 km away, and 26,000 farther out. The largest group lives more than 15 km from any line, where standalone solar and mini-grids are the realistic first step for years to come.
- Within 2 km: 2,000 (4%)
- 2 to 15 km: 14,000 (34%)
- More than 15 km: 26,000 (62%)
See the numbers as a table
| Distance | Million people | Share |
|---|---|---|
| Within 2 km of a line | 0.00 | 4% |
| 2 to 15 km | 0.01 | 34% |
| More than 15 km | 0.03 | 62% |
| Total | 0.04 | 100% |
How we count this
"Without night-time light" is a satellite proxy, not a measured access rate. Distances are straight lines to mapped or predicted lines. See the grid-edge atlas for the method.
Power plants and projects
Five operating power plants of 10 MW and above add up to about 121 MW, 82% of it oil. The largest is Palmarejo (66 MW, oil). Another 2 plants totaling about 20 MW are under construction or planned. Most of the pipeline is solar. One early-stage project, Chã Gonçalves solar farm, accounts for 50% of that, so the total says more about ambition than about what will be built soon.
| Type | Operating MW | Pipeline MW |
|---|---|---|
| Oil | 99 | |
| Solar | 10 | |
| Wind | 22 | 10 |
| Total | 121 | 20 |
More about Cabo Verde
Open any topic for the full text and tables.
Waste to WealthSecond life for solar and batteries
Between 2026 and 2040, about 643 tonnes of solar equipment and stationary batteries are expected to retire in Cabo Verde, most of it solar panels. That is 0.1% of the total for the 49 countries in our second-life atlas. Up to 12 MWh of retired batteries could be tested and reused as storage, for example in solar home systems, shops and mini-grids (0.3% of the atlas total). West and Central Africa have no recycler for panels or lithium batteries yet (one is planned in Ogun State, Nigeria), only e-waste collection in Accra, Lagos and Dakar and some lead-acid smelters, so for now this waste would be shipped abroad from the nearest seaport. Reuse comes first: Spiro already puts retired swap batteries to work as storage.
| Stream | Tonnes | Share of country |
|---|---|---|
| Solar panels | 354 | 55% |
| Off-grid solar kits and mini-grids | 101 | 16% |
| Batteries | 188 | 29% |
| Total | 643 | 100% |
| Cabo Verde | Atlas total | Share | |
|---|---|---|---|
| Retiring solar and batteries (tonnes) | 643 | 507,091 | 0.1% |
| Reusable battery storage (MWh) | 12 | 4,664 | 0.3% |
| Retiring in 2030 (tonnes) | 24 | ||
| Retiring in 2035 (tonnes) | 54 | ||
| Retiring in 2040 (tonnes) | 63 |
From our second-life atlas, central case, by country. Electric vehicle batteries are modeled for the region as a whole, so they are not in these country figures.
EmissionsGrid emission factor
Each megawatt-hour generated in Cabo Verde in 2024 came with about 0.53 tonnes of CO2. For carbon projects such as solar mini-grids, the combined margin (the usual basis for crediting) is about 0.38 tCO2/MWh. Looking ahead, our scenarios from the plants in the pipeline put the average at 0.47 to 0.52 tCO2/MWh in 2030 and 0.51 to 0.55 in 2035, depending on how many plants arrive on time (see the scenarios). We have not yet rated the quality of its data. See our grid emission factors for the method and all 49 countries.
Grid mix, 2024.
Oil and diesel 69% Solar 15% Wind 15%
| Measure | tCO2/MWh |
|---|---|
| Generated in country | 0.528 |
| Electricity used, with imports | 0.528 |
| Combined margin (for carbon projects) | 0.381 |
Tariffs and load sheddingWhat power costs here
EDEC's Baixa Tensao Domestica (BTD) tariff, in force from 1 August 2026. Our utilities, tariffs and load shedding page compares 49 African countries by customer class, with what each tariff includes and load shedding since 2015.
| Measure | Value |
|---|---|
| Lifeline or first block (0-30 kWh/month) | 19.50 CVE/kWh, about US$0.198 |
| Household (0-60 kWh/month) | 32.50 CVE/kWh, about US$0.329 |
| Load shedding now | No load shedding reports found (searched 19 Nov 2026) |
Energy charge only, at the central bank rate on 30 October 2026. Check what is included (VAT, levies, fixed charges) on the research page.
