Southern African Power Pool
Mozambique electricity grid and access
Mozambique is home to Cahora Bassa, one of Africa's largest hydro plants, and much of its power is exported to neighbors while about 20 million people at home live without night-time light. The country is long, and its grid is thin in places: 74% of people without light live within 15 km of a line, the rest farther out. A planned north-south backbone would join the network end to end, but its date has slipped by years.

Open the live atlas for Mozambique Download the two-page brief (PDF) Ficha em português (PDF) Distribution network map
Free A2 posters of Mozambique’s grid: today and 2035 and beyond (PDF). All posters
Lines, substations and demand
Mozambique's mapped high-voltage network runs to about 9,745 km of lines at 66 kV and above, with 70 substations. The highest voltage on the map is 500 kV, and 50% of the line length runs at 220 kV or more. About 658 km come from older World Bank (2017) maps, used where OpenStreetMap has gaps. In August 2026, SAPP reported a peak demand of 1,085 MW against 2,186 MW available.
| Voltage | km |
|---|---|
| 500 kV | 1,433 |
| 400 kV | 790 |
| 275 kV | 244 |
| 220 kV | 2,054 |
| 132 kV | 12 |
| 110 kV | 3,574 |
| 66 kV | 248 |
| Voltage not recorded | 732 |
| Gap-fill from older public maps | 658 |
| Total | 9,745 |
Who lives near the grid but off it
About 20 million people in Mozambique, roughly 56% of the population, live where satellites see no electric light at night. Of them, 74% live within 15 km of a mapped or predicted power line: 4.1 million within 2 km, 10 million 2 to 15 km away, and 5.0 million farther out. The largest group lives 2 to 15 km out: close enough to plan for the grid, too far for a quick connection. That is where mini-grids built to join the grid later can do the most good. At its 2016-2023 pace, about 1.4 percentage points a year (World Bank), Mozambique would reach the 100% access target in its Mission 300 compact after 2050, not 2030; the target needs about 9.1 points a year.
- Within 2 km: 4.1 million (21%)
- 2 to 15 km: 10 million (53%)
- More than 15 km: 5.0 million (26%)
See the numbers as a table
| Distance | Million people | Share |
|---|---|---|
| Within 2 km of a line | 4.13 | 21% |
| 2 to 15 km | 10.38 | 53% |
| More than 15 km | 5.01 | 26% |
| Total | 19.52 | 100% |
How we count this
"Without night-time light" is a satellite proxy, not a measured access rate. Distances are straight lines to mapped or predicted lines. See the grid-edge atlas for the method.
Power plants and projects
There are 14 operating power plants of 10 MW and above, adding up to about 2,992 MW, 73% of it hydro. The largest is Cahora Bassa hydroelectric plant (2,075 MW, hydro). Another 35 plants totaling about 20,857 MW are under construction or planned, 944 MW of them under construction. Most of the pipeline is solar. One early-stage project, JER Green Hydrogen Solar PV Project (Mozambique), accounts for 58% of that, so the total says more about ambition than about what will be built soon. The largest plant under construction is Temane power station (450 MW, gas).
Three transmission projects touching Mozambique are in our register. The most delayed is Mozambique north-south backbone (Mphanda Nkuwa): 6 years later than first promised, now expected in 2034.
- Mozambique-Malawi interconnector (MoMa) (400 kV): commissioning, expected 2026, 2 years behind the first date.
- Mozambique north-south backbone (Mphanda Nkuwa): structuring, expected 2034, 6 years behind the first date.
- Mozambique-Tanzania interconnector: studies starting.
| Type | Operating MW | Pipeline MW |
|---|---|---|
| Hydro | 2,171 | 3,680 |
| Coal | 300 | |
| Gas | 698 | 3,099 |
| Oil | 12 | |
| Solar | 111 | 13,628 |
| Wind | 150 | |
| Total | 2,992 | 20,857 |
More about Mozambique
Open any topic for the full text and tables.
