Country data

West African Power Pool

Guinea-Bissau electricity grid and access

About 1.5 million people in Guinea-Bissau live where satellites see no electric light at night, and 19% of them live within 15 km of a power line. This page brings together what our open atlases show for Guinea-Bissau: about 219 km of high-voltage lines, 10 MW of power plants and the projects still to come.

1.5 Mpeople live without night-time light, a proxy for no power
19%of them live within 15 km of a power line
219km of high-voltage lines, 66 kV and above
10MW of operating power plants, 10 MW and above
3power plants and transmission lines planned or under construction
The grid today

Lines, substations and demand

Guinea-Bissau's mapped high-voltage network runs to about 219 km of lines at 66 kV and above, with 4 substations. The highest voltage on the map is 220 kV, and 100% of the line length runs at 220 kV or more. Installed capacity was about 10 MW (GEM Sep 2026). The latest international tracking report puts access to electricity at 44% of people.

Mapped line length
Voltagekm
220 kV219
Total219
Near the grid, not on it

Who lives near the grid but off it

About 1.5 million people in Guinea-Bissau, roughly 69% of the population, live where satellites see no electric light at night. Of them, 19% live within 15 km of a mapped or predicted power line: 103,000 within 2 km, 189,000 2 to 15 km away, and 1.2 million farther out. The largest group lives more than 15 km from any line, where standalone solar and mini-grids are the realistic first step for years to come.

  • Within 2 km: 103,000 (7%)
  • 2 to 15 km: 189,000 (12%)
  • More than 15 km: 1.2 million (81%)
See the numbers as a table
People without night-time light, by distance to a line
DistanceMillion peopleShare
Within 2 km of a line0.107%
2 to 15 km0.1912%
More than 15 km1.2381%
Total1.52100%
How we count this

"Without night-time light" is a satellite proxy, not a measured access rate. Distances are straight lines to mapped or predicted lines. See the grid-edge atlas for the method.

Generation and pipeline

Power plants and projects

One operating power plant of 10 MW and above adds up to about 10 MW, 100% of it solar. The largest is Helios Solar solar farm (10 MW, solar). Another 3 plants totaling about 63 MW are under construction or planned. Most of the pipeline is solar. One early-stage project, Bissau solar farm, accounts for 60% of that, so the total says more about ambition than about what will be built soon.

Power plants of 10 MW and above
TypeOperating MWPipeline MW
Solar1063
Total1063
Topics

More about Guinea-Bissau

Open any topic for the full text and tables.

Waste to Wealth

Second life for solar and batteries

Between 2026 and 2040, about 864 tonnes of solar equipment and stationary batteries are expected to retire in Guinea-Bissau, most of it off-grid solar kits and mini-grids.

Between 2026 and 2040, about 864 tonnes of solar equipment and stationary batteries are expected to retire in Guinea-Bissau, most of it off-grid solar kits and mini-grids. That is 0.2% of the total for the 49 countries in our second-life atlas. West and Central Africa have no recycler for panels or lithium batteries yet (one is planned in Ogun State, Nigeria), only e-waste collection in Accra, Lagos and Dakar and some lead-acid smelters, so for now this waste would be shipped abroad from the nearest seaport. Reuse comes first: Spiro already puts retired swap batteries to work as storage.

Solar and batteries retiring, 2026-2040 (tonnes)
StreamTonnesShare of country
Solar panels33939%
Off-grid solar kits and mini-grids52561%
Total864100%
Guinea-Bissau compared with the 49 countries in our second-life atlas, 2026-2040
Guinea-BissauAtlas totalShare
Retiring solar and batteries (tonnes)864507,0910.2%
Reusable battery storage (MWh)14,6640.0%
Retiring in 2030 (tonnes)41
Retiring in 2035 (tonnes)55
Retiring in 2040 (tonnes)79

From our second-life atlas, central case, by country. Electric vehicle batteries are modeled for the region as a whole, so they are not in these country figures.

Emissions

Grid emission factor

Each megawatt-hour generated in Guinea-Bissau in 2024 came with about 0.76 tonnes of CO2.

Each megawatt-hour generated in Guinea-Bissau in 2024 came with about 0.76 tonnes of CO2. For carbon projects such as solar mini-grids, the combined margin (the usual basis for crediting) is about 0.38 tCO2/MWh. Looking ahead, our scenarios from the plants in the pipeline put the average at 0.76 tCO2/MWh in 2030 and 0.76 in 2035, depending on how many plants arrive on time (see the scenarios). We have not yet rated the quality of its data. See our grid emission factors for the method and all 49 countries.

Grid mix, 2024.

Oil and diesel 100%

Grid emission factor, 2024 (tCO2/MWh)
MeasuretCO2/MWh
Generated in country0.762
Electricity used, with imports0.762
Combined margin (for carbon projects)0.381
Tariffs and load shedding

What power costs here

EAGB's BT Tarifa Normal tariff.