Grid consumptionWho uses the power on the grid
Households used about 36% of the country's electricity in 2023, by UN estimates. We have not found an official split by customer class yet. Our grid consumption page compares sales by customer class, power use per customer and peak demand across 49 African countries.
| Measure | Value |
|---|---|
| Households (UN) | 36% |
| Commercial and public (UN) | 48% |
| Industry (UN) | 16% |
| National use, UN 2023 | 446 GWh * |
UN: UN Energy Statistics Database (UNdata). * UN estimate or a single figure from a news report.
Certificates and carbon creditsRenewable energy certificates
Cabo Verde cannot issue I-RECs, the international renewable energy certificate, yet. On the voluntary carbon registries it has 1 carbon credit project, none of them issuing credits yet; 1 is a renewable energy project. Under the Paris Agreement it has 1 activity approved for the UN's new crediting mechanism. See our certificates page to compare certificates with carbon credits across the region.
| Measure | Value |
|---|---|
| I-REC status | Not approved |
| Registered plants | - |
| I-RECs issued, all years | - |
| Carbon credit projects | 1 |
| Carbon credits issued | - |
I-RECs: Xpansiv I-REC Registry statistics, October 2026. Carbon projects: CarbonPlan OffsetsDB (Verra, Gold Standard and other voluntary registries), data to June 2026. Article 6: UNEP Copenhagen Climate Centre Article 6 Pipeline, November 2026.
Lit but off the mapWhere the lights are and the map is not
Satellites see 79 lit places in Cabo Verde at night. 13 are within 2 km of a mapped line, 17 are 2 to 10 km away and 49 are 10 km or more from any mapped line. Places lit far from the map point to lines the map is missing, mines and plants with their own power, or mini-grids.
The lit places off the map cover about 296 km² and are home to about 81,860 people.
| Distance | Lit places | Newly lit |
|---|---|---|
| Within 2 km of a mapped line | 13 | |
| 2 to 10 km away | 17 | 12 |
| 10 km or more | 49 | 29 |
See them on the map: the "Lit but off the map" layer of the grid-edge atlas.
Climate and carbonCarbon per new connection
The Mission 300 compact for Cabo Verde adds about 2,400 new connections by 2030: 1,500 to the grid, 350 on mini-grids and 560 with solar home systems.
Counted with what household surveys show people use for light now (kerosene is the main light in 5% of homes without power), they avoid about 49 t of CO2 a year and add about 290 t from the power they use, a net addition of 241 t a year.
| Measure | Value |
|---|---|
| New connections by 2030 | 2,433 |
| CO2 avoided (t a year) | 49 |
| CO2 added (t a year) | 290 |
| Net CO2 avoided (t a year) | -241 |
| Net per 1,000 connections (t a year) | -99.2 |
The default methodology view and every source: carbon per connection.
Second lifeWho could use a second-life panel
Places in Cabo Verde that could use a second-life solar panel add up to about 46 MWp (range 21 to 105): 46 MWp to cut generator use in towns, 0 MWp for mini-grids, 0 MWp for household systems and 0.0 MWp for 1 health facilities and 0 schools with no light at night.
Mapped by half-degree cell, with years to 2040: where the panels are needed.
E-mobilityElectric transport, per km
On Cabo Verde's grid, an electric motorbike emits about 36 g of CO2 per km from the power it charges with, against 48 g for a petrol one (23% less).
| Vehicle | Electric | Petrol or diesel | Difference |
|---|---|---|---|
| Motorbike | 36 | 48 | -23% |
| Bus | 683 | 1,673 | -59% |
| Small car (newer petrol car) | 110 | 125 | -12% |
Life-cycle figures, a cost calculator and city air: e-mobility.
