Regional reports

Central African Power Pool

CAPP regional report

The Central African Power Pool (CAPP) side by side: power plants and lines, the generation mix, Mission 300 compacts, prices, carbon, access, drought risk, storage and waste for each country, with a pool total. About 227 million people live in the 10 countries in our data; our atlases map about 14,949 MW of operating plants and 20,365 MW more planned or under construction.

10countries in our data
146 Mpeople live without night-time light, a proxy for no power
62%of them live within 15 km of a power line
14,949MW of operating power plants, 10 MW and above
8countries with a Mission 300 compact in our data

Download the regional report (PDF, 0.4 MB, November 2026) Rapport régional en français (PDF, novembre 2026) Relatório regional em português (PDF, novembro de 2026) Open the CAPP grid atlas

Formed in 2003, it brings together ten ECCAS countries. Angola, Burundi and DR Congo are also members of SAPP or EAPP, so they appear in those reports too.

Grid and generation

Power plants, lines and the generation mix

Across the 10 CAPP countries in our data, our atlases map about 14,949 MW of operating power plants of 10 MW and above (hydro 64%, gas 15%, oil and diesel 9%), about 3,135 MW under construction and about 17,230 MW more planned. Hydro is the largest source in 4 of the 10 countries.

The mapped high-voltage network runs to about 24,040 km of lines.

Power plants and lines by country
CountryOperating (MW)Largest sourceUnder construction (MW)Planned (MW)Lines (km)Top voltageSubstations
Angola6,329Hydro (64%)2,1975,3157,023400 kV56
Burundi224Hydro (51%)00480220 kV9
Cameroon2,053Hydro (68%)205,7402,692220 kV18
Central African Republic119Oil and diesel (42%)50225151110 kV2
Chad266Oil and diesel (57%)6052015688 kV8
DR Congo3,884Hydro (84%)3983,6019,846500 kV142
Equatorial Guinea338Gas (64%)20001,208220 kV15
Gabon868Gas (60%)160862622220 kV13
Republic of the Congo843Gas (63%)509571,856220 kV23
São Tomé and Príncipe26Oil and diesel (57%)0108-0
CAPP total14,949Hydro (64%)3,13517,23024,040286
Generation mix by country
Angola
Burundi
Cameroon
Central African Republic
Chad
DR Congo
Equatorial Guinea
Gabon
Republic of the Congo
São Tomé and Príncipe
CAPP total
CoalGasOil and dieselNuclearHydroSolarWindGeothermal, bioenergy and other
Electricity generation by source, 2024
CountryGeneration (TWh)CoalGasOil and dieselNuclearHydroSolarWindGeothermal, bioenergy and other
Angola15.6-9%17%-71%3%--
Burundi0.5--24%-73%--2%
Cameroon7.3-22%5%-72%1%-1%
Central African Republic0.1----100%---
Chad0.4--95%---3%3%
DR Congo15.9----84%16%--
Equatorial Guinea1.5-72%1%-27%---
Gabon2.6-44%20%-35%---
Republic of the Congo5.5-74%5%-20%--1%
São Tomé and Príncipe0.1--89%-11%---
CAPP total49.4-19%9%-66%6%--
Capacity and peak demand, latest published
CountryCapacity (MW)Peak demand (MW)As of
Angola6,3822,186Oct 2022
Burundi166-2025
Cameroon2,011-2025
Central African Republic98-Sep 2026 (GEM)
Chad487-2025
DR Congo1,6502,379August 2026
Equatorial Guinea343-Sep 2026 (GEM)
Gabon852-Sep 2026 (GEM)
Republic of the Congo748-2025
São Tomé and Príncipe12-Sep 2026 (GEM)
Cross-border line projects we track: 2 completed, 4 under construction, 12 in preparation
CountriesVoltageStatusYear
Rwanda-Burundi-Tanzania220 kVCompleted2024
Republic of the Congo-DR Congo220 kVCompleted-
Rwanda-Burundi220 kVUnder construction2027 (expected)
Rwanda-DR Congo220 kVUnder construction2027 (expected)
Burundi-DR Congo220 kVUnder construction2028 (expected)
Cameroon-Chad225 kVUnder construction2030 (expected)
Angola-Namibia400 kVIn preparation2029 (expected)
DR Congo-Rwanda-Burundi220 kVIn preparation2030 (expected)
Uganda-DR Congo220 kVIn preparation2030 (expected)
Cameroon-Republic of the Congo225 kVIn preparation2032 (expected)
Gabon-Republic of the Congo400 kVIn preparation2032 (expected)
Republic of the Congo-Angola400 kVIn preparation2032 (expected)
Cameroon-Gabon-Equatorial Guinea-In preparation2033 (expected)
Angola-DR Congo-In preparation-
Angola-Namibia400 kVIn preparation-
DR Congo-Angola-In preparation-
Zambia-Angola-In preparation-
Zambia-DR Congo330 kVIn preparation-