EAGB's BT Tarifa Normal tariff. Our utilities, tariffs and load shedding page compares 49 African countries by customer class, with what each tariff includes and load shedding since 2015.

Tariff and load shedding
MeasureValue
Lifeline or first block (0-50 kWh/month)81 XOF/kWh, about US$0.138
Household (0-200 kWh/month)128 XOF/kWh, about US$0.218
Load shedding nowNo 2026 load shedding reports found; Bissau supplied from the OMVG interconnector since Aug 2024

Energy charge only, at the central bank rate on 30 October 2026. Check what is included (VAT, levies, fixed charges) on the research page.

Grid consumption

Who uses the power on the grid

Households used about 45% of the country's electricity in 2023, by UN estimates.

Households used about 45% of the country's electricity in 2023, by UN estimates. We have not found an official split by customer class yet. Our grid consumption page compares sales by customer class, power use per customer and peak demand across 49 African countries.

Grid consumption
MeasureValue
Households (UN)45%
Commercial and public (UN)16%
Industry (UN)20%
Agriculture and other (UN)19%
National use, UN 2023174 GWh *

UN: UN Energy Statistics Database (UNdata). * UN estimate or a single figure from a news report.

Certificates and carbon credits

Renewable energy certificates

Guinea-Bissau cannot issue I-RECs, the international renewable energy certificate, yet.

Guinea-Bissau cannot issue I-RECs, the international renewable energy certificate, yet. On the voluntary carbon registries it has 2 carbon credit projects, 1 of them issuing, with about 0.3 million credits issued; none is a renewable energy project. See our certificates page to compare certificates with carbon credits across the region.

Certificates and carbon credits
MeasureValue
I-REC statusNot approved
Registered plants-
I-RECs issued, all years-
Carbon credit projects2
Carbon credits issued0.3 million

I-RECs: Xpansiv I-REC Registry statistics, October 2026. Carbon projects: CarbonPlan OffsetsDB (Verra, Gold Standard and other voluntary registries), data to June 2026. Article 6: UNEP Copenhagen Climate Centre Article 6 Pipeline, November 2026.

Lit but off the map

Where the lights are and the map is not

Satellites see 13 lit places in Guinea-Bissau at night. 4 are within 2 km of a mapped line, 1 are 2 to 10 km away and 8 are 10 km or more from any mapped line.

Satellites see 13 lit places in Guinea-Bissau at night. 4 are within 2 km of a mapped line, 1 are 2 to 10 km away and 8 are 10 km or more from any mapped line. Places lit far from the map point to lines the map is missing, mines and plants with their own power, or mini-grids.

The lit places off the map cover about 29 km² and are home to about 187,587 people.

Lit places by distance to a mapped line
DistanceLit placesNewly lit
Within 2 km of a mapped line4
2 to 10 km away11
10 km or more86

See them on the map: the "Lit but off the map" layer of the grid-edge atlas.

Climate and carbon

Carbon per new connection

The Mission 300 compact for Guinea-Bissau adds about 117,200 new connections by 2030: 73,100 to the grid, 17,100 on mini-grids and 27,100 with solar home systems.

The Mission 300 compact for Guinea-Bissau adds about 117,200 new connections by 2030: 73,100 to the grid, 17,100 on mini-grids and 27,100 with solar home systems.

Counted with what household surveys show people use for light now (kerosene is the main light in 5% of homes without power), they avoid about 2,340 t of CO2 a year and add about 20,000 t from the power they use, a net addition of 17,661 t a year.

New connections and CO2, central case
MeasureValue
New connections by 2030117,229
CO2 avoided (t a year)2,340
CO2 added (t a year)20,000
Net CO2 avoided (t a year)-17,661
Net per 1,000 connections (t a year)-150.7

The default methodology view and every source: carbon per connection.

Waste to Wealth

Power from waste

Guinea-Bissau's sugar mills, landfills, sewage works, factories and crop residues could make about 9 MW of power that is not built yet (central case), avoiding about 24,004 t of CO2e a year.

Guinea-Bissau's sugar mills, landfills, sewage works, factories and crop residues could make about 9 MW of power that is not built yet (central case), avoiding about 24,004 t of CO2e a year.

Power from waste by source (MW, central case)
SourceMW
City waste0.2
Crop and sawmill residues8.5

Every site, costs and the method: power from waste.

Second life

Who could use a second-life panel

Places in Guinea-Bissau that could use a second-life solar panel add up to about 108 MWp (range 48 to 243): 96 MWp to cut generator use in towns, 8 MWp for mini-grids, 4 MWp for household systems and 0.1 MWp for 2 health facilities and 1 schools with no light at night.

