Country data

Southern African Power Pool

Lesotho electricity grid and access

About 1.1 million people in Lesotho live where satellites see no electric light at night, and 88% of them live within 15 km of a power line. This page brings together what our open atlases show for Lesotho: about 636 km of high-voltage lines, 102 MW of power plants and the projects still to come.

1.1 Mpeople live without night-time light, a proxy for no power
88%of them live within 15 km of a power line
636km of high-voltage lines, 66 kV and above
102MW of operating power plants, 10 MW and above
5power plants and transmission lines planned or under construction
The grid today

Lines, substations and demand

Lesotho's mapped high-voltage network runs to about 636 km of lines at 66 kV and above, with 24 substations. The highest voltage on the map is 132 kV. In August 2026, SAPP reported a peak demand of 206 MW against 76 MW available.

Mapped line length
Voltagekm
132 kV503
88 kV60
66 kV59
Voltage not recorded5
Gap-fill from older public maps10
Total636
Near the grid, not on it

Who lives near the grid but off it

About 1.1 million people in Lesotho, roughly 48% of the population, live where satellites see no electric light at night. Of them, 88% live within 15 km of a mapped or predicted power line: 360,000 within 2 km, 628,000 2 to 15 km away, and 133,000 farther out. The largest group lives 2 to 15 km out: close enough to plan for the grid, too far for a quick connection. That is where mini-grids built to join the grid later can do the most good. At its 2016-2023 pace, about 3.0 percentage points a year (World Bank), Lesotho would reach the 100% access target in its Mission 300 compact around 2037, not 2030; the target needs about 6.1 points a year.

  • Within 2 km: 360,000 (32%)
  • 2 to 15 km: 628,000 (56%)
  • More than 15 km: 133,000 (12%)
See the numbers as a table
People without night-time light, by distance to a line
DistanceMillion peopleShare
Within 2 km of a line0.3632%
2 to 15 km0.6356%
More than 15 km0.1312%
Total1.12100%
How we count this

"Without night-time light" is a satellite proxy, not a measured access rate. Distances are straight lines to mapped or predicted lines. See the grid-edge atlas for the method.

Generation and pipeline

Power plants and projects

Two operating power plants of 10 MW and above add up to about 102 MW, 71% of it hydro. The largest is 'Muela (72 MW, hydro). Another 5 plants totaling about 340 MW are under construction or planned.

Power plants of 10 MW and above
TypeOperating MWPipeline MW
Hydro7280
Solar30140
Wind120
Total102340
Topics

More about Lesotho

Open any topic for the full text and tables.

Mission 300

What the energy compact commits to

Lesotho's Mission 300 energy compact commits to raising electricity access from 53% to 100% by 2030.

Lesotho's Mission 300 energy compact commits to raising electricity access from 53% to 100% by 2030. New access is planned as 58% grid, 2% mini-grids and 40% standalone solar. Each value is quoted, with its page, on our compacts page, where compacts sit side by side. Nothing is scored or ranked.

Mission 300 energy compact
CommitmentValue
Electricity access now53% (2024)
Access target100% by 2030
Planned split of new accessgrid 58%, mini-grids 2%, standalone solar 40%
Clean cooking targetfrom 45% to 75% by 2030
Private investment soughtUS$1.47 billion
Rules for mini-grids when the grid arrivesMentioned only
E-waste commitmentNo
Waste to Wealth

Second life for solar and batteries

Between 2026 and 2040, about 510 tonnes of solar equipment and stationary batteries are expected to retire in Lesotho, most of it solar panels.

Between 2026 and 2040, about 510 tonnes of solar equipment and stationary batteries are expected to retire in Lesotho, most of it solar panels. That is 0.1% of the total for the 18 countries in our second-life atlas. Today the nearest recyclers for panels and lithium batteries are in Gauteng and Cape Town, so most of this waste would travel far and cross borders.

Solar and batteries retiring, 2026-2040 (tonnes)
StreamTonnesShare of country
Solar panels38275%
Off-grid solar kits and mini-grids12825%
Total510100%
Lesotho compared with the 18 countries in our second-life atlas, 2026-2040
LesothoAtlas totalShare
Retiring solar and batteries (tonnes)510412,6680.1%
Reusable battery storage (MWh)04,3220.0%
Retiring in 2030 (tonnes)17
Retiring in 2035 (tonnes)20
Retiring in 2040 (tonnes)55

From our second-life atlas, central case, by country. Electric vehicle batteries are modeled for the region as a whole, so they are not in these country figures.

Emissions

Grid emission factor

Each megawatt-hour generated in Lesotho in 2024 came with close to zero tonnes of CO2.

Each megawatt-hour generated in Lesotho in 2024 came with close to zero tonnes of CO2. Counting imported power, the factor for electricity used in the country is about 0.36 tCO2/MWh, with imports making up 50% of supply. For carbon projects such as solar mini-grids, the combined margin (the usual basis for crediting) is close to zero tCO2/MWh. Looking ahead, our scenarios from the plants in the pipeline put the average at 0.00 tCO2/MWh in 2030 and 0.00 in 2035, depending on how many plants arrive on time (see the scenarios). Data quality is rated good. See our grid emission factors for the method and all 38 countries.