Capacity is what the country or CAPP reports (available capacity in the SAPP monthly report, installed capacity elsewhere); it is not the same as our mapped plants. GEM marks the plant total from Global Energy Monitor where no national figure is published. The project table lists lines in our project tracker; older interconnectors are on the atlas and the interconnector limits page. Every plant and line: the CAPP grid atlas.

Mission 300 compacts compared

What the compacts say, side by side

8 of the 10 CAPP countries in our data have published a Mission 300 national energy compact. Together they seek about US$32.9 billion of private investment by 2030. 1 set out how to handle e-waste from solar kits and batteries, and 5 say what happens to mini-grids when the main grid arrives.

No compact in our data: Angola, Equatorial Guinea.

Set the split beside the access section below, which shows where the people without power live by distance to a mapped line: a compact that relies on the grid fits a country where most of them live within 2 km.

Access targets and how they are split
CountryAccess nowTargetGridMini-gridStandaloneWhat the split measures
Burundi25.9% in 202570% by 203060%13%27%Share of new connections
Cameroon74% in 2025100% by 2030---Not stated
Central African Republic16.8% in 202450% by 203044%32%23%Share of new connections
Chad11% in None90% by 203050%20%20%Share of people with access
DR Congo21.5% in 202462% by 203044%56%0%Share of new connections
Gabon92.7% in 202395% by 2030---Not split
Republic of the Congo31.7% in None81% by 2030-10%90%Share of people with access
São Tomé and Príncipe84% in 2024100% by 2030---Not stated
What each compact commits to
CountryProductive useE-wasteLeast-cost or GIS planMini-grid rules when the grid arrivesCost-reflective tariffPrivate investment sought (US$ billion)
BurundiMentionedYesExistsYesCommitted1.5
CameroonMentionedMentionedPlannedYesCommitted5.9
Central African RepublicMentionedNoExistsMentionedCommitted0.5
ChadMentionedNoPlannedYesMentioned1.3
DR CongoMentionedNoExistsYesCommitted20
GabonMentionedNoPlannedYesCommitted2.0
Republic of the CongoMentionedNoPlannedNot statedCommitted1.4
São Tomé and PríncipeYesNoExistsMentionedCommitted0.2

Read from each compact document, with page numbers and quotes for every value: Mission 300 compacts compared. "Not stated" means the compact does not say.

Prices

What power costs across the pool

Household tariffs are the energy charge at the central bank exchange rate; check on the tariffs page what each includes. Our power price data holds 5 deals in CAPP countries, from auctions, signed power purchase agreements and published bids.

Household tariffs and load shedding
CountryUtilityHousehold (US$/kWh)Lifeline or first block (US$/kWh)Load shedding
AngolaENDE0.0150.004No data
BurundiREGIDESO0.0460.023Cuts reported
CameroonEneo Cameroon0.1350.085Not confirmed this month
Central African Republic---Cuts reported
Chad---Not confirmed this month
DR CongoSNEL0.0890.039Cuts reported
Equatorial Guinea---None reported
Gabon---Not confirmed this month
Republic of the CongoEnergie Electrique du Congo (E2C)0.084-Not confirmed this month
São Tomé and Príncipe---Not confirmed this month
Power deals signed or bid in the pool, US$/MWh as signed
SourceDealsMedianLowestHighest
Hydro3714572
Diesel and fuel oil1321--
Solar PV1142--

Every tariff and status with its source: utilities, tariffs and load shedding. Every deal with its source: power prices and deals. Load shedding is grouped from the status we last read for each country.

Carbon

Grid carbon and carbon markets

2 of the 10 CAPP countries in our data issue I-REC renewable energy certificates, about 0.0 TWh to date. The grid factor is the average CO2 per MWh of electricity used; a low factor means grid power, electric transport and new grid connections add little CO2.