Mission 300What the energy compact commits to
Mozambique's Mission 300 energy compact commits to raising electricity access from 60% to 100% by 2030. Each value is quoted, with its page, on our compacts page, where compacts sit side by side. Nothing is scored or ranked.
| Commitment | Value |
|---|---|
| Electricity access now | 60% (2024) |
| Access target | 100% by 2030 |
| Clean cooking target | from 17% to 54% by 2030 |
| Private investment sought | US$8.698 billion |
| Rules for mini-grids when the grid arrives | Mentioned only |
| E-waste commitment | No |
Waste to WealthSecond life for solar and batteries
Between 2026 and 2040, about 26,300 tonnes of solar equipment and stationary batteries are expected to retire in Mozambique, most of it off-grid solar kits and mini-grids. That is 6.4% of the total for the 18 countries in our second-life atlas. Up to 7 MWh of retired batteries could be tested and reused as storage, for example in solar home systems, shops and mini-grids (0.2% of the atlas total). Today the nearest recyclers for panels and lithium batteries are in Gauteng and Cape Town, so most of this waste would travel far and cross borders.
| Stream | Tonnes | Share of country |
|---|---|---|
| Solar panels | 2,190 | 8% |
| Off-grid solar kits and mini-grids | 24,039 | 91% |
| Batteries | 58 | 0% |
| Total | 26,287 | 100% |
| Mozambique | Atlas total | Share | |
|---|---|---|---|
| Retiring solar and batteries (tonnes) | 26,287 | 412,668 | 6.4% |
| Reusable battery storage (MWh) | 7 | 4,322 | 0.2% |
| Retiring in 2030 (tonnes) | 1,641 | ||
| Retiring in 2035 (tonnes) | 1,703 | ||
| Retiring in 2040 (tonnes) | 1,887 |
From our second-life atlas, central case, by country. Electric vehicle batteries are modeled for the region as a whole, so they are not in these country figures.
EmissionsGrid emission factor
Each megawatt-hour generated in Mozambique in 2024 came with about 0.09 tonnes of CO2. For carbon projects such as solar mini-grids, the combined margin (the usual basis for crediting) is about 0.10 tCO2/MWh. Looking ahead, our scenarios from the plants in the pipeline put the average at 0.00 to 0.13 tCO2/MWh in 2030 and 0.00 to 0.13 in 2035, depending on how many plants arrive on time (see the scenarios). Data quality is rated fair. See our grid emission factors for the method and all 38 countries.
Grid mix, 2024.
Gas 16% Oil and diesel 1% Hydro 82% Bioenergy 1%
Air in the city
Satellite-based estimates put fine particulate matter (PM2.5) in Maputo, the capital, at about 13 µg/m³ on average in 2023, about 3 times the WHO guideline of 5, about the same as 13 in 2013. On OpenAQ, 4 low-cost sensors in and around the city averaged about 29 over the 12 months to October 2026. Electric motorbikes and buses cut exhaust where people breathe it; see e-mobility for 71 cities.
| Measure | tCO2/MWh |
|---|---|
| Generated in country | 0.086 |
| Electricity used, with imports | 0.086 |
| Combined margin (for carbon projects) | 0.100 |
Tariffs and load sheddingWhat power costs here
EDM's Domestic tariff, in force from 1 March 2019. Our utilities, tariffs and load shedding page compares 39 African countries by customer class, with what each tariff includes and load shedding since 2015.
| Measure | Value |
|---|---|
| Lifeline or first block (0-125 kWh/month) | 1.07 MZN/kWh, about US$0.017 |
| Household (0-300 kWh/month) | 6.63 MZN/kWh, about US$0.103 |
| Load shedding now | None found (maintenance cuts only) |
Energy charge only, at the central bank rate on 30 October 2026. Check what is included (VAT, levies, fixed charges) on the research page.
