SAPP regional report

The Southern African Power Pool (SAPP) side by side: power plants and lines, the generation mix, Mission 300 compacts, prices, carbon, access, drought risk, storage and waste for each country, with a pool total. About 383 million people live in the 12 countries in our data; our atlases map about 97,331 MW of operating plants and 155,422 MW more planned or under construction.

12countries in our data
202 Mpeople live without night-time light, a proxy for no power
74%of them live within 15 km of a power line
97,331MW of operating power plants, 10 MW and above
9countries with a Mission 300 compact in our data

Download the regional report (PDF, 0.4 MB, November 2026) Rapport régional en français (PDF, novembre 2026) Relatório regional em português (PDF, novembro de 2026) Open the SAPP grid atlas

Formed in 1995, it brings together the twelve mainland SADC countries. It runs a competitive day-ahead power market.

Grid and generation

Power plants, lines and the generation mix

Across the 12 SAPP countries in our data, our atlases map about 97,331 MW of operating power plants of 10 MW and above (coal 51%, hydro 24%, solar 9%), about 20,201 MW under construction and about 135,221 MW more planned. Hydro is the largest source in 8 of the 12 countries.

The mapped high-voltage network runs to about 163,501 km of lines.

Power plants and lines by country
CountryOperating (MW)Largest sourceUnder construction (MW)Planned (MW)Lines (km)Top voltageSubstations
Angola6,329Hydro (64%)2,1975,3157,023400 kV56
Botswana1,012Coal (72%)7004,5857,808400 kV64
DR Congo3,884Hydro (84%)3983,6019,846500 kV142
Eswatini202Biomass (47%)05741,113400 kV18
Lesotho102Hydro (71%)0340636132 kV24
Malawi565Hydro (62%)4311,4762,700400 kV40
Mozambique2,992Hydro (73%)94419,9139,745500 kV70
Namibia869Solar (41%)7,41716,72711,536400 kV60
South Africa67,042Coal (69%)4,35249,60482,409765 kV2,411
Tanzania3,870Hydro (75%)4028,1489,206400 kV64
Zambia5,993Hydro (71%)1,96013,31313,477330 kV169
Zimbabwe4,473Hydro (48%)1,40011,6268,003400 kV81
SAPP total97,331Coal (51%)20,201135,221163,5013,199
Generation mix by country
Angola
Botswana
DR Congo
Eswatini
Lesotho
Malawi
Mozambique
Namibia
South Africa
Tanzania
Zambia
Zimbabwe
SAPP total
CoalGasOil and dieselNuclearHydroSolarWindGeothermal, bioenergy and other
Electricity generation by source, 2024
CountryGeneration (TWh)CoalGasOil and dieselNuclearHydroSolarWindGeothermal, bioenergy and other
Angola15.6-9%17%-71%3%--
Botswana3.498%-1%-----
DR Congo15.9----84%16%--
Eswatini0.63%---57%5%-34%
Lesotho0.5----99%1%--
Malawi1.8--4%-92%1%-3%
Mozambique19.8-16%1%-82%--1%
Namibia1.62%---61%35%1%-
South Africa247.684%-1%3%-7%4%-
Tanzania8.8-63%4%-32%--1%
Zambia13.618%-3%-79%1%--
Zimbabwe10.343%---56%--1%
SAPP total339.664%3%2%2%19%7%3%-
Capacity and peak demand, latest published
CountryCapacity (MW)Peak demand (MW)As of
Angola6,3822,186Oct 2022
Botswana475698August 2026
DR Congo1,6502,379August 2026
Eswatini60229August 2026
Lesotho76206August 2026
Malawi580452Aug 2026
Mozambique2,1861,085August 2026
Namibia490672August 2026
South Africa32,51027,582August 2026
Tanzania3,0921,9442025
Zambia3,1292,734August 2026
Zimbabwe1,5051,693August 2026
Cross-border line projects we track: 3 completed, 3 under construction, 14 in preparation
CountriesVoltageStatusYear
Kenya-Tanzania400 kVCompleted2024
Rwanda-Burundi-Tanzania220 kVCompleted2024
Republic of the Congo-DR Congo220 kVCompleted-
Mozambique-Malawi400 kVUnder construction2026 (expected)
Rwanda-DR Congo220 kVUnder construction2027 (expected)
Burundi-DR Congo220 kVUnder construction2028 (expected)
Angola-Namibia400 kVIn preparation2029 (expected)
Uganda-Tanzania400 kVIn preparation2029 (expected)
DR Congo-Rwanda-Burundi220 kVIn preparation2030 (expected)
Malawi-Zambia400 kVIn preparation2030 (expected)
Uganda-DR Congo220 kVIn preparation2030 (expected)
Zimbabwe-Zambia-Botswana-Namibia330 kVIn preparation2030 (expected)
Republic of the Congo-Angola400 kVIn preparation2032 (expected)
Angola-DR Congo-In preparation-
Angola-Namibia400 kVIn preparation-
Botswana-Namibia-In preparation-
DR Congo-Angola-In preparation-
Mozambique-Tanzania-In preparation-
Zambia-Angola-In preparation-
Zambia-DR Congo330 kVIn preparation-

Capacity is what the country or SAPP reports (available capacity in the SAPP monthly report, installed capacity elsewhere); it is not the same as our mapped plants. GEM marks the plant total from Global Energy Monitor where no national figure is published. The project table lists lines in our project tracker; older interconnectors are on the atlas and the interconnector limits page. Every plant and line: the SAPP grid atlas.

