About 1.5 million people in Namibia live where satellites see no electric light at night, and 92% of them live within 15 km of a power line. This page brings together what our open atlases show for Namibia: about 11,536 km of high-voltage lines, 869 MW of power plants and the projects still to come.

1.5 Mpeople live without night-time light, a proxy for no power
92%of them live within 15 km of a power line
11,536km of high-voltage lines, 66 kV and above
869MW of operating power plants, 10 MW and above
48power plants and transmission lines planned or under construction
The grid today

Lines, substations and demand

Namibia's mapped high-voltage network runs to about 11,536 km of lines at 66 kV and above, with 60 substations. The highest voltage on the map is 400 kV, and 47% of the line length runs at 220 kV or more. In August 2026, SAPP reported a peak demand of 672 MW against 490 MW available.

Mapped line length
Voltagekm
400 kV1,406
350 kV952
330 kV524
220 kV2,570
132 kV2,359
66 kV3,480
Voltage not recorded245
Total11,536
Near the grid, not on it

Who lives near the grid but off it

About 1.5 million people in Namibia, roughly 50% of the population, live where satellites see no electric light at night. Of them, 92% live within 15 km of a mapped or predicted power line: 658,000 within 2 km, 737,000 2 to 15 km away, and 117,000 farther out. The largest group lives 2 to 15 km out: close enough to plan for the grid, too far for a quick connection. That is where mini-grids built to join the grid later can do the most good. At its 2016-2023 pace, about 0.9 percentage points a year (World Bank), Namibia would reach the 70% access target in its Mission 300 compact around 2038, not 2030; the target needs about 1.9 points a year.

  • Within 2 km: 658,000 (44%)
  • 2 to 15 km: 737,000 (49%)
  • More than 15 km: 117,000 (8%)
See the numbers as a table
People without night-time light, by distance to a line
DistanceMillion peopleShare
Within 2 km of a line0.6644%
2 to 15 km0.7449%
More than 15 km0.128%
Total1.51100%
How we count this

"Without night-time light" is a satellite proxy, not a measured access rate. Distances are straight lines to mapped or predicted lines. See the grid-edge atlas for the method.

Generation and pipeline

Power plants and projects

There are 19 operating power plants of 10 MW and above, adding up to about 869 MW, 41% of it solar. The largest is Ruacana hydroelectric plant (332 MW, hydro). Another 43 plants totaling about 24,144 MW are under construction or planned, 7,417 MW of them under construction. Most of the pipeline is solar. The largest plant under construction is Daures Green Hydrogen Village solar farm (3,500 MW, solar).

Five transmission projects touching Namibia are in our register.

  • Angola-Namibia interconnector (ANNA) (400 kV): procurement, expected 2029.
  • ZiZaBoNa interconnector (330 kV): feasibility done, expected 2030.
  • Baynes HPP transmission lines (400 kV): feasibility.
  • Baynes HPP transmission lines (Namibia leg) (400 kV): feasibility.
  • Botswana-Namibia interconnector: pre-feasibility, data collection.
Power plants of 10 MW and above
TypeOperating MWPipeline MW
Hydro3321,761
Coal120
Gas50475
Oil10
Solar35714,242
Wind7,586
Biomass80
Total86924,144
Topics

More about Namibia

Open any topic for the full text and tables.

Mission 300

What the energy compact commits to

Namibia's Mission 300 energy compact commits to raising electricity access from 60% to 70% by 2030.

Namibia's Mission 300 energy compact commits to raising electricity access from 60% to 70% by 2030. Each value is quoted, with its page, on our compacts page, where compacts sit side by side. Nothing is scored or ranked.

Mission 300 energy compact
CommitmentValue
Electricity access now60% (2023)
Access target70% by 2030
Clean cooking targetfrom 48% to 61% by 2030
Private investment soughtUS$0.411 billion
Rules for mini-grids when the grid arrivesNot stated
E-waste commitmentNo
Waste to Wealth

Second life for solar and batteries

Between 2026 and 2040, about 8,600 tonnes of solar equipment and stationary batteries are expected to retire in Namibia, most of it solar panels.

Between 2026 and 2040, about 8,600 tonnes of solar equipment and stationary batteries are expected to retire in Namibia, most of it solar panels. That is 2.1% of the total for the 18 countries in our second-life atlas. Up to 27 MWh of retired batteries could be tested and reused as storage, for example in solar home systems, shops and mini-grids (0.6% of the atlas total). Today the nearest recyclers for panels and lithium batteries are in Gauteng and Cape Town, so most of this waste would travel far and cross borders.

Solar and batteries retiring, 2026-2040 (tonnes)
StreamTonnesShare of country
Solar panels7,91692%
Off-grid solar kits and mini-grids2573%
Batteries3865%
Total8,559100%
Namibia compared with the 18 countries in our second-life atlas, 2026-2040
NamibiaAtlas totalShare
Retiring solar and batteries (tonnes)8,559412,6682.1%
Reusable battery storage (MWh)274,3220.6%
Retiring in 2030 (tonnes)205
Retiring in 2035 (tonnes)443
Retiring in 2040 (tonnes)1,581

From our second-life atlas, central case, by country. Electric vehicle batteries are modeled for the region as a whole, so they are not in these country figures.

Emissions

Grid emission factor

Each megawatt-hour generated in Namibia in 2024 came with about 0.02 tonnes of CO2.