Certificates and carbon creditsRenewable energy certificates
Mozambique cannot issue I-RECs, the international renewable energy certificate, yet. On the voluntary carbon registries it has 96 carbon credit projects, 47 of them issuing, with about 4.1 million credits issued; 3 are renewable energy projects. Under the Paris Agreement it has 1 activity approved for the UN's new crediting mechanism. See our certificates page to compare certificates with carbon credits across the region.
| Measure | Value |
|---|---|
| I-REC status | Not approved |
| Registered plants | - |
| I-RECs issued, all years | - |
| Carbon credit projects | 96 |
| Carbon credits issued | 4.1 million |
I-RECs: Xpansiv I-REC Registry statistics, October 2026. Carbon projects: CarbonPlan OffsetsDB (Verra, Gold Standard and other voluntary registries), data to June 2026. Article 6: UNEP Copenhagen Climate Centre Article 6 Pipeline, November 2026.
Neighbors, sources and updates
Neighboring countries
Tanzania Malawi Zambia Zimbabwe South Africa Eswatini
More in the SAPP grid atlas, grid-edge atlas, second-life atlas, grid emission factors and Mission 300 compacts, or see all countries.
Sources 8 sources
- Grid lines: OpenStreetMap contributors (ODbL), with gap-fill from the World Bank Africa electricity grid (2017).
- Power plants: Global Energy Monitor, Global Integrated Power Tracker (September 2026), with WRI and curated public project sources.
- Supply and demand: SAPP monthly report (August 2026).
- People without night-time light and distance to the grid: WorldPop 2020 and gridfinder (Arderne et al. 2020, CC BY 4.0), as screened in our grid-edge atlas.
- Retiring solar and batteries: our second-life atlas model (central case, regular losses), from public project registers and IRENA lifetimes.
- City air: Atmospheric Composition Analysis Group, Washington University in St. Louis (PM2.5 V6.GL.02.04); WHO Ambient Air Quality Database 2026; OpenAQ (sensor data, November 2025 to October 2026).
- Emission factors: our grid emission factors (Ember, 2024).
- Compact commitments: the national Mission 300 energy compact, as quoted page by page on our compacts page.
The maps are free to view. The data behind this page is available on request: email [email protected]. Lines are indicative, not for engineering or investment decisions.
What changed 5 updates
Our data is checked every month, and this page is rebuilt after each check.
- 16 November 2026 - Latest update to the SAPP grid atlas, which this page is generated from.
- 16 November 2026 - Monthly check. The Mozambique-Malawi interconnector was energized on 8 August 2026; it stays in commissioning until a tariff deal lets commercial trading start. Source. The Tanzania section of the Tanzania-Zambia interconnector is 92% complete and now due in December 2026, seven months after its May 2026 target. Source. Angola-Namibia (ANNA): implementation agreement signed in April 2026 added to the project history.
- Aug 2026 - Mozambique-Malawi interconnector (MoMa): Final testing reported, now expected 2026.
- Sep 2026 - Mozambique-Malawi interconnector (MoMa): Ministry of Energy, Malawi, now expected 2026; energized 8 Aug 2026, commercial trading awaits tariff agreement.
- Jul 2026 - Mozambique north-south backbone (Mphanda Nkuwa): Implementation Office update, now expected 2034.
Common questions about Mozambique
Where can I find a map of Mozambique's electricity grid?
The free SAPP grid atlas maps Mozambique's high-voltage lines, substations, power plants of 10 MW and above and planned projects. Open it zoomed to Mozambique.
How many people in Mozambique live without electricity?
About 20 million people live where satellites see no electric light at night, a proxy for living without power. Of them, 74% are within 15 km of a power line.
How long is Mozambique's transmission network?
About 9,745 km of mapped lines at 66 kV and above, mostly from OpenStreetMap, with older public maps filling gaps.
How much power generation does Mozambique have?
Operating plants of 10 MW and above add up to about 2,992 MW in our atlas, with about 20,857 MW more under construction or planned.
What is the grid emission factor for Mozambique?
About 0.09 tCO2/MWh for electricity used in 2024, and 0.10 tCO2/MWh as a combined margin for carbon projects. See our grid emission factors for the method.
What is Mozambique's Mission 300 energy compact target?
Mozambique's Mission 300 energy compact commits to raising electricity access from 60% to 100% by 2030. See all compacts side by side on our compacts page.
Can I get the data for Mozambique?
Yes, on request. The maps are free to view; email [email protected] and tell us what you need it for.