Country data

Eastern Africa Power Pool

Burundi electricity grid and access

About 10 million people in Burundi live where satellites see no electric light at night, and 99% of them live within 15 km of a power line. This page brings together what our open atlases show for Burundi: about 480 km of high-voltage lines, 224 MW of power plants and the projects still to come.

10 Mpeople live without night-time light, a proxy for no power
99%of them live within 15 km of a power line
480km of high-voltage lines, 66 kV and above
224MW of operating power plants, 10 MW and above
3power plants and transmission lines planned or under construction
The grid today

Lines, substations and demand

Burundi's mapped high-voltage network runs to about 480 km of lines at 66 kV and above, with 9 substations. The highest voltage on the map is 220 kV, and 22% of the line length runs at 220 kV or more. Installed capacity was about 166 MW (2025). The latest international tracking report puts access to electricity at 20% of people.

Mapped line length
Voltagekm
220 kV100
110 kV195
66 kV113
Voltage not recorded39
Gap-fill from older public maps33
Total480
Near the grid, not on it

Who lives near the grid but off it

About 10 million people in Burundi, roughly 72% of the population, live where satellites see no electric light at night. Of them, 99% live within 15 km of a mapped or predicted power line: 3.3 million within 2 km, 6.6 million 2 to 15 km away, and 148,000 farther out. The largest group lives 2 to 15 km out: close enough to plan for the grid, too far for a quick connection. That is where mini-grids built to join the grid later can do the most good. At its 2016-2023 pace, about 0.3 percentage points a year (World Bank), Burundi would reach the 70% access target in its Mission 300 compact after 2050, not 2030; the target needs about 8.3 points a year.

  • Within 2 km: 3.3 million (33%)
  • 2 to 15 km: 6.6 million (66%)
  • More than 15 km: 148,000 (1%)
See the numbers as a table
People without night-time light, by distance to a line
DistanceMillion peopleShare
Within 2 km of a line3.3233%
2 to 15 km6.6166%
More than 15 km0.151%
Total10.07100%
How we count this

"Without night-time light" is a satellite proxy, not a measured access rate. Distances are straight lines to mapped or predicted lines. See the grid-edge atlas for the method.

Generation and pipeline

Power plants and projects

Eight operating power plants of 10 MW and above add up to about 224 MW, 51% of it hydro. The largest is Mamba Hakan (Peatpower Plant) (80 MW, other).

Three transmission projects touching Burundi are in our register.

  • Rwanda-Burundi 220 kV (Kigoma-Butare-Ngozi-Gitega) (220 kV): under construction, expected 2027.
  • Burundi-DR Congo 220 kV (Kamanyola-Bujumbura) (220 kV): under construction, expected 2028.
  • Ruzizi III 220 kV evacuation (220 kV): financed, expected 2030.
Power plants of 10 MW and above
TypeOperating MWPipeline MW
Hydro114
Gas30
Other80
Total2240
Topics

More about Burundi

Open any topic for the full text and tables.

Mission 300

What the energy compact commits to

Burundi's Mission 300 energy compact commits to raising electricity access from 26% to 70% by 2030.

Burundi's Mission 300 energy compact commits to raising electricity access from 26% to 70% by 2030. New access is planned as 60% grid, 13% mini-grids and 27% standalone solar. Each value is quoted, with its page, on our compacts page, where compacts sit side by side. Nothing is scored or ranked.

Mission 300 energy compact
CommitmentValue
Electricity access now26% (2025)
Access target70% by 2030
Planned split of new accessgrid 60%, mini-grids 13%, standalone solar 27%
Clean cooking target40% by 2030
Private investment soughtUS$1.54 billion
Rules for mini-grids when the grid arrivesYes
E-waste commitmentYes
Waste to Wealth

Second life for solar and batteries

Between 2026 and 2040, about 1,200 tonnes of solar equipment and stationary batteries are expected to retire in Burundi, most of it off-grid solar kits and mini-grids.

Between 2026 and 2040, about 1,200 tonnes of solar equipment and stationary batteries are expected to retire in Burundi, most of it off-grid solar kits and mini-grids. That is 0.3% of the total for the 18 countries in our second-life atlas. Eastern Africa and Madagascar have e-waste collection and dismantling, in Kenya and Rwanda, but no recycler for panels or lithium batteries yet, so this waste would have to travel to South Africa, mostly by sea to Durban.

Solar and batteries retiring, 2026-2040 (tonnes)
StreamTonnesShare of country
Solar panels22619%
Off-grid solar kits and mini-grids98881%
Total1,214100%
Burundi compared with the 18 countries in our second-life atlas, 2026-2040
BurundiAtlas totalShare
Retiring solar and batteries (tonnes)1,214412,6680.3%
Reusable battery storage (MWh)04,3220.0%
Retiring in 2030 (tonnes)68
Retiring in 2035 (tonnes)74
Retiring in 2040 (tonnes)92

From our second-life atlas, central case, by country. Electric vehicle batteries are modeled for the region as a whole, so they are not in these country figures.

Emissions

Grid emission factor

Each megawatt-hour generated in Burundi in 2024 came with about 0.19 tonnes of CO2.