Neighbors, sources and updates
Sources 10 sources
- Grid lines: OpenStreetMap contributors (ODbL), with gap-fill from the World Bank Africa electricity grid (2017).
- Power plants: Global Energy Monitor, Global Integrated Power Tracker (September 2026), with WRI and curated public project sources.
- Capacity and access: national regulators and utilities, and the Tracking SDG7 Energy Progress Report 2026.
- People without night-time light and distance to the grid: WorldPop 2020 and gridfinder (Arderne et al. 2020, CC BY 4.0), as screened in our grid-edge atlas.
- Retiring solar and batteries: our second-life atlas model (central case, regular losses), from public project registers and IRENA lifetimes.
- Emission factors: our grid emission factors (Ember, 2024).
- Lit places: NASA Black Marble night lights, compared with our mapped lines (grid-edge atlas).
- Carbon per connection: compact targets, household lighting surveys (census, MICS, DHS, MTF) and our grid emission factors.
- Second-life demand: grid-edge screening, compact targets, World Bank Enterprise Surveys and health and school facility lists, in our second-life atlas.
- Transport per km: our grid emission factors and vehicle energy use; running costs from national pump prices and tariffs.
The maps are free to view. The data behind this page is available on request: email [email protected]. Lines are indicative, not for engineering or investment decisions.
More data
More in the WAPP grid atlas, grid-edge atlas, second-life atlas and grid emission factors, or see all countries.
What changed 4 updates
Our data is checked every month, and this page is rebuilt after each check.
- 19 November 2026 - Latest update to the WAPP grid atlas, which this page is generated from.
- 19 November 2026 - Latest update to the grid-edge atlas, which this page is generated from.
- 19 November 2026 - Lit but off the map now covers all 43 countries (Mali, Guinea-Bissau, Cabo Verde and Equatorial Guinea added, with their OpenStreetMap lines), and people around Chad's lit places now come from the building-based layer: 20,300 places 2 km or more from a mapped line, about 106 million people. The free download is now version 2: 20,647 places in 43 countries. Road distances for Mali, Guinea-Bissau, Cabo Verde, Equatorial Guinea, Djibouti and Comoros now feed the chance bands.
- 19 November 2026 - Mali, Guinea-Bissau, Cabo Verde and Equatorial Guinea added: 43 countries. Every country now counts people from buildings: Chad moves from WorldPop to Microsoft building footprints and Mali uses Overture Maps buildings, because Google's building data has none there. Headline: 633 million people without night-time light (was 617 M), 499 million of them within 15 km of a line (was 490 M). The lit-but-off-the-map layer still covers the first 39 countries.
Common questions about Cabo Verde
Where can I find a map of Cabo Verde's electricity grid?
The free WAPP grid atlas maps Cabo Verde's high-voltage lines, substations, power plants of 10 MW and above and planned projects. Open it zoomed to Cabo Verde.
How many people in Cabo Verde live without electricity?
About 42,000 people live where satellites see no electric light at night, a proxy for living without power. Of them, 38% are within 15 km of a power line.
How long is Cabo Verde's transmission network?
About 0 km of mapped lines at 66 kV and above, mostly from OpenStreetMap.
How much power generation does Cabo Verde have?
Operating plants of 10 MW and above add up to about 121 MW in our atlas, with about 20 MW more under construction or planned.
What is the grid emission factor for Cabo Verde?
About 0.53 tCO2/MWh for electricity used in 2024, and 0.38 tCO2/MWh as a combined margin for carbon projects. See our grid emission factors for the method.
Can I get the data for Cabo Verde?
Yes, on request. The maps are free to view; email [email protected] and tell us what you need it for.
Spotted an error, or something missing on this page? Report an issue or send feedback