Mission 300 compacts compared

What the compacts say, side by side

9 of the 12 SAPP countries in our data have published a Mission 300 national energy compact. Together they seek about US$50.2 billion of private investment by 2030. 1 set out how to handle e-waste from solar kits and batteries, and 3 say what happens to mini-grids when the main grid arrives.

No compact in our data: Angola, Eswatini, South Africa.

Set the split beside the access section below, which shows where the people without power live by distance to a mapped line: a compact that relies on the grid fits a country where most of them live within 2 km.

Access targets and how they are split
CountryAccess nowTargetGridMini-gridStandaloneWhat the split measures
Botswana76.6% in 2025100% by 2030---Not split
DR Congo21.5% in 202462% by 203044%56%0%Share of new connections
Lesotho53% in 2024100% by 203058%2%40%Share of new connections
Malawi25.9% in 202370% by 203030.1%2.6%37.4%Share of people with access
Mozambique60.1% in 2024100% by 2030---Not split
Namibia59.5% in 202370% by 2030---Not split
Tanzania46% in 202275% by 2030---Not split
Zambia53.6% in 2023100% by 203045%10%45%Share of new connections
Zimbabwe41% in 2024100% by 203062%1%38%Share of new connections
What each compact commits to
CountryProductive useE-wasteLeast-cost or GIS planMini-grid rules when the grid arrivesCost-reflective tariffPrivate investment sought (US$ billion)
BotswanaMentionedNoPlannedMentionedCommittedNot stated
DR CongoMentionedNoExistsYesCommitted20
LesothoYesNoExistsMentionedCommitted1.5
MalawiMentionedYesExistsMentionedCommitted1.6
MozambiqueMentionedNoExistsMentionedCommitted8.7
NamibiaMentionedNoExistsNot statedCommitted0.4
TanzaniaMentionedNoExistsMentionedCommitted4.0
ZambiaMentionedMentionedExistsYesCommitted9.5
ZimbabweMentionedNoExistsYesCommitted4.4

Read from each compact document, with page numbers and quotes for every value: Mission 300 compacts compared. "Not stated" means the compact does not say.

Prices

What power costs across the pool

Household tariffs are the energy charge at the central bank exchange rate; check on the tariffs page what each includes. Our power price data holds 25 deals in SAPP countries, from auctions, signed power purchase agreements and published bids.

The SAPP day-ahead market cleared at an average of 5.6 US cents per kWh in August 2026.

Household tariffs and load shedding
CountryUtilityHousehold (US$/kWh)Lifeline or first block (US$/kWh)Load shedding
AngolaENDE0.0150.004No data
BotswanaBotswana Power Corporation (BPC)0.1160.056Cuts reported
DR CongoSNEL0.0890.039Cuts reported
EswatiniEswatini Electricity Company (EEC)0.1720.094No data
LesothoLesotho Electricity Company (LEC)0.1250.056No data
MalawiESCOM0.0700.046Cuts reported
MozambiqueEDM0.1030.017None reported
NamibiaCity of Windhoek0.146-No data
South AfricaEskom0.1680.141None reported
TanzaniaTANESCO0.1110.038None reported
ZambiaZESCO0.0490.017Not confirmed this month
ZimbabweZETDC0.1600.080Cuts reported
Power deals signed or bid in the pool, US$/MWh as signed
SourceDealsMedianLowestHighest
Solar PV7692590
Coal56859110
Hydro535684
Diesel and fuel oil2380260500
Gas2162105220
Battery storage1120--
Imports across a border1170--
Mixed dispatchable bids1106--
Wind134--

Every tariff and status with its source: utilities, tariffs and load shedding. Every deal with its source: power prices and deals. Load shedding is grouped from the status we last read for each country.

Carbon

Grid carbon and carbon markets

5 of the 12 SAPP countries in our data issue I-REC renewable energy certificates, about 19.9 TWh to date. The grid factor is the average CO2 per MWh of electricity used; a low factor means grid power, electric transport and new grid connections add little CO2.