Grid carbon, certificates and carbon markets
CountryGrid factor (tCO2/MWh)YearI-REC certificatesIssued to date (GWh)Article 6 deals and activitiesNet CO2 avoided by new connections (t a year)
Angola0.1772024Not approved-0-18,122
Burundi0.1612024Approved, none issued-0-19,931
Cameroon0.1502024Not approved-0-25,241
Central African Republic0.0002023Not approved-08,046
Chad0.7212024Issuing20-318,030
DR Congo0.0612024Issuing110174,106
Equatorial Guinea0.3712024Not approved-0-
Gabon0.3852024Not approved-15,008
Republic of the Congo0.4132024Not approved-0-68,976
São Tomé and Príncipe0.6772023Not approved-0-272

Methods: grid emission factors, clean energy certificates and carbon per connection (central case, new connections to 2030 under each compact or national target). A negative value means the new connections add CO2 on net, because the grid power they use emits more than the kerosene and diesel they replace.

Access

Who lives near the grid but not on it

About 146 million people in the CAPP countries in our data live where satellites see no electric light at night, out of about 227 million. 62% of them live within 15 km of a mapped power line, and 28% within 2 km, close enough for a grid connection to be the obvious first step.

Satellites also see 1,065 lit places 2 km or more from any mapped line: missing lines, mines and plants with their own power, or mini-grids.

People without power and how far they live from the grid
CountryPeople (million)Without night light (million)Within 2 km of a line2 to 15 kmBeyond 15 kmMedian distance (km)Lit places off the map
Angola381626%47%27%7.2315
Burundi141033%66%1%3.545
Cameroon291529%36%35%7.0219
Central African Republic5.33.516%11%73%77.146
Chad201515%26%59%32.7121
DR Congo1098330%30%40%7.7160
Equatorial Guinea1.90.470%30%0%0.527
Gabon2.50.352%31%17%1.475
Republic of the Congo6.31.439%35%26%4.654
São Tomé and Príncipe0.20.076%14%10%0.53
CAPP total22714628%34%38%1,065

Night-time light is a proxy for no power, not a household survey. Map and method: the grid-edge atlas.

Risk, storage and waste

Drought, battery sites, waste and second life

A dry year that takes a fifth of hydro output would cost the CAPP countries about 773 MW on average over the year, and a severe drought (two fifths) about 1,550 MW. 15 coal, gas and oil plant sites with about 2,594 MW of grid connection could host batteries as they close. Waste could fuel about 513 MW of power, and about 25,674 t of solar panels, kits and batteries will reach end of life from 2026 to 2040.

Drought risk, storage sites, waste and second life
CountryHydro in operating plantsDry year, MW lostSevere drought, MW lostThermal plant sites for batteries (MW)Power from waste (MW)Solar and battery waste 2026-2040 (t)Second-life panel demand (MWp)
Angola63%2785569291006,7544,012
Burundi51%714-101,214656
Cameroon68%1192393641474,0171,412
Central African Republic23%375029753388
Chad---67191,407879
DR Congo84%302605-12410,4055,416
Equatorial Guinea36%10201544204157
Gabon38%295849650314117
Republic of the Congo28%255153430606999
São Tomé and Príncipe----1-19
CAPP total7731,5502,59451325,67414,056

Methods: hydro and drought, power plant to battery site, power from waste and the second-life atlas. Central cases throughout.

Country pages

Every country in this report

Each country page has the detail behind these tables and its own country report to download.

Angola Burundi Cameroon Central African Republic Chad DR Congo Equatorial Guinea Gabon Republic of the Congo São Tomé and Príncipe

Other power pools: SAPP EAPP WAPP

Sources and method

  • Plants and lines: our grid atlases (Global Energy Monitor, WRI, OpenStreetMap, World Bank and national sources). Generation mix: Ember. Capacity and peak demand: SAPP monthly report and national regulators and utilities.
  • Compacts: the published Mission 300 national energy compacts and World Bank compact progress reports. Distances: our grid-edge atlas.
  • Tariffs and load shedding: utility tariff books, regulators and news reports (Utilities and Tariffs data). Deals: auction results, regulators, utilities and trade press (power prices data).
  • Grid factors: Ember and national data, in our grid emission factors. Certificates: the I-REC registry (Evident). Article 6: UNEP-CCC Article 6 pipeline.
  • Access: WorldPop population, NASA Black Marble night lights, Google Open Buildings and our mapped lines (grid-edge atlas).
  • Hydro: our grid atlases and Ember. Thermal sites: Global Energy Monitor (September 2026). Waste: FAOSTAT, Global Energy Monitor and OpenStreetMap. Second life: IRENA, compact targets and our second-life atlas.

Rows run in alphabetical order. These are side-by-side facts, not scores or rankings. A dash means we hold no data for that country. Pool totals count member countries only. Rebuilt every month with the country reports. Free to share under CC BY 4.0.