Each megawatt-hour generated in Burundi in 2024 came with about 0.19 tonnes of CO2. Counting imported power, the factor for electricity used in the country is about 0.16 tCO2/MWh, with imports making up 14% of supply. For carbon projects such as solar mini-grids, the combined margin (the usual basis for crediting) is about 0.21 tCO2/MWh. Looking ahead, our scenarios from the plants in the pipeline put the average at 0.26 tCO2/MWh in 2030 and 0.26 in 2035, depending on how many plants arrive on time (see the scenarios). We have not yet rated the quality of its data. See our grid emission factors for the method and all 38 countries.

Grid mix, 2024. 14% of the electricity used is imported.

Oil and diesel 24% Hydro 73% Bioenergy 2%

Air in the city

Satellite-based estimates put fine particulate matter (PM2.5) in Gitega, the capital, at about 24 µg/m³ on average in 2023, about 5 times the WHO guideline of 5, down from 39 in 2013. In Bujumbura, the largest city, it was about 28. The WHO database has no ground measurement for the city. Electric motorbikes and buses cut exhaust where people breathe it; see e-mobility for 71 cities.

Grid emission factor, 2024 (tCO2/MWh)
MeasuretCO2/MWh
Generated in country0.187
Electricity used, with imports0.161
Combined margin (for carbon projects)0.209
Tariffs and load shedding

What power costs here

REGIDESO's LV households (bimonthly billing) tariff, in force from 1 June 2012.

REGIDESO's LV households (bimonthly billing) tariff, in force from 1 June 2012. Our utilities, tariffs and load shedding page compares 39 African countries by customer class, with what each tariff includes and load shedding since 2015.

Tariff and load shedding
MeasureValue
Lifeline or first block (0-100 kWh)68 BIF/kWh, about US$0.023
Household (101-300 kWh)138 BIF/kWh, about US$0.046
Load shedding nowGeneration deficit; no schedule found

Energy charge only, at the central bank rate on 30 October 2026. Check what is included (VAT, levies, fixed charges) on the research page.

Certificates and carbon credits

Renewable energy certificates

Burundi is approved to issue I-RECs, the international renewable energy certificate, but none have been issued yet.

Burundi is approved to issue I-RECs, the international renewable energy certificate, but none have been issued yet. On the voluntary carbon registries it has 14 carbon credit projects, 5 of them issuing, with about 4.8 million credits issued; 3 are renewable energy projects. Under the Paris Agreement it has 1 activity approved for the UN's new crediting mechanism. Check it on the I-REC Standard site. See our certificates page to compare certificates with carbon credits across the region.

Certificates and carbon credits
MeasureValue
I-REC statusApproved, nothing issued yet
Registered plants-
I-RECs issued, all years-
Carbon credit projects14
Carbon credits issued4.8 million

I-RECs: Xpansiv I-REC Registry statistics, October 2026. Carbon projects: CarbonPlan OffsetsDB (Verra, Gold Standard and other voluntary registries), data to June 2026. Article 6: UNEP Copenhagen Climate Centre Article 6 Pipeline, November 2026.

Reference

Neighbors, sources and updates

Sources 8 sources
  • Grid lines: OpenStreetMap contributors (ODbL), with gap-fill from the World Bank Africa electricity grid (2017).
  • Power plants: Global Energy Monitor, Global Integrated Power Tracker (September 2026), with WRI and curated public project sources.
  • Capacity and access: national regulators and utilities, and the Tracking SDG7 Energy Progress Report 2026.
  • People without night-time light and distance to the grid: WorldPop 2020 and gridfinder (Arderne et al. 2020, CC BY 4.0), as screened in our grid-edge atlas.
  • Retiring solar and batteries: our second-life atlas model (central case, regular losses), from public project registers and IRENA lifetimes.
  • City air: Atmospheric Composition Analysis Group, Washington University in St. Louis (PM2.5 V6.GL.02.04); WHO Ambient Air Quality Database 2026.
  • Emission factors: our grid emission factors (Ember, 2024).
  • Compact commitments: the national Mission 300 energy compact, as quoted page by page on our compacts page.

The maps are free to view. The data behind this page is available on request: email [email protected]. Lines are indicative, not for engineering or investment decisions.

What changed 2 updates

Our data is checked every month, and this page is rebuilt after each check.

  • 13 November 2026 - Latest update to the EAPP grid atlas, which this page is generated from.
  • Jun 2026 - Ruzizi III 220 kV evacuation: KT Press, now expected 2030.

Common questions about Burundi

Where can I find a map of Burundi's electricity grid?

The free EAPP grid atlas maps Burundi's high-voltage lines, substations, power plants of 10 MW and above and planned projects. Open it zoomed to Burundi.

How many people in Burundi live without electricity?

About 10 million people live where satellites see no electric light at night, a proxy for living without power. Of them, 99% are within 15 km of a power line.

How long is Burundi's transmission network?

About 480 km of mapped lines at 66 kV and above, mostly from OpenStreetMap.

How much power generation does Burundi have?

Operating plants of 10 MW and above add up to about 224 MW in our atlas.

What is the grid emission factor for Burundi?

About 0.16 tCO2/MWh for electricity used in 2024, and 0.21 tCO2/MWh as a combined margin for carbon projects. See our grid emission factors for the method.

What is Burundi's Mission 300 energy compact target?

Burundi's Mission 300 energy compact commits to raising electricity access from 26% to 70% by 2030. New access is planned as 60% grid, 13% mini-grids and 27% standalone solar. See all compacts side by side on our compacts page.

Can I get the data for Burundi?

Yes, on request. The maps are free to view; email [email protected] and tell us what you need it for.