Grid carbon, certificates and carbon markets
CountryGrid factor (tCO2/MWh)YearI-REC certificatesIssued to date (GWh)Article 6 deals and activitiesNet CO2 avoided by new connections (t a year)
Angola0.1772024Not approved-0-18,122
Botswana0.9052024Approved, none issued-0-39,865
DR Congo0.0612024Issuing110174,106
Eswatini0.4732024Not approved-0409
Lesotho0.3642024Approved, none issued-044,562
Malawi0.0332024Not approved-623,728
Mozambique0.0862024Not approved-0-14,448
Namibia0.4452024Issuing5601,587
South Africa0.8192024Issuing15,8660-382,290
Tanzania0.3582024Not approved-4-441,814
Zambia0.1902024Issuing816-23,373
Zimbabwe0.4652024Issuing3,8612-202,777

Methods: grid emission factors, clean energy certificates and carbon per connection (central case, new connections to 2030 under each compact or national target). A negative value means the new connections add CO2 on net, because the grid power they use emits more than the kerosene and diesel they replace.

Access

Who lives near the grid but not on it

About 202 million people in the SAPP countries in our data live where satellites see no electric light at night, out of about 383 million. 74% of them live within 15 km of a mapped power line, and 29% within 2 km, close enough for a grid connection to be the obvious first step.

Satellites also see 10,319 lit places 2 km or more from any mapped line: missing lines, mines and plants with their own power, or mini-grids.

People without power and how far they live from the grid
CountryPeople (million)Without night light (million)Within 2 km of a line2 to 15 kmBeyond 15 kmMedian distance (km)Lit places off the map
Angola381626%47%27%7.2315
Botswana2.50.332%52%15%4.1316
DR Congo1098330%30%40%7.7160
Eswatini1.20.372%28%0%0.9169
Lesotho2.31.132%56%12%3.745
Malawi221535%63%2%3.2284
Mozambique352021%53%26%7.4559
Namibia3.01.544%49%8%2.5250
South Africa646.353%45%2%1.95,490
Tanzania693526%59%15%4.61,756
Zambia211231%54%15%4.5109
Zimbabwe171228%61%11%4.5866
SAPP total38320229%45%26%10,319

Night-time light is a proxy for no power, not a household survey. Map and method: the grid-edge atlas.

Risk, storage and waste

Drought, battery sites, waste and second life

A dry year that takes a fifth of hydro output would cost the SAPP countries about 1,659 MW on average over the year, and a severe drought (two fifths) about 3,322 MW. 50 coal, gas and oil plant sites with about 57,917 MW of grid connection could host batteries as they close. Waste could fuel about 1,328 MW of power, and about 356,556 t of solar panels, kits and batteries will reach end of life from 2026 to 2040.

Drought risk, storage sites, waste and second life
CountryHydro in operating plantsDry year, MW lostSevere drought, MW lostThermal plant sites for batteries (MW)Power from waste (MW)Solar and battery waste 2026-2040 (t)Second-life panel demand (MWp)
Angola63%2785569291006,7544,012
Botswana---80223,963182
DR Congo84%302605-12410,4055,416
Eswatini35%715-8823998
Lesotho71%1123-147690
Malawi62%3977-562,630728
Mozambique73%3667326587026,3391,153
Namibia24%234712076,33071
South Africa5%5410852,379538274,3642,495
Tanzania68%661318041776,3583,562
Zambia65%3827654059213,3061,551
Zimbabwe32%1312631,820735,392786
SAPP total1,6593,32257,9171,328356,55620,144

Methods: hydro and drought, power plant to battery site, power from waste and the second-life atlas. Central cases throughout.

Country pages

Every country in this report

Each country page has the detail behind these tables and its own country report to download.

Angola Botswana DR Congo Eswatini Lesotho Malawi Mozambique Namibia South Africa Tanzania Zambia Zimbabwe

Other power pools: EAPP WAPP CAPP

Sources and method

  • Plants and lines: our grid atlases (Global Energy Monitor, WRI, OpenStreetMap, World Bank and national sources). Generation mix: Ember. Capacity and peak demand: SAPP monthly report and national regulators and utilities.
  • Compacts: the published Mission 300 national energy compacts and World Bank compact progress reports. Distances: our grid-edge atlas.
  • Tariffs and load shedding: utility tariff books, regulators and news reports (Utilities and Tariffs data). Deals: auction results, regulators, utilities and trade press (power prices data).
  • Grid factors: Ember and national data, in our grid emission factors. Certificates: the I-REC registry (Evident). Article 6: UNEP-CCC Article 6 pipeline.
  • Access: WorldPop population, NASA Black Marble night lights, Google Open Buildings and our mapped lines (grid-edge atlas).
  • Hydro: our grid atlases and Ember. Thermal sites: Global Energy Monitor (September 2026). Waste: FAOSTAT, Global Energy Monitor and OpenStreetMap. Second life: IRENA, compact targets and our second-life atlas.

Rows run in alphabetical order. These are side-by-side facts, not scores or rankings. A dash means we hold no data for that country. Pool totals count member countries only. Rebuilt every month with the country reports. Free to share under CC BY 4.0.