Places in Guinea-Bissau that could use a second-life solar panel add up to about 108 MWp (range 48 to 243): 96 MWp to cut generator use in towns, 8 MWp for mini-grids, 4 MWp for household systems and 0.1 MWp for 2 health facilities and 1 schools with no light at night.

Mapped by half-degree cell, with years to 2040: where the panels are needed.

E-mobility

Electric transport, per km

On Guinea-Bissau's grid, an electric motorbike emits about 53 g of CO2 per km from the power it charges with, against 48 g for a petrol one (10% more, because of how this grid makes its power).

On Guinea-Bissau's grid, an electric motorbike emits about 53 g of CO2 per km from the power it charges with, against 48 g for a petrol one (10% more, because of how this grid makes its power).

CO2 per km from use (g)
VehicleElectricPetrol or dieselDifference
Motorbike5348+10%
Bus9861,673-41%
Small car (newer petrol car)158125+26%

Life-cycle figures, a cost calculator and city air: e-mobility.

Reference

Neighbors, sources and updates

Sources 11 sources
  • Grid lines: OpenStreetMap contributors (ODbL), with gap-fill from the World Bank Africa electricity grid (2017).
  • Power plants: Global Energy Monitor, Global Integrated Power Tracker (September 2026), with WRI and curated public project sources.
  • Capacity and access: national regulators and utilities, and the Tracking SDG7 Energy Progress Report 2026.
  • People without night-time light and distance to the grid: WorldPop 2020 and gridfinder (Arderne et al. 2020, CC BY 4.0), as screened in our grid-edge atlas.
  • Retiring solar and batteries: our second-life atlas model (central case, regular losses), from public project registers and IRENA lifetimes.
  • Emission factors: our grid emission factors (Ember, 2024).
  • Lit places: NASA Black Marble night lights, compared with our mapped lines (grid-edge atlas).
  • Carbon per connection: compact targets, household lighting surveys (census, MICS, DHS, MTF) and our grid emission factors.
  • Power from waste: FAOSTAT, Global Energy Monitor and OpenStreetMap sites, in our waste-to-energy model.
  • Second-life demand: grid-edge screening, compact targets, World Bank Enterprise Surveys and health and school facility lists, in our second-life atlas.
  • Transport per km: our grid emission factors and vehicle energy use; running costs from national pump prices and tariffs.

The maps are free to view. The data behind this page is available on request: email [email protected]. Lines are indicative, not for engineering or investment decisions.

What changed 4 updates

Our data is checked every month, and this page is rebuilt after each check.

  • 19 November 2026 - Latest update to the WAPP grid atlas, which this page is generated from.
  • 19 November 2026 - Latest update to the grid-edge atlas, which this page is generated from.
  • 19 November 2026 - Lit but off the map now covers all 43 countries (Mali, Guinea-Bissau, Cabo Verde and Equatorial Guinea added, with their OpenStreetMap lines), and people around Chad's lit places now come from the building-based layer: 20,300 places 2 km or more from a mapped line, about 106 million people. The free download is now version 2: 20,647 places in 43 countries. Road distances for Mali, Guinea-Bissau, Cabo Verde, Equatorial Guinea, Djibouti and Comoros now feed the chance bands.
  • 19 November 2026 - Mali, Guinea-Bissau, Cabo Verde and Equatorial Guinea added: 43 countries. Every country now counts people from buildings: Chad moves from WorldPop to Microsoft building footprints and Mali uses Overture Maps buildings, because Google's building data has none there. Headline: 633 million people without night-time light (was 617 M), 499 million of them within 15 km of a line (was 490 M). The lit-but-off-the-map layer still covers the first 39 countries.

Common questions about Guinea-Bissau

Where can I find a map of Guinea-Bissau's electricity grid?

The free WAPP grid atlas maps Guinea-Bissau's high-voltage lines, substations, power plants of 10 MW and above and planned projects. Open it zoomed to Guinea-Bissau.

How many people in Guinea-Bissau live without electricity?

About 1.5 million people live where satellites see no electric light at night, a proxy for living without power. Of them, 19% are within 15 km of a power line.

How long is Guinea-Bissau's transmission network?

About 219 km of mapped lines at 66 kV and above, mostly from OpenStreetMap.

How much power generation does Guinea-Bissau have?

Operating plants of 10 MW and above add up to about 10 MW in our atlas, with about 63 MW more under construction or planned.

What is the grid emission factor for Guinea-Bissau?

About 0.76 tCO2/MWh for electricity used in 2024, and 0.38 tCO2/MWh as a combined margin for carbon projects. See our grid emission factors for the method.

Can I get the data for Guinea-Bissau?

Yes, on request. The maps are free to view; email [email protected] and tell us what you need it for.

Spotted an error, or something missing on this page? Report an issue or send feedback