Each megawatt-hour generated in Namibia in 2024 came with about 0.02 tonnes of CO2. Counting imported power, the factor for electricity used in the country is about 0.45 tCO2/MWh, with imports making up 59% of supply. For carbon projects such as solar mini-grids, the combined margin (the usual basis for crediting) is about 0.01 tCO2/MWh. Looking ahead, our scenarios from the plants in the pipeline put the average at 0.07 to 0.10 tCO2/MWh in 2030 and 0.01 to 0.22 in 2035, depending on how many plants arrive on time (see the scenarios). Data quality is rated good. See our grid emission factors for the method and all 38 countries.

Grid mix, 2024. 59% of the electricity used is imported.

Coal 2% Hydro 61% Solar 35% Wind 1%

Air in the city

Satellite-based estimates put fine particulate matter (PM2.5) in Windhoek, the capital, at about 8 µg/m³ on average in 2023, about 2 times the WHO guideline of 5, down from 13 in 2013. The WHO database has no ground measurement for the city. Electric motorbikes and buses cut exhaust where people breathe it; see e-mobility for 71 cities.

Grid emission factor, 2024 (tCO2/MWh)
MeasuretCO2/MWh
Generated in country0.024
Electricity used, with imports0.445
Combined margin (for carbon projects)0.010
Tariffs and load shedding

What power costs here

City of Windhoek (one of several distributors)'s Residential prepaid (PPD) tariff, in force from 1 September 2026.

City of Windhoek (one of several distributors)'s Residential prepaid (PPD) tariff, in force from 1 September 2026. Our utilities, tariffs and load shedding page compares 39 African countries by customer class, with what each tariff includes and load shedding since 2015.

Tariff and load shedding
MeasureValue
Household (single rate)2.4298 NAD/kWh, about US$0.146
Load shedding nowNothing found

Energy charge only, at the central bank rate on 30 October 2026. Check what is included (VAT, levies, fixed charges) on the research page.

Certificates and carbon credits

Renewable energy certificates

Namibia can issue I-RECs, the international renewable energy certificate. 4 plants are registered (19 MW) and 56 GWh of certificates have been issued.

Namibia can issue I-RECs, the international renewable energy certificate. 4 plants are registered (19 MW) and 56 GWh of certificates have been issued. On the voluntary carbon registries it has 7 carbon credit projects, 5 of them issuing, with about 0.5 million credits issued; 4 are renewable energy projects. Check it on the I-REC Standard site. See our certificates page to compare certificates with carbon credits across the region.

Certificates and carbon credits
MeasureValue
I-REC statusIssuing
Registered plants4 (19 MW)
I-RECs issued, all years56 GWh
Carbon credit projects7
Carbon credits issued0.5 million

I-RECs: Xpansiv I-REC Registry statistics, October 2026. Carbon projects: CarbonPlan OffsetsDB (Verra, Gold Standard and other voluntary registries), data to June 2026. Article 6: UNEP Copenhagen Climate Centre Article 6 Pipeline, November 2026.

Reference

Neighbors, sources and updates

Sources 8 sources
  • Grid lines: OpenStreetMap contributors (ODbL), with gap-fill from the World Bank Africa electricity grid (2017).
  • Power plants: Global Energy Monitor, Global Integrated Power Tracker (September 2026), with WRI and curated public project sources.
  • Supply and demand: SAPP monthly report (August 2026).
  • People without night-time light and distance to the grid: WorldPop 2020 and gridfinder (Arderne et al. 2020, CC BY 4.0), as screened in our grid-edge atlas.
  • Retiring solar and batteries: our second-life atlas model (central case, regular losses), from public project registers and IRENA lifetimes.
  • City air: Atmospheric Composition Analysis Group, Washington University in St. Louis (PM2.5 V6.GL.02.04); WHO Ambient Air Quality Database 2026.
  • Emission factors: our grid emission factors (Ember, 2024).
  • Compact commitments: the national Mission 300 energy compact, as quoted page by page on our compacts page.

The maps are free to view. The data behind this page is available on request: email [email protected]. Lines are indicative, not for engineering or investment decisions.

What changed 2 updates

Our data is checked every month, and this page is rebuilt after each check.

  • 16 November 2026 - Latest update to the SAPP grid atlas, which this page is generated from.
  • 16 November 2026 - Monthly check. The Mozambique-Malawi interconnector was energized on 8 August 2026; it stays in commissioning until a tariff deal lets commercial trading start. Source. The Tanzania section of the Tanzania-Zambia interconnector is 92% complete and now due in December 2026, seven months after its May 2026 target. Source. Angola-Namibia (ANNA): implementation agreement signed in April 2026 added to the project history.

Common questions about Namibia

Where can I find a map of Namibia's electricity grid?

The free SAPP grid atlas maps Namibia's high-voltage lines, substations, power plants of 10 MW and above and planned projects. Open it zoomed to Namibia.

How many people in Namibia live without electricity?

About 1.5 million people live where satellites see no electric light at night, a proxy for living without power. Of them, 92% are within 15 km of a power line.

How long is Namibia's transmission network?

About 11,536 km of mapped lines at 66 kV and above, mostly from OpenStreetMap.

How much power generation does Namibia have?

Operating plants of 10 MW and above add up to about 869 MW in our atlas, with about 24,144 MW more under construction or planned.

What is the grid emission factor for Namibia?

About 0.45 tCO2/MWh for electricity used in 2024, and 0.01 tCO2/MWh as a combined margin for carbon projects. See our grid emission factors for the method.

What is Namibia's Mission 300 energy compact target?

Namibia's Mission 300 energy compact commits to raising electricity access from 60% to 70% by 2030. See all compacts side by side on our compacts page.

Can I get the data for Namibia?