Grid mix, 2024. 50% of the electricity used is imported.

Hydro 99% Solar 1%

Air in the city

Satellite-based estimates put fine particulate matter (PM2.5) in Maseru, the capital, at about 21 µg/m³ on average in 2023, about 4 times the WHO guideline of 5, down from 36 in 2013. On OpenAQ, 1 low-cost sensor in and around the city averaged about 19 over the 12 months to October 2026. Electric motorbikes and buses cut exhaust where people breathe it; see e-mobility for 71 cities.

Grid emission factor, 2024 (tCO2/MWh)
MeasuretCO2/MWh
Generated in country0.000
Electricity used, with imports0.364
Combined margin (for carbon projects)0.000
Tariffs and load shedding

What power costs here

Lesotho Electricity Company (LEC)'s Domestic tariff, in force from 1 April 2025.

Lesotho Electricity Company (LEC)'s Domestic tariff, in force from 1 April 2025. Our utilities, tariffs and load shedding page compares 39 African countries by customer class, with what each tariff includes and load shedding since 2015.

Tariff and load shedding
MeasureValue
Lifeline or first block (single rate)0.9304 LSL/kWh, about US$0.056
Household (single rate)2.0816 LSL/kWh, about US$0.125
Load shedding nowNothing found

Energy charge only, at the central bank rate on 30 October 2026. Check what is included (VAT, levies, fixed charges) on the research page.

Certificates and carbon credits

Renewable energy certificates

Lesotho is approved to issue I-RECs, the international renewable energy certificate, but none have been issued yet.

Lesotho is approved to issue I-RECs, the international renewable energy certificate, but none have been issued yet. On the voluntary carbon registries it has 5 carbon credit projects, 1 of them issuing, with about 0.3 million credits issued; 0 are renewable energy projects. Check it on the I-REC Standard site. See our certificates page to compare certificates with carbon credits across the region.

Certificates and carbon credits
MeasureValue
I-REC statusApproved, nothing issued yet
Registered plants-
I-RECs issued, all years-
Carbon credit projects5
Carbon credits issued0.3 million

I-RECs: Xpansiv I-REC Registry statistics, October 2026. Carbon projects: CarbonPlan OffsetsDB (Verra, Gold Standard and other voluntary registries), data to June 2026. Article 6: UNEP Copenhagen Climate Centre Article 6 Pipeline, November 2026.

Reference

Neighbors, sources and updates

Sources 8 sources
  • Grid lines: OpenStreetMap contributors (ODbL), with gap-fill from the World Bank Africa electricity grid (2017).
  • Power plants: Global Energy Monitor, Global Integrated Power Tracker (September 2026), with WRI and curated public project sources.
  • Supply and demand: SAPP monthly report (August 2026).
  • People without night-time light and distance to the grid: WorldPop 2020 and gridfinder (Arderne et al. 2020, CC BY 4.0), as screened in our grid-edge atlas.
  • Retiring solar and batteries: our second-life atlas model (central case, regular losses), from public project registers and IRENA lifetimes.
  • City air: Atmospheric Composition Analysis Group, Washington University in St. Louis (PM2.5 V6.GL.02.04); WHO Ambient Air Quality Database 2026; OpenAQ (sensor data, November 2025 to October 2026).
  • Emission factors: our grid emission factors (World Bank PID P513939, 2024).
  • Compact commitments: the national Mission 300 energy compact, as quoted page by page on our compacts page.

The maps are free to view. The data behind this page is available on request: email [email protected]. Lines are indicative, not for engineering or investment decisions.

What changed

Our data is checked every month, and this page is rebuilt after each check.

  • 16 November 2026 - Latest update to the SAPP grid atlas, which this page is generated from.

Common questions about Lesotho

Where can I find a map of Lesotho's electricity grid?

The free SAPP grid atlas maps Lesotho's high-voltage lines, substations, power plants of 10 MW and above and planned projects. Open it zoomed to Lesotho.

How many people in Lesotho live without electricity?

About 1.1 million people live where satellites see no electric light at night, a proxy for living without power. Of them, 88% are within 15 km of a power line.

How long is Lesotho's transmission network?

About 636 km of mapped lines at 66 kV and above, mostly from OpenStreetMap.

How much power generation does Lesotho have?

Operating plants of 10 MW and above add up to about 102 MW in our atlas, with about 340 MW more under construction or planned.

What is the grid emission factor for Lesotho?

About 0.36 tCO2/MWh for electricity used in 2024, and 0.00 tCO2/MWh as a combined margin for carbon projects. See our grid emission factors for the method.

What is Lesotho's Mission 300 energy compact target?

Lesotho's Mission 300 energy compact commits to raising electricity access from 53% to 100% by 2030. New access is planned as 58% grid, 2% mini-grids and 40% standalone solar. See all compacts side by side on our compacts page.

Can I get the data for Lesotho?

Yes, on request. The maps are free to view; email [email protected] and tell us